TLF-Contract-Claims-Insight-4.jpg

Overcoming the Sovereign Acts Defense

The Sovereign Acts Doctrine allows the federal government to avoid liability arising from its actions as a sovereign. As relevant to federal contracts, the doctrine seeks to reconcile the government’s dual roles as a contracting party and a sovereign. It ensures that the government’s generally applicable public acts do not create contractual liability due to their incidental impacts on specific government contracts. Restrictions in response to COVID-19 and government shutdowns are examples of sovereign acts impacting federal contracts. When in breach of a contract, the government may invoke the Sovereign Acts Doctrine as an affirmative defense.

When invoking this defense, the Government asserts that it is not liable for breaching the contract as the breach occurred due to incidental consequences of a sovereign act. Adjudicative forums generally utilize a two-part test to determine whether the Sovereign Act Defense applies. Firstly, the government’s sovereign act must be public, general, and only incidentally fall upon the contract or order. Secondly, the sovereign act must render performance by the government acting as a private contractor impossible or impracticable under the general principles of contract law. Notably, the defense only applies when there has been a breach of contract. In other words, the existence of a contractual breach is a prerequisite to the applicability of the sovereign acts defense.

In situations where a sovereign act has adversely impacted contract performance by either causing delays or increasing costs, contractors should first assess whether the act in question was explicitly directed toward their contract. If the answer is yes, the act is not public and general, and the government will not be relieved of its liability. In the COVID-19-related claims, contractors often found this hurdle challenging to overcome. That is, the contractors found it challenging to prove that the government restrictions impacting their contracts were actions directed specifically at their contracts.

Secondly, in invoking the affirmative sovereign acts defense, the government is required to prove that the sovereign act rendered its performance as a contracting party impossible or impracticable under the principles of contract law. In such cases, the government’s burden of proof is similar to a private contractor’s burden in an impracticability claim. In StructSure Projects, Inc., ASBCA No. 62927, which was a relatively rare successful contractor claim involving COVID-19 restrictions, the government could not prove that its performance under the contract was rendered impossible or impracticable due to the restrictions. Consequently, the government failed to affirmatively raise the sovereign acts defense.

In that case, due to COVID-19 restrictions, non-essential contractor employees were denied physical access to the base and were therefore unable to perform on the task order, which involved design and alteration services at the David Grant Medical Center on the Travis Air Force Base. It was undisputed that the government’s denial of access to contractor personnel was a sovereign act. However, the government’s duty of cooperation for a specific contract line item involving temporary phasing facilities remained unimpacted by the restrictions. Notably, during the period when the COVID-19 restrictions were in effect, the government continued using temporary phasing facilities for storage purposes and ongoing treatments of patients. Since the physical availability of contractor personnel was not necessary for successful performance under the phasing facilities line item, the government’s duty to cooperate remained unaffected by the COVID-19 restrictions. Consequently, the government’s performance of its cooperation duties for the phasing facilities line item was not rendered impossible or impracticable. Additionally, the ASBCA determined that the contractor successfully delivered performance on the separate phasing facilities line item. Therefore, there was no evidence that the government breached its duties under the contract. Since the government did not breach its duties as relevant to the line item and the contractor successfully delivered performance under it, the Board found that the Sovereign Acts doctrine was inapplicable. Thus, the contractor could recover the costs of providing the temporary phasing facilities during the stoppage of work, despite it being a fixed-price contract.

The Sovereign Acts Doctrine presents a somewhat complex legal landscape for federal contractors because it shields the government from liability for the consequences of its public and general actions taken as a sovereign. When facing the government’s affirmative invocation of the Sovereign Acts Doctrine, contractors should aim to prove that the sovereign act was not public and general and was specifically directed at their contract. If that proves unsuccessful, contractors should attempt to prove that the sovereign act did not render the government’s performance of its duties impossible or impracticable under general principles of contract law. Such an argument is strongly supported by demonstrating that performance was successfully delivered under the contract, as the doctrine is inapplicable in the absence of a contractual breach.

This Federal Contract Claims Insight is provided as a general summary of the applicable law in the practice area and does not constitute legal advice. Contractors wishing to learn more are encouraged to consult the TILLIT LAW PLLC Client Portal or Contact Us to determine how the law would apply in a specific situation.

