shutterstock_2740412339.jpg

Government Waiver of Completion Deadlines in Construction Contracts

Government agencies have a prima facie case for default termination when a contractor fails to deliver performance in a timely manner. However, even when terminating the contractor on this basis, the government must exercise its broad discretion fairly and reasonably. In this regard, when the government elects to allow a contractor to continue performance past the contract completion date, it may waive the due date and thus its ability to terminate the contract for default for the contractor’s failure to meet it, provided two conditions are satisfied. First, the government fails to terminate within a reasonable period following the default, indicating forbearance. Second, the contractor relies on the government’s failure to terminate and continues performing under the terms of the contract with the government’s knowledge and express or implied consent. A waiver of the contract completion date under such conditions protects contractors who may be under the impression that time is no longer of the essence and, as a result, continue to expend significant effort and resources even after the performance deadline has passed. In construction contracts, the government’s imposition of liquidated damages after a performance date has passed or an express reservation of its rights in the performance deadline typically renders this waiver doctrine inapplicable. However, the completion deadline may be waived in construction contracts when the liquidated damages provision is not invoked or the government otherwise fails to adequately reserve its rights with respect to the completion deadline. Once the original completion deadline is waived, the government must establish a new deadline before it can terminate the contractor for default for failing to make progress.

In Armed Services Board of Contract Appeals (ASBCA) No. 62753, a decision issued on May 1, 2023, the contractor’s default termination was converted into one for the government’s convenience after the Board determined that the procuring agency had waived the original contract completion date and failed to establish a new completion date. On July 31, 2018, the Navy issued the relevant task order under a previously awarded indefinite delivery, indefinite quantity (IDIQ) construction contract for the design and construction of a vestibule and replacement of the doors in Building 261 at the Naval Support Activity (NSA) Bahrain. The task order specified September 29, 2019, as the completion date and included a liquidated damages provision, establishing a $400 per calendar day rate for delay. The contractor had difficulty obtaining the necessary aluminum doors from its Italian supplier and, in June 2019, proposed installing anti-blast steel doors instead at no additional cost to the government. After a Navy contracting specialist indicated agreement with this request, the contractor submitted a proposal requesting a 180-day time extension in July 2019. On September 9, 2019, the Navy issued a unilateral modification with a partial notice to proceed but stating that the contract completion date remained unchanged. On September 25, 2019, four days before the task order completion date, the contractor submitted proposed specifications and drawings for the doors. The project remained incomplete as the September 29, 2019, deadline passed.

On October 15, 2019, the contracting officer’s representative (COR) sent an email to the contractor requesting information regarding the September 25, 2019 submittal. Over the next few months, the Navy and the contractor continued to communicate regarding a modification for the steel doors, with the contractor requesting additional time to complete the project. On January 5, 2020, the Navy sent a cure notice, which the contractor did not receive. The next day, the Navy project manager approved the contractor’s hardware submittal. On January 15, 2020, the government construction manager provided the contractor instructions for submitting product data and shop drawings. Both the project manager and the construction manager failed to mention the cure notice or the liquidated damages and made no attempt to reserve the government’s rights in the project completion date. On February 11, 2020, the Navy issued a show-cause notice to the contractor for failing to perform the task order within the time specified in its terms. The contractor was advised that the Navy was considering terminating the contract for default. Following a February 13, 2020, meeting with the government in Bahrain, the contractor placed an order for hardware and engaged a subcontractor for installation. On March 11, 2020, the contracting officer (CO) issued a modification directing the contractor to stop all work on the project. On September 15, 2020, the CO terminated the task order for default for the contractor’s failure to perform within the specified time. The contractor filed a timely appeal at the ASBCA.

In the appeal before the Board, the contractor argued that the termination for default was not justified because the Navy had waived the project completion date and failed to establish a new date. Although the CO terminated the task order for failure to perform within the specified time, the Navy argued before the Board that the default termination was justified because the contractor did not make adequate progress or provide necessary assurances of timely performance or cure. The Board agreed with the contractor despite the September 9, 2019, modification indicating that the completion date remained unchanged. The waiver doctrine, which is typically inapplicable in construction contracts, was applicable in this case. In this connection, the Navy’s first modification had failed to adequately preserve its rights in the completion date. The Board noted that it was unrealistic for the September 9, 2019, modification to retain the project completion date while simultaneously issuing a partial notice to proceed for work that would take months to complete. Thus, it was apparent that neither party expected the work to be completed by September 29, 2019, at the date of the issuance of the first modification. Moreover, the September 9, 2019, modification failed to even mention the task order’s liquidated damages clause or otherwise expressly reserve the government’s rights. Under the circumstances, the modification’s mere statement that the contract completion remained the same was insufficient to preserve the government’s rights in the original task order completion date. The Navy also failed to assess liquidated damages in the period following the September 29, 2019, completion date. Accordingly, the waiver doctrine applied in this case, even though a construction contract was involved.

Next, the Board discussed the application of the waiver doctrine factors to hold that the Navy had indeed waived the task order’s completion date. First, the Navy had failed to terminate the task order for default within a reasonable period following the default, which demonstrated forbearance. After the original completion date passed, the Navy did not assess liquidated damages or issue a stop work order for months. Instead, the Navy allowed the contractor to muddle through for six months, while continuing to authorize work on the project. This indicated to the contractor that time was no longer of the essence. Furthermore, the task order was not terminated for default until September 15, 2020, which was almost a year after the original contract completion date. Second, the contractor relied on the Navy’s failure to terminate and continued performance with the Navy’s knowledge and consent. Between the September 29, 2019, completion date and the issuance of the March 11, 2020, stop-work order, the contractor relied on Navy communications and authorizations and continued performance under the task order. During this time, the contractor placed orders for hardware and even engaged a subcontractor for installation. Thus, the second condition of the waiver doctrine was satisfied as well, and the Board held that the Navy had waived the September 29, 2019, completion date.

