Insight #25-5.jpg

Requesting the CO’s Final Decision on a Claim within a Specified Period

The Contract Disputes Act (CDA) requires that a contractor present its claim to the contracting officer (CO) before an appeal or suit may be properly filed on that claim. This presentment requirement can be characterized as the linchpin of the contract appeals process under the CDA and is also the last clear chance for the government and the contractor to avoid appeals litigation. Once the contractor submits its claim to the CO, the CDA requires the CO to issue his final decision within 60 days of receiving the claim if the claimed amount is less than $100,000. For certified claims over $100,000, the CO must either issue his final decision within 60 days or notify the contractor within 60 days of the time within which a final decision will be issued. The CDA also requires that the CO issue the final decision within a reasonable time, accounting for factors such as the size and complexity of the claim and the adequacy of information provided by the contractor in support of its claim. In the event of an undue delay by the CO in issuing a final decision, the contractor may request the appeals adjudicative forum to exercise its discretion and direct the CO to issue a decision within a specified period. If the CO fails to issue a decision within that period, the contractor’s claim may be “deemed denied” and considered appealable under the CDA.

In ASBCA 63325, the Armed Services Board of Contract Appeals (ASBCA) issued an order on August 19, 2022, directing the CO to issue a decision within a specified time. The commercial-item indefinite-delivery, indefinite-quantity contract underlying that appeal was issued to a subsistence contractor in Afghanistan on a fixed-price basis. The Defense Logistics Agency (DLA) initially issued the contract in 2012, the term of which was later extended in 2020 through April 2025. After the withdrawal of U.S. forces from Afghanistan was announced in April 2021, the DLA and the contractor attempted to re-negotiate the continued performance under the contract but ultimately failed to reach an agreement. Subsequently, the contractor requested that the government terminate the contract for convenience, which the government refused to do. On March 21, 2022, the contractor submitted a duly certified claim for approximately $34 M in damages arising from the government’s alleged failure to acknowledge that the contract was constructively terminated. Notably, a constructive termination for convenience is a legal fiction that imposes the termination on the contractor even when the CO never specifically ordered a termination. On May 20, 2022, DLA notified the contractor that it intended to issue a final decision by April 20, 2023, due to the size and complexity of the contractor’s claim. The government also cited the CO’s workload issues, her vacation schedule, and concurrent matters that the contractor had in litigation at the time. However, the government acknowledged that the contractor’s claim was only 20 pages long, with 17 accompanying exhibits.

The contractor filed a request with the ASBCA pursuant to ASBCA Rule(1)(a)(5) for an order directing the CO to render a final decision on the claim by August 8, 2022. The ASBCA began its analysis by noting that the Board determines, on a case-by-case basis, whether the time a CO states he will issue a final decision in is reasonable. The Board pointed to its previous decisions for the proposition that while the size and complexity of the claim were considered factors in determining a reasonable time for the final decision, the government’s internal staffing matters were not a factor. ASBCA explained that the scarcity of attorneys to assist with the review of a CO’s final decision is a matter wholly and exclusively within the government’s control. Therefore, DLA was not justified in citing the CO’s workload and vacation schedule as issues contributing to the reasonableness of the time for the final decision. The Board reviewed the contractor’s claim and determined that while the contractor’s claim was somewhat complex, it did not appear, on its face, to be so extraordinarily complex that it would justify the government requiring additional time to assess. Thus, the ASBCA concluded that the DLA’s requested date for the issuance of the CO’s final decision nearly 13 months after the submission of the contractor’s initial claim was unreasonable. The Board directed the CO to issue a decision on the claim by December 16, 2022, failing which the contractor could file an appeal based on a deemed denial.