Related Insights

TLF-Contract-Claims-Insight-6.jpg

Subcontractors under U.S. federal contracts cannot generally sue the government directly as they lack privity of contract with the government. Privity refers to a legal concept describing a relationship or nexus between contracting parties. The government often utilizes a two-tiered contracting system for procurements where it enters into a contract with the prime contractor that, in turn, contracts with subcontractor(s) to fulfill contractual requirements. Thus, in a federal contract, the government only has a privity of contract with the prime contractor, creating a legal buffer between the government and the subcontractor. Since subcontractors are not in privity with the government, the government does not waive its sovereign immunity, and subcontractors may not bring direct claims against the government.

However, as with most rules in U.S. federal contracting, the no subcontractor privity rule has its exceptions. These exceptions require that subcontractors looking to bring direct claims against the government must first establish a privity of contract with the government. That is, the contractor must successfully demonstrate that it explicitly or implicitly entered into a contract with the government.

more
TLF-Contract-Claims-Insight-38.jpg

A War Risks clause may be added to government contracts if performance is required in regions with a risk of war or war-like events. Such a clause helps allocate responsibility between the government and the contractor for any losses or damages caused by such events. While the Federal Acquisition Regulation (FAR) does not specifically contain a standard war risks clause, the defense supplement to the FAR (DFARS) includes clauses such as DFARS 252.228-7000, “Reimbursement for War-Hazard Losses.” Such a clause addresses the allowability of costs of war-hazard benefits for contractor employees. A War Risks clause can typically be negotiated between the government and the prospective contractor at the time of formation of the contract. As contracts in different regions have varying circumstances, risk allocation for specific events described in the War Risks clause should also be tailored and negotiated for each applicable contract. When disputes between the government and the contractor arise that implicate the War Risks clause, adjudicative forums such as the Boards of Contract Appeals or Federal Courts interpret the language of the War Risks clause to allocate increased costs liability between the parties.

more
TLF-Federal-Procurement-Insight-12.jpg

The federal government generally procures software as commercial items. The terms and conditions governing the use of commercial software are contained in the end-user licensing agreement (EULA), which is generally incorporated into the government contract. Since the Federal Acquisition Regulation (FAR) does not provide standard licensing agreements for commercial software, manufacturers or resellers must negotiate the terms of use of such software when the EULA is incorporated into the contract. Depending on the contract, the EULA can be incorporated into an individual order or the master agreement of a government-wide acquisition vehicle, such as a Federal Supply Schedule (FSS) contract.

As relevant to government contracts, the U.S. federal government waives its sovereign immunity for liability arising from contract claims under the Contract Disputes Act (CDA). However, the government may use the Sovereign Acts Doctrine as an affirmative defense against contractor claims. Standard contract provisions within the software manufacturer’s EULA may occasionally conflict with federal laws, including the government’s rights as a sovereign. Contractors must, therefore, review their standard EULA terms and negotiate specific clauses with the software manufacturer, if necessary, before submitting them to the government for incorporation into a government contract. While contractors should review all provisions with sovereign immunity implications, they should pay especially close attention to the following standard clauses before the EULA is submitted to the government for incorporation into a federal contract.

more
TLF-Contract-Claims-Insight-47.jpg

While there are ways in which subcontractors may achieve privity of contract, they may not generally bring direct claims against the Government due to a lack of privity. Therefore, subcontractor claims against the Government are typically asserted by prime contractors as pass-through claims. However, prime contractors may only bring such pass-through claims if they meet the requirements of the Severin Doctrine. First articulated by the Court of Claims in 1943, the Severin Doctrine bars pass-through subcontractor claims unless the prime contractor itself remains liable to claims by the subcontractor. While the Severin Doctrine has evolved through its application to various pass-through claims scenarios, at its outset, it barred the assertion of pass-through claims unless the prime contractor either reimbursed the subcontractor due to the Government’s fault or was at least liable to make such a reimbursement in the future.

Based on the principles of sovereign acts immunity and privity of contract as applied to government contracts, the Severin Doctrine requires the prime contractor to have at least some demonstrable exposure to subcontractor liability. To prevent pass-through claims through this affirmative defense, the Government typically points to any provisions in the subcontract that tend to exculpate the prime contractor from liability to the subcontractor. When entering teaming arrangements, contractors should be aware that if the subcontract agreement contains a clause completely or specifically exonerating a prime contractor from liability to the subcontractor for pertinent damages, then the prime contractor may not assert a related pass-through claim against the Government. Prime contractors are similarly barred from asserting pass-through claims if the subcontract specifically extinguishes prime contractor liability upon the meeting of certain requirements, such as the subcontractor being granted additional time or the acceptance of final payment.

more

Overcoming the Sovereign Acts Defense

TILLIT LAW Federal Contract Claims Insights