The Contract Disputes Act (CDA) provides contractors with alternate forums to resolve claims relating to their federal contracts. After submitting their claim to the contracting officer (CO) and either receiving a denial or a deemed denial on their claim, contractors may appeal the CO’s final decision to either an appropriate Board of Contract Appeals (BCA) or the Court of Federal Claims (COFC). However, once the contractor elects one of the two dispute adjudicative forums and appeals the CO’s adverse decision after receiving notice of the available options, it may not then change forums. Also known as the election doctrine, this rule ensures that once the contractor chooses the forum in which to lodge its appeal under the CDA, it is bound by the election decision and may no longer pursue its appeal in the alternate forum. For the doctrine to apply, the contractor must make an informed, knowing, and voluntary decision to pursue the appeal in one of the two forums with jurisdiction. Once the action is filed in one forum, the other forum must dismiss any subsequently filed appeals concerning the same claim for lack of jurisdiction.
In a 2015 case, the COFC dismissed a contractor’s lawsuit based on the election doctrine as the contractor had previously pursued an appeal on the same claim at the Armed Services Board of Contract Appeals (ASBCA). The contractor was awarded an indefinite-quantity type contract to provide hydraulic and lube oil flushing services on Navy vessels located within a 50-mile radius of San Diego. When the contractor did not receive the anticipated amount of fixed-price delivery orders, it submitted claims to the CO, including a claim for lost profits. After the CO denied the claims in their entirety, the contractor filed an appeal with the ASBCA, making various allegations, including that the awarded contract was a requirements-type contract under which the Navy was essentially obligated to order all flushing services on Navy vessels located within a 50-mile radius of San Diego from the contractor. The ASBCA dismissed the contractor’s appeal for failing to state a claim upon which relief could be granted, ruling that since the contractor was awarded an indefinite-quantity contract, the Navy was not prohibited from ordering the flushing services from other contractors.
Following the Board’s dismissal, the contractor filed a pro se appeal at the Federal Circuit. The Federal Circuit dismissed the appeal for the contractor’s failure to pay the docketing fee and a failure to file the required entry of appearance form by an attorney admitted to the court’s bar. The court later denied a motion for reconsideration on the same grounds. Subsequently, the owner of the contracting company filed a complaint with the Court of Federal Claims (COFC) as a pro se litigant representing the contractor. The COFC ruled that not only was the plaintiff unable to represent the contractor pro se, but it was also precluded from pursuing the lawsuit at the COFC under the CDA’s election doctrine. The COFC ruled that the contractor’s decision to initially appeal the CO’s final decision on the same claim at the ASBCA foreclosed the contractor and its owner’s ability to file suit at the COFC. The court noted that the CDA gave contractors ninety days to appeal a CO’s adverse final decision to a relevant agency Board. Alternatively, in lieu of appealing the CO’s adverse decision to an agency Board, the contractor could bring an action under the CDA directly before the COFC within twelve months of the final decision. Thus, while the CDA offered the contractor a choice between the two forums to appeal the adverse final decision, once the contractor made an informed, knowing, and voluntary decision to elect a forum, the contractor was precluded from filing the same action in the alternate forum.
The CDA provides contractors with an exclusive mechanism for dispute resolution. Under that dispute resolution mechanism, contractors can choose between two alternate forums to appeal the CO’s adverse final decision. However, contractors should be mindful that once they file their appeal with a BCA or the COFC, the election doctrine, which is built into the CDA, operates to preclude them from filing an appeal on the same claim under the same contract in the alternate forum. Thus, contractors should carefully weigh the pros and cons of each forum in the context of their overall litigation strategy before selecting the appropriate forum to file their appeal. Notably, the election doctrine is inapplicable in cases where the forum initially selected by the contractor does not have jurisdiction over the appeal at the time of filing. Consequently, contractors may file an appeal or a suit in the alternate forum if the initially selected forum dismisses their matter for lack of jurisdiction. In such a scenario, contractors should still be able to meet the alternate forum’s statutory deadlines for filing the action. Finally, it is also worth noting that the election doctrine does not preclude contractors from filing suit at the COFC after filing an untimely appeal at a BCA.
This Federal Contract Claims Insight is provided as a general summary of the applicable law in the practice area and does not constitute legal advice. Contractors wishing to learn more are encouraged to consult the TILLIT LAW PLLC Client Portal or Contact Us to determine how the law would apply in a specific situation.

 



