shutterstock_1043665888 copy.jpg

Establishing Breach of Contract Due to Cardinal Change

The government may sometimes unilaterally direct the contractor to perform additional work outside the scope of the changes clause of a government contract. Such an order for alterations is a cardinal change and amounts to a breach. In order to establish that a cardinal change has occurred, the contractor must show that the work ordered by the government, either explicitly or impliedly, was beyond the contract requirements and materially different from what the contract specified. To determine whether a cardinal change exists, claim adjudicative forums compare the total altered work with the work included in the contract. If the alterations in the work are out of character with the work contemplated in the contract or require a level of effort reasonably unforeseeable at the time of formation, a cardinal change has occurred. In other words, a cardinal change exists when the government requests a unilateral change that so drastically alters the work that the contractor must essentially perform duties that are materially different from those it originally bargained for. While facts and figures involving the number of days of delay and performance cost increases may be helpful in understanding the extent of the additional work, establishing whether a cardinal change has occurred involves a highly fact specific inquiry that must look beyond such numbers alone, into the contractor’s entire undertaking. Once established, a cardinal change is a breach of contract and accordingly has the effect of freeing the contractor from its contractual obligations.

In Edward R. Marden Corp. v. United States, 442 F.2d 364 194 Ct. Cl. 799 (Ct. Cl. 1971), the Court of Claims held that a cardinal change had occurred when considering the entire undertaking of the contractor. The U.S. Navy awarded a contract for, among other things, the construction of a new aircraft maintenance hangar at the Naval Air Station in South Weymouth, Massachusetts. During construction, the entire structure collapsed, causing death, serious injuries, and significant damage to the already completed work. Following the collapse, the government directed the contractor to clean up the debris and complete the construction of the hangar per the government’s instructions. The contractor reconstructed the hangar under protest and later brought a breach of contract claim against the government for $3,700,000, alleging that it had been supplied defective specifications. The Court noted the fluid nature of the cardinal change doctrine and stressed the importance of individualized analysis of each case based on its own facts and circumstances, while giving due consideration to the magnitude and quality of the government-ordered changes and their cumulative effect on the project. Although the final reconstructed building was presumably identical to the one contemplated by the original specifications, the change in this case involved major reconstruction that the contractor could not have foreseen at contract formation. The contractor also suffered increased costs of almost double the contract price and the work was materially different from what the parties had bargained for. Under the circumstances, the Court held that a cardinal change had occurred because of the sheer magnitude of reconstruction work stemming from the allegedly defective specifications.

Meanwhile, in Armed Services Board of Contract Appeals (ASBCA) No. 62285, a decision issued on December 30, 2022, the Board determined that no cardinal change had occurred when a one year construction project took nearly four years to complete. The U.S. Air Force awarded the contract in question for the repair and renovation of a building located on Minot Air Force Base in North Dakota. Due to numerous delays, the project was completed 1021 days after the original contract completion period of 365 days. The contractor alleged that the government had accepted responsibility for 97% of the delays because it issued modifications extending the performance period for a total of 986 days. Notably, the contractor did not provide a critical path analysis or address the government’s contentions that the mere grant of extensions did not establish government responsibility for the delays and that the government delays accounted for no more than 246 days. The Board found that the contractor had failed to satisfy its burden of proof to establish a cardinal change. Since the application of the cardinal change doctrine requires a fact-intensive inquiry, the contractor was required to provide the details necessary for the Board to determine whether the government was responsible for the delays and difficulties on the project. However, the contractor did not provide a critical path analysis or respond to the government’s contrary assertions about the responsibility for the delays. Furthermore, the work performed did not result in a materially different project and the work and level of effort were essentially the same as the contractor bargained for before the contract was awarded. Consequently, the contractor failed to establish a cardinal change.

A cardinal change is a breach of contract that occurs when the government directs the contractor to make alterations in the work that are so drastic that the contractor is forced to perform materially different duties from those the parties originally bargained for at the time of contract formation. Since, by its very definition, a cardinal change is not redressable under the contract, if a claim can be resolved within the remedy-granting clauses of the contract, such as the changes or the differing site conditions clause, the cardinal change claim is denied, and the contractor is granted remedy within the contract. Contractors should be mindful that there is no exact mathematical formula to determine whether a change is a cardinal change. In this regard, while numbers such as the total days of delay and the increased costs of performance are helpful in determining the magnitude of the alterations in work, they may not be sufficient in and of themselves to establish that a cardinal change has occurred. Instead, Courts and Boards resolve the highly fact-specific inquiry by assessing the parties’ intentions at the time of contract formation, evaluating the quality and magnitude of the changed work, and reviewing the overall impact of the change on the project as a whole. If the altered work is materially different from the work contemplated under the contract or the contractor’s level of effort is drastically different and not foreseeable at formation, a cardinal change has likely occurred. Once established, a cardinal change renders the government in breach and releases the contractor of liability under the contract.

This Federal Contract Claims Insight is provided as a general summary of the applicable law in the practice area and does not constitute legal advice. Contractors wishing to learn more are encouraged to consult the TILLIT LAW PLLC Client Portal or Contact Us to determine how the law would apply in a specific situation.

