Shutterstock_73059598.jpg

Operation of the Election Doctrine Under the CDA

The Contract Disputes Act (CDA) provides contractors with alternate forums to resolve claims relating to their federal contracts. After submitting their claim to the contracting officer (CO) and either receiving a denial or a deemed denial on their claim, contractors may appeal the CO’s final decision to either an appropriate Board of Contract Appeals (BCA) or the Court of Federal Claims (COFC). However, once the contractor elects one of the two dispute adjudicative forums and appeals the CO’s adverse decision after receiving notice of the available options, it may not then change forums. Also known as the election doctrine, this rule ensures that once the contractor chooses the forum in which to lodge its appeal under the CDA, it is bound by the election decision and may no longer pursue its appeal in the alternate forum. For the doctrine to apply, the contractor must make an informed, knowing, and voluntary decision to pursue the appeal in one of the two forums with jurisdiction. Once the action is filed in one forum, the other forum must dismiss any subsequently filed appeals concerning the same claim for lack of jurisdiction.

In a 2015 case, the COFC dismissed a contractor’s lawsuit based on the election doctrine as the contractor had previously pursued an appeal on the same claim at the Armed Services Board of Contract Appeals (ASBCA). The contractor was awarded an indefinite-quantity type contract to provide hydraulic and lube oil flushing services on Navy vessels located within a 50-mile radius of San Diego. When the contractor did not receive the anticipated amount of fixed-price delivery orders, it submitted claims to the CO, including a claim for lost profits. After the CO denied the claims in their entirety, the contractor filed an appeal with the ASBCA, making various allegations, including that the awarded contract was a requirements-type contract under which the Navy was essentially obligated to order all flushing services on Navy vessels located within a 50-mile radius of San Diego from the contractor. The ASBCA dismissed the contractor’s appeal for failing to state a claim upon which relief could be granted, ruling that since the contractor was awarded an indefinite-quantity contract, the Navy was not prohibited from ordering the flushing services from other contractors.

Following the Board’s dismissal, the contractor filed a pro se appeal at the Federal Circuit. The Federal Circuit dismissed the appeal for the contractor’s failure to pay the docketing fee and a failure to file the required entry of appearance form by an attorney admitted to the court’s bar. The court later denied a motion for reconsideration on the same grounds. Subsequently, the owner of the contracting company filed a complaint with the Court of Federal Claims (COFC) as a pro se litigant representing the contractor. The COFC ruled that not only was the plaintiff unable to represent the contractor pro se, but it was also precluded from pursuing the lawsuit at the COFC under the CDA’s election doctrine. The COFC ruled that the contractor’s decision to initially appeal the CO’s final decision on the same claim at the ASBCA foreclosed the contractor and its owner’s ability to file suit at the COFC. The court noted that the CDA gave contractors ninety days to appeal a CO’s adverse final decision to a relevant agency Board. Alternatively, in lieu of appealing the CO’s adverse decision to an agency Board, the contractor could bring an action under the CDA directly before the COFC within twelve months of the final decision. Thus, while the CDA offered the contractor a choice between the two forums to appeal the adverse final decision, once the contractor made an informed, knowing, and voluntary decision to elect a forum, the contractor was precluded from filing the same action in the alternate forum.

The CDA provides contractors with an exclusive mechanism for dispute resolution. Under that dispute resolution mechanism, contractors can choose between two alternate forums to appeal the CO’s adverse final decision. However, contractors should be mindful that once they file their appeal with a BCA or the COFC, the election doctrine, which is built into the CDA, operates to preclude them from filing an appeal on the same claim under the same contract in the alternate forum. Thus, contractors should carefully weigh the pros and cons of each forum in the context of their overall litigation strategy before selecting the appropriate forum to file their appeal. Notably, the election doctrine is inapplicable in cases where the forum initially selected by the contractor does not have jurisdiction over the appeal at the time of filing. Consequently, contractors may file an appeal or a suit in the alternate forum if the initially selected forum dismisses their matter for lack of jurisdiction. In such a scenario, contractors should still be able to meet the alternate forum’s statutory deadlines for filing the action. Finally, it is also worth noting that the election doctrine does not preclude contractors from filing suit at the COFC after filing an untimely appeal at a BCA.

This Federal Contract Claims Insight is provided as a general summary of the applicable law in the practice area and does not constitute legal advice. Contractors wishing to learn more are encouraged to consult the TILLIT LAW PLLC Client Portal or Contact Us to determine how the law would apply in a specific situation.

Related Insights

TLF-Contract-Claims-Insight-57.jpg

Once a contractor submits a claim to the government under the Contract Disputes Act (CDA), the government is required to provide it a copy of the contracting officer’s final decision (COFD). The receipt of the COFD by the contractor is a key event in the lifecycle of a CDA claim because it triggers the beginning of the statute of limitation period to appeal the COFD at a Board of Contract Appeals (BCA) or the Court of Federal Claims (COFC). Upon receipt of the COFD, the contractor has ninety (90) days to file an appeal at a BCA or twelve (12) months to file an appeal at the COFC. Since the statute of limitations is a condition on the waiver of the government’s sovereign immunity, adjudicative forums enforce it strictly as long as the government can establish, by evidence, the date on which the contractor received the COFD. The Federal Acquisition Regulation (FAR) § 33.211(b) obligates the contracting officer (CO) to furnish to the contractor a written copy of the COFD by certified mail, return receipt requested, or by any other method that generates evidence of receipt. Notably, the CO’s obligation to furnish a copy of the COFD to the contractor applies equally to all final decisions on claims, regardless of whether the contractor or the government initiates the claim.