The CO’s final decision on a claim is a good indicator of the government’s position and basis for denial. It is also the parties’ last chance to avoid appeals litigation. Therefore, contractors facing undue delays from the CO after submitting their claims should be mindful that they may request the appropriate appeals tribunal to direct the CO to issue a final decision on their claim within a specified period. While what constitutes a reasonable time to issue a final decision will depend on the facts of a particular claim, contractors can compare the size, complexity, and issues of their claim to past similar cases to ascertain an approximate timeframe. For instance, the ASBCA gave the DLA CO nearly nine months after the contractor’s initial claim to issue a final decision in the above case. Similarly, nine months was reasonable when the contractor’s claimed amount exceeded $71 M, and the claim’s narrative section exceeded 160 pages. In another case, eight months was found reasonable where there were a significant number of issues, voluminous records, and a lengthy period was required to gather information due to the relocation of personnel. Meanwhile, the ASBCA has found 14-16 months unreasonable for a small construction claim, where the impact of the claim had already been extensively analyzed and audited. When faced with unreasonable delays by the CO in the issuance of a final decision, contractors should familiarize themselves with this framework to assess whether it is appropriate to request the appeals adjudicative forum to direct the CO to issue a final decision within a specified period.

This Federal Contract Claims Insight is provided as a general summary of the applicable law in the practice area and does not constitute legal advice. Contractors wishing to learn more are encouraged to consult the TILLIT LAW PLLC Client Portal or Contact Us to determine how the law would apply in a specific situation.

Related Insights

TLF-Contract-Claims-Insight-57.jpg

Once a contractor submits a claim to the government under the Contract Disputes Act (CDA), the government is required to provide it a copy of the contracting officer’s final decision (COFD). The receipt of the COFD by the contractor is a key event in the lifecycle of a CDA claim because it triggers the beginning of the statute of limitation period to appeal the COFD at a Board of Contract Appeals (BCA) or the Court of Federal Claims (COFC). Upon receipt of the COFD, the contractor has ninety (90) days to file an appeal at a BCA or twelve (12) months to file an appeal at the COFC. Since the statute of limitations is a condition on the waiver of the government’s sovereign immunity, adjudicative forums enforce it strictly as long as the government can establish, by evidence, the date on which the contractor received the COFD. The Federal Acquisition Regulation (FAR) § 33.211(b) obligates the contracting officer (CO) to furnish to the contractor a written copy of the COFD by certified mail, return receipt requested, or by any other method that generates evidence of receipt. Notably, the CO’s obligation to furnish a copy of the COFD to the contractor applies equally to all final decisions on claims, regardless of whether the contractor or the government initiates the claim.

more
Shutterstock_530695792.jpg

To file appeals under the Contract Disputes Act (CDA), contractors are required to first submit their claims to the contracting officer (CO) for a contracting officer’s final decision (COFD). The Federal Acquisition Regulation (FAR) § 33.211(a)(4)(v) requires COs to include in their final decisions a notice detailing the contractor’s rights to appeal the COFD at the Boards or the COFC. Such notice of contractor appeal rights should include language substantially similar to the following:

“This is the final decision of the Contracting Officer. You may appeal this decision to the agency board of contract appeals. If you decide to appeal, you must, within 90 days from the date you receive this decision, mail or otherwise furnish written notice to the agency board of contract appeals and provide a copy to the Contracting Officer from whose decision this appeal is taken.”

As detailed in the appeal rights notice, the contractor has ninety (90) days to appeal the COFD to an appropriate Board of Contract Appeals or up to twelve (12) months to appeal the decision at the Court of Federal Claims (COFC). The receipt of the COFD by the contractor triggers the beginning of the CDA appeals limitations period, within which the contractor must appeal the COFD at a Board of Contract Appeals (BCA) or the Court of Federal Claims (COFC). Notably, in cases where the government issues a decision terminating a contract for default, the receipt of notification of the CO’s decision to terminate the contract begins the CDA appeals limitation period. Such a default termination notice must typically contain the contractor appeal rights language detailed above. However, the omission of the appeals rights language in the termination notice does not, by itself, negate an otherwise final decision. Additionally, the lack of such an appeal rights notice also does not stop the receipt of the COFD from triggering the CDA appeals limitation period – unless the contractor can demonstrate detrimental reliance or prejudice stemming from the omission of such notice.