Related Insights

Insight 5 - Substack.jpg

The primary method for managing risks associated with latent physical conditions encountered in construction projects is the differing site conditions clause in Federal Acquisition Regulation (FAR) 52.236-2. Since fully redressable claims under specifically included contract clauses may not be brought under separate breach of contract claims, most claims for hidden site conditions are brought under the differing site conditions clause. However, certain federal contracts for smaller construction projects awarded through simplified procedures, and some custom-negotiated construction contracts may lack a well-defined differing site conditions clause. In such cases, contractors must pursue their claims arising out of unforeseen conditions, such as claims related to subsurface conditions under traditional breach of contract theories. Additionally, when faced with unforeseeable events like extreme and unpredictable weather or unanticipated changes in labor conditions that are not typically covered by the differing site conditions clause, construction contractors may opt to initiate breach of contract claims to recover their increased costs.

The Government’s non-disclosure or misrepresentation of information material to site conditions are two breach of contract actions available to construction contractors in such situations. To be successful in a non-disclosure claim, the construction contractor must demonstrate that the Government possessed information pertinent to a material site condition, which it failed to disclose to the contractor. The contractor must also establish that the presence of the material site condition could not have been readily determined through a site inspection or other reasonable methods. Government misrepresentation is the other breach of contract claim commonly applicable in contracts without a differing site conditions clause. A misrepresentation claim is essentially based on the Government breaching its duty to disclose its superior knowledge of the site condition. To prove that the Government breached its duty to disclose, the Court of Federal Claims (COFC) has previously required that the contractor demonstrate Government culpability. One way of demonstrating Government culpability is by proving that the Government knew that the contractor was unaware of the differing site conditions. However, the Federal Circuit has recently rejected the Government culpability requirement, making contractor claims easier to prove in such situations. Therefore, depending upon the circumstances, the adjudicative forum’s analysis for a breach of contract claim for Government misrepresentation is similar if not identical to a differing site conditions claim.

more
Shutterstock_1931171357.jpg

In the performance of government contracts, there are instances where the government does not breach any specific terms or conditions of the contract but is nevertheless responsible for the contractor’s damages due to the fault or negligence of government officials. If the government personnel’s negligence or fault occurs in the administration of the contract, the government may be liable for breach of contract. In such situations, the contractor must prove its breach of contract claim by showing that the government had an obligation or duty arising out of the contract and that the government was in breach of this contractual obligation. Additionally, the contractor asserting the breach of contract claim due to the government’s fault or negligence in administration must also establish that the damages it claims were reasonably foreseeable at the time of contract award. Finally, the contractor’s damages must also be the natural and proximate result of the government’s breach. Notably, while the contractor may recover damages resulting from the natural and probable consequences of the government’s breach, damages that are too remote or attenuated from the breach are typically not recoverable.

more
Shutterstock_2211056755.jpg

The government provides contractors with a variety of information during the solicitation process before a contract is awarded. Such information may be furnished through pre-award conferences, questions and answers, solicitation attachments, specifications, diagrams, drawings, contract provisions, etc. When the government misstates material facts during the contract formation process, it may later be liable under express provisions of the contract or for breaching an implied warranty that it furnishes correct information. In this regard, when the government provides incorrect representations and directs or expects prospective offerors to base their contract pricing on those misrepresentations, the government is responsible for any losses the contractor suffers as a result of its reliance on that information. In other words, when the government instructs offerors to base their pricing on data it furnishes, it assumes responsibility for ensuring that the data accurately reflects the conditions the contractor will encounter during performance. In such cases, as long as the contractor can demonstrate that the government's information was incorrect, it need not prove the government's intent to deceive or bad faith. Furthermore, the contractor may also not need to prove that the incorrect information was inadequately or negligently prepared.

more
shutterstock_2740412339.jpg

Government agencies have a prima facie case for default termination when a contractor fails to deliver performance in a timely manner. However, even when terminating the contractor on this basis, the government must exercise its broad discretion fairly and reasonably. In this regard, when the government elects to allow a contractor to continue performance past the contract completion date, it may waive the due date and thus its ability to terminate the contract for default for the contractor’s failure to meet it, provided two conditions are satisfied. First, the government fails to terminate within a reasonable period following the default, indicating forbearance. Second, the contractor relies on the government’s failure to terminate and continues performing under the terms of the contract with the government’s knowledge and express or implied consent. A waiver of the contract completion date under such conditions protects contractors who may be under the impression that time is no longer of the essence and, as a result, continue to expend significant effort and resources even after the performance deadline has passed. In construction contracts, the government’s imposition of liquidated damages after a performance date has passed or an express reservation of its rights in the performance deadline typically renders this waiver doctrine inapplicable. However, the completion deadline may be waived in construction contracts when the liquidated damages provision is not invoked or the government otherwise fails to adequately reserve its rights with respect to the completion deadline. Once the original completion deadline is waived, the government must establish a new deadline before it can terminate the contractor for default for failing to make progress.

more

Establishing Breach of Contract Due to Cardinal Change

TILLIT LAW Contract Claims Insights