TLF-Contract-Claims-Insight-69.jpg

Demonstrating Changed Circumstances to Avoid Terminations for Default

The government retains the right to terminate a contract for default when the contractor fails to meet its performance obligations. The default termination, commonly considered one of the most undesirable outcomes for contractors, may nevertheless be converted into a termination for the government’s convenience if, on appeal, the government fails to prove that its default termination decision was justifiable. Notably, when the contractor appeals the government’s decision to terminate its contract for default, it is the government’s burden to prove default termination in the first instance. In other words, the government must demonstrate the correctness of its actions in terminating a contract for default. When contract modifications change the terms of the original contract such that the government’s default termination decision is no longer justified under the modified contract, adjudicative forums will typically convert the default termination to one for the convenience of the government, citing the change in circumstances from contract award to termination.

The Armed Services Board of Contract Appeals (ASBCA) in ASBCA 58866 and ASBCA 58867 converted the Army’s terminations for default for two similar contracts into terminations for convenience due to changes in the terms of the contracts due to later modifications. The Army awarded the underlying contracts for the acquisition of thousands of foreign language test items to assess the proficiency of military linguists. The contracts included the Federal Acquisition Regulation (FAR) 52.212-4 clause: “Contract Terms and Conditions—Commercial Products and Commercial Services.” During the performance, the government was only responsible for paying for the items it accepted, with no apparent definition of what constituted an acceptable item, presumably leaving the acceptability determination at the government’s discretion. The government retained intellectual property rights in both accepted and rejected items as the contracts provided the government sole ownership and exclusive rights to the deliverables. After the contracts were awarded to the same contractor, the Army issued nearly identical modifications, stating that any foreign language test items still required under the contracts but not accepted by the government would be “automatically descoped” from the contract. The Army eventually terminated the contracts for default, citing the contractor’s failure to provide the agreed-upon number of acceptable items.

The contractor appealed the government’s decision to terminate its contracts for default, arguing that it was no longer required to deliver the originally agreed-upon number of acceptable items because of the contract modifications. In conducting a plain meaning analysis of the descoping language, the ASBCA agreed with the contractor that its delivery obligations had changed because of the modifications. Specifically, the ASBCA ruled that under the modification, the contractor was no longer required to deliver the originally agreed-upon number of acceptable items under the contracts. The Board explained that since the modification stated that the test items that the government rejected would be “automatically descoped” from the contract – by entering the modification, the government had essentially agreed to reduce the number of acceptable items that were originally required to be delivered under the contract to however many acceptable items the contractor ultimately delivered. Therefore, after the parties agreed to the modifications, the contractor’s failure to provide the agreed-upon number of acceptable items was no longer an adequate reason for a default termination. The government also attempted to argue that the contractor failed to meet an agreed-upon delivery schedule as justification for terminating the contract for default. However, the government could not identify the relevant delivery schedule or provide specific evidence supporting this argument. Consequently, the ASBCA rejected this argument and converted the default terminations into terminations for the government’s convenience.

A default termination decision can present significant challenges for a contractor, including but not limited to loss of revenue and difficulties in obtaining future contracts. However, contractors may avoid such undesirable outcomes by successfully appealing the default termination decision and getting it converted into a termination for the government’s convenience. Therefore, contractors facing default termination decisions should carefully review any applicable contract modifications to determine if the terms of the underlying contract were sufficiently changed such that the government’s default termination decision may be deemed unreasonable or no longer supported by the terms of the modified contract. Depending on the specific circumstances, the contractor’s ability to demonstrate a change in circumstances during the appeals phase may also open avenues for alternate dispute resolution, potentially helping the contractor avoid a default termination.

This Federal Contract Claims Insight is provided as a general summary of the applicable law in the practice area and does not constitute legal advice. Contractors wishing to learn more are encouraged to consult the TILLIT LAW PLLC Client Portal or Contact Us to determine how the law would apply in a specific situation.

Related Insights

TLF-Contract-Claims-Insight-7.jpg

Contractors often face situations requiring them to enter bilateral contract modifications towards the end of a contract to close it out. To avoid incurring excessive costs and liability in such situations, contractors should carefully consider whether the modifications increase the scope of the contract beyond what was initially agreed upon. Federal contractors should review the impact of any applicable Federal Acquisition Regulation (FAR) provisions in their contract on the modification at issue, as recovery under future requests for equitable adjustments and claims may depend on it.