more
Shutterstock_1059713198.jpg

A claim under the Contract Disputes Act (CDA) must first be presented to and denied by the contracting officer (CO) before it can be appealed to a Board of Contract Appeals (BCA) or the Court of Federal Claims (COFC). Adjudicative forums have consistently held the CDA’s presentment requirement to be jurisdictional. That is, for a BCA or the COFC to exercise jurisdiction over a CDA appeal, the underlying claim must first have been presented to the CO for a final decision. Contractors may satisfy the presentment requirement by submitting the claim to the CO in accordance with the requirements of the CDA. While the CDA does not require the claim to be submitted in a particular form, it must typically provide a clear and unequivocal statement that gives the CO adequate notice of the basis and amount of the claim. The CO must then issue a final decision on the claim. The contractor may appeal the CO’s final decision at a BCA or the COFC within 90 days or 12 months, respectively.

In Avant Assessment v. U.S., No. 20-1185C, a decision issued on May 7, 2024, the COFC dismissed an appeal from a CDA claim for a lack of subject matter jurisdiction because the contractor failed to first present its claim to the CO. The appeal was part of a long-running litigation relating to contracts first issued by the U.S. Army in 2011 for foreign language testing materials to assess the proficiency of military linguists. The Army terminated the contracts for default in 2013, but following a successful appeal at the Armed Services Board of Contract Appeals (ASBCA), the default termination was converted into a termination for the government’s convenience. Following the successful convenience conversions, the contractor submitted termination settlement proposals to the CO, which were denied. After the CO’s denial, the contractor again appealed the CO’s final decision to the ASBCA. Notably, during the discovery phase in the second round of ASBCA litigation, the contractor learned that the government had not only retained the rejected testing materials but also “used” them by transferring them to a third party. Therefore, the contractor demanded payment for the rejected test materials. The contractor alleged that the Army had constructively accepted the rejected testing materials by retaining and using them after rejection. Alternatively, the contractor argued that the Army improperly rejected the testing materials. The ASBCA dismissed a large portion of the contractor’s claim for lack of jurisdiction since the contractor’s constructive acceptance claims had not first been first presented to the CO.

more
Shutterstock_2160344179.jpg

While the Contract Disputes Act provides no definition of a claim, the Federal Acquisition Regulation (FAR) § 2.101 defines a claim as a written demand or assertion by one of the contracting parties seeking, as a matter of right, the payment of a sum certain arising under or relating to the contract. The FAR further provides that a routine request for payment that is not in dispute when submitted is not a claim. However, such submissions may be converted to a claim by written notice to the contracting officer as provided in FAR § 33.206(a) if it is disputed as to the liability or amount or is not acted upon in a reasonable time. Finally, the FAR requires claims over $100,000 to be certified. To assess whether a submission is a CDA claim rather than a request for equitable adjustment (REA), contractors may typically look to three objective criteria:

  1. The submission meets the definition of a “claim”
  2. The submission includes a CDA certification
  3. The contractor must request a final decision from the contracting officer

Despite these objective criteria, it may not always be clear when an REA is converted into a “claim,” the denial or deemed denial of which can be appealed to a Board of Contract Appeals or the Court of Federal Claims (COFC). On August 29, 2024, the Armed Services Board of Contract Appeals (ASBCA) in ASBCA No. 63197 issued a decision on a government’s motion to dismiss for the contractor’s failure to convert an REA into a CDA claim. The underlying contract for medical coding services was issued by the Army in January 2018 using the government-provided browser-based Application Virtualization Hosting Environment (AVHE) for the United States Medical Command. Almost two years later, on November 18, 2019, the contractor submitted a “Request for Price Modification” seeking various cost adjustments. The pertinent portion of the request sought costs for lost production due to the government-imposed downtime for the AVHE system. In February 2021, the contractor provided supporting material to validate downtime costs in response to a government request for additional information. In July 2021, the contractor submitted a revised request for price modification labeled “Request for Equitable Adjustment,” seeking payment for downtime costs in the amount of $615,199 categorized as an unexpected loss.

more

Requesting the CO’s Final Decision on a Claim within a Specified Period

TILLIT LAW Federal Contract Claims Insights