more
TLF-Contract-Claims-Insight-72.jpg

Res judicata provides that when a final judgment has been entered on the merits of a case, it is a finality as to the claim or demand in controversy. Therefore, in federal contract claims litigation, contractors are typically required to bring all their claims arising out of the same contract in the same litigation. The doctrine of res judicata, which encompasses the related doctrines of issue and claim preclusion, may apply when a contractor litigates a matter at a Board of Contract Appeals and later brings a suit with the same or similar set of operative facts at the Court of Federal Claims (COFC). Issue preclusion prohibits a losing party from relitigating already litigated issues. Meanwhile, claim preclusion prevents litigation of matters that have not been litigated but should have been raised in an earlier litigation. Therefore, the doctrine of claim preclusion operates as an affirmative defense, warranting the dismissal of matters that should have been raised in earlier litigation with the same or similar set of operative facts.

In Avant Assessment, LLC v. U.S., 159 Fed. Cl. 632 (2022), the COFC dismissed parts of the complaint based on the doctrine of claim preclusion, finding that the plaintiff should have raised certain arguments during its prior litigation at the Armed Services Board of Contract Appeals (ASBCA). The Army issued the contracts underlying the claims for the acquisition of foreign language testing materials to gauge the proficiency of military linguists. Under the contract, the government retained intellectual property rights in both accepted and rejected items as the contracts provided the government sole ownership and exclusive rights to the testing materials. Army had initially terminated the contracts for default, but the default terminations were later converted into convenience terminations as a result of the contractor’s successful appeals at the ASBCA. Following the successful convenience conversions, the contractor submitted termination settlement proposals to the contracting officer (CO), which were denied. After the CO’s denial, the contractor again appealed the CO’s adverse decision to the ASBCA.

more
Shutterstock_1059713198.jpg

A claim under the Contract Disputes Act (CDA) must first be presented to and denied by the contracting officer (CO) before it can be appealed to a Board of Contract Appeals (BCA) or the Court of Federal Claims (COFC). Adjudicative forums have consistently held the CDA’s presentment requirement to be jurisdictional. That is, for a BCA or the COFC to exercise jurisdiction over a CDA appeal, the underlying claim must first have been presented to the CO for a final decision. Contractors may satisfy the presentment requirement by submitting the claim to the CO in accordance with the requirements of the CDA. While the CDA does not require the claim to be submitted in a particular form, it must typically provide a clear and unequivocal statement that gives the CO adequate notice of the basis and amount of the claim. The CO must then issue a final decision on the claim. The contractor may appeal the CO’s final decision at a BCA or the COFC within 90 days or 12 months, respectively.

In Avant Assessment v. U.S., No. 20-1185C, a decision issued on May 7, 2024, the COFC dismissed an appeal from a CDA claim for a lack of subject matter jurisdiction because the contractor failed to first present its claim to the CO. The appeal was part of a long-running litigation relating to contracts first issued by the U.S. Army in 2011 for foreign language testing materials to assess the proficiency of military linguists. The Army terminated the contracts for default in 2013, but following a successful appeal at the Armed Services Board of Contract Appeals (ASBCA), the default termination was converted into a termination for the government’s convenience. Following the successful convenience conversions, the contractor submitted termination settlement proposals to the CO, which were denied. After the CO’s denial, the contractor again appealed the CO’s final decision to the ASBCA. Notably, during the discovery phase in the second round of ASBCA litigation, the contractor learned that the government had not only retained the rejected testing materials but also “used” them by transferring them to a third party. Therefore, the contractor demanded payment for the rejected test materials. The contractor alleged that the Army had constructively accepted the rejected testing materials by retaining and using them after rejection. Alternatively, the contractor argued that the Army improperly rejected the testing materials. The ASBCA dismissed a large portion of the contractor’s claim for lack of jurisdiction since the contractor’s constructive acceptance claims had not first been first presented to the CO.

more
Insight #25-5.jpg

The Contract Disputes Act (CDA) requires that a contractor present its claim to the contracting officer (CO) before an appeal or suit may be properly filed on that claim. This presentment requirement can be characterized as the linchpin of the contract appeals process under the CDA and is also the last clear chance for the government and the contractor to avoid appeals litigation. Once the contractor submits its claim to the CO, the CDA requires the CO to issue his final decision within 60 days of receiving the claim if the claimed amount is less than $100,000. For certified claims over $100,000, the CO must either issue his final decision within 60 days or notify the contractor within 60 days of the time within which a final decision will be issued. The CDA also requires that the CO issue the final decision within a reasonable time, accounting for factors such as the size and complexity of the claim and the adequacy of information provided by the contractor in support of its claim. In the event of an undue delay by the CO in issuing a final decision, the contractor may request the appeals adjudicative forum to exercise its discretion and direct the CO to issue a decision within a specified period. If the CO fails to issue a decision within that period, the contractor’s claim may be “deemed denied” and considered appealable under the CDA.

more

Operation of the Election Doctrine Under the CDA

TILLIT LAW Federal Contract Claims Insights