The Armed Services Board of Contract Appeals (ASBCA), in one of its first decisions of 2024, reminded contractors to carefully assess the scope and governing authority before agreeing to bilateral contract modifications. In ASBCA No. 61819, the contractor brought unsuccessful claims of contract changes based on economic waste theory and differing site conditions against NASA. The contract involved construction work on an aircraft parking apron and taxiway at a NASA flight facility in Virginia. It included the Default (Fixed-Price Construction) clause from FAR § 52.249-10(a) and an Inspection of Construction clause from FAR § 52.246-12. The contract also contained Technical Direction and Special Instruction provisions that prohibited the Contracting Officer’s Representative (COR), Government inspectors, or any other Government employees from issuing technical directions that waived or changed any contract provisions without written authorization from the Contracting Officer (CO).

more
TLF-Contract-Claims-Insight-8-2.jpg

One of the unique privileges enjoyed by the U.S. Government as a contracting party under a federal contract is its authority to terminate the contract at any time, regardless of the contractor’s fault. Known as termination for convenience, the contracting action allows the Government an exclusive and almost unlimited right to terminate a government contract unilaterally. When terminating a contract for convenience, the Government may terminate the contract entirely or choose to make partial terminations with practically no limitations on the extent, type, or profitability of the portion of the contract being terminated.

While contract termination is seldom a cause for celebration for the contractor, a convenience termination is still greatly preferred over termination for default. This is because of the simple reason that a convenience termination indicates that the Government terminated the contract in its own best interests rather than due to the contractor’s fault. This allows contractors to receive the costs they incurred in performing the contract up to the point of termination, along with any profits on the completed work, if applicable. Under convenience termination, contractors can also recover any costs expended in delivering the termination proposal.

more
TLF-Contract-Claims-Insight-14.jpg

Government officials often direct contractors to perform contract work in a specific manner not detailed in the contract. If such orders increase the scope of performance beyond the specifications of the contract, they may be construed as constructive changes. While such orders are generally given on the belief that they naturally fall within the scope of performance, they may nevertheless expand the scope of performance beyond the stated specifications. In such situations, contractors may be entitled to compensation for constructive change even if the accompanying government directive expressly states that it is not meant as a change order. Upon receipt of such directives, contractors must compare the new requirements with their existing contract specifications carefully and raise any scope creep issues promptly. Such a proactive approach may prove crucial in avoiding potential disputes and aid the contractor’s arguments in case of litigation.

Additional performance specifications not previously described in the contract may have the effect of increasing the scope of performance and add to costs incurred by the contractor. In such cases contractors may file a claim for increased costs. Such a claim was before the Armed Services Board of Contract Appeals (ASBCA) in ASBCA No. 49648 pursuant to a contract for grounds maintenance services at the Arlington National Cemetery in Virginia. Under the contract, the contractor was required to furnish all labor, equipment, and materials for grounds maintenance supervision. While the contract specifications prohibited any contractor employees, vehicles, or equipment from infringing upon any government ceremonies or visitations, they did not expressly specify the distance contractor employees would have to maintain to comply with the no-infringement provision. Notably, the government had omitted provisions describing the exact no-infringement distances to maximize competition and avoid artificially high bids.

more
TLF-Contract-Claims-Insight-53.jpg

The government may terminate a federal contract if the contractor fails to meet its contractual obligations. The contracting officer (CO), in such cases, issues a final decision terminating the contract for default and outlines the reasons for the default. In the event of a termination for default, the government is only liable to the contractor for the portion of the contract that was already performed. While the CO may exercise discretion to terminate a contract for default, such a decision is appealable to the Board of Contract Appeals or the Court of Federal Claims (COFC) pursuant to the Contract Disputes Act (CDA). The CO’s decision to terminate may be set aside by the adjudicative forum if it is arbitrary, capricious, or constitutes an abuse of the CO’s discretion. For instance, a decision to terminate for default may be arbitrary and capricious if there is a lack of nexus between the CO’s decision to terminate the contract for default and the contractor’s performance on the contract. In such situations, while the concerned adjudicative forum may lack the ability to provide injunctive relief, it may nevertheless convert the CO’s default termination to one for the government’s convenience.

more

Demonstrating Changed Circumstances to Avoid Terminations for Default

TILLIT LAW Federal Contract Claims Insights