The Board determined that although the CO had terminated the task order for the contractor’s failure to perform the required work within the time specified in the task order, the Navy was nevertheless permitted to change its rationale for the default to the contractor’s failure to make progress. However, even the Navy’s changed rationale for default was rejected as the agency had not only waived the September 29, 2019, completion date but also failed to establish a new performance completion date. In this regard, the Board reminded the parties that after the government waives a contract completion date, it cannot terminate the contract for default based on the contractor’s failure to make progress without establishing a new completion date with which to measure the contractor’s alleged failure to make progress. Here, the Navy failed to establish a new contract completion date following the waiver of the September 29, 2019 deadline either unilaterally or in mutual agreement with the contractor. Therefore, the Navy’s revised rationale for default, based on the contractor’s failure to make progress, was not justified because the Navy waived the original completion date and failed to establish a new contract completion date. Furthermore, the Navy CO’s original rationale for the default termination, which was for the contractor’s failure to perform within the specified time, was also not justified because the government had waived the original completion date. Consequently, the contractor’s appeal of the Navy’s default termination decision was sustained, and the Board converted the default termination to one for the government’s convenience.

The government may waive the contract completion deadline if it elects to allow the contractor to continue performance beyond the original deadline. Such a waiver is more likely to be found in supply contracts because supply contractors that continue to operate in default typically incur costs that may not be recovered if the government later terminates the contract for default for their failure to meet the contract completion deadline. On the other hand, construction contracts generally allow payment for work performed after the completion deadline, with liquidated damages imposed as a remedy for the contractor’s failure to meet it. However, as demonstrated in the case above, the waiver doctrine may apply to construction contracts when the government does not adequately preserve its rights in the default deadline or assess liquidated damages. For the government to waive the completion deadline, it must indicate forbearance by failing to terminate the contract within a reasonable period following the default. Additionally, the contractor must demonstrate its reliance on the government’s failure to terminate by continuing performance after the original deadline, with the government’s knowledge and consent. The totality of the circumstances is considered to determine whether a waiver has occurred, including any government notice reserving the right to terminate for default. However, the mere presence of such a notice does not mean that waiver has not occurred. If the government waives the original completion deadline, it may no longer terminate the contract for default for the contractor’s failure to meet that deadline. Once the original deadline is waived, the government must also establish a new completion deadline before it can terminate the contractor for default for a failure to make progress or meet the new deadline.

This Federal Contract Claims Insight is provided as a general summary of the applicable law in the practice area and does not constitute legal advice. Contractors wishing to learn more are encouraged to consult the TILLIT LAW PLLC Client Portal or Contact Us to determine how the law would apply in a specific situation.

Related Insights

TLF-Contract-Claims-Insight-53.jpg

The government may terminate a federal contract if the contractor fails to meet its contractual obligations. The contracting officer (CO), in such cases, issues a final decision terminating the contract for default and outlines the reasons for the default. In the event of a termination for default, the government is only liable to the contractor for the portion of the contract that was already performed. While the CO may exercise discretion to terminate a contract for default, such a decision is appealable to the Board of Contract Appeals or the Court of Federal Claims (COFC) pursuant to the Contract Disputes Act (CDA). The CO’s decision to terminate may be set aside by the adjudicative forum if it is arbitrary, capricious, or constitutes an abuse of the CO’s discretion. For instance, a decision to terminate for default may be arbitrary and capricious if there is a lack of nexus between the CO’s decision to terminate the contract for default and the contractor’s performance on the contract. In such situations, while the concerned adjudicative forum may lack the ability to provide injunctive relief, it may nevertheless convert the CO’s default termination to one for the government’s convenience.

more
TLF-Contract-Claims-Insight-69.jpg

The government retains the right to terminate a contract for default when the contractor fails to meet its performance obligations. The default termination, commonly considered one of the most undesirable outcomes for contractors, may nevertheless be converted into a termination for the government’s convenience if, on appeal, the government fails to prove that its default termination decision was justifiable. Notably, when the contractor appeals the government’s decision to terminate its contract for default, it is the government’s burden to prove default termination in the first instance. In other words, the government must demonstrate the correctness of its actions in terminating a contract for default. When contract modifications change the terms of the original contract such that the government’s default termination decision is no longer justified under the modified contract, adjudicative forums will typically convert the default termination to one for the convenience of the government, citing the change in circumstances from contract award to termination.

The Armed Services Board of Contract Appeals (ASBCA) in ASBCA 58866 and ASBCA 58867 converted the Army’s terminations for default for two similar contracts into terminations for convenience due to changes in the terms of the contracts due to later modifications. The Army awarded the underlying contracts for the acquisition of thousands of foreign language test items to assess the proficiency of military linguists. The contracts included the Federal Acquisition Regulation (FAR) 52.212-4 clause: “Contract Terms and Conditions—Commercial Products and Commercial Services.” During the performance, the government was only responsible for paying for the items it accepted, with no apparent definition of what constituted an acceptable item, presumably leaving the acceptability determination at the government’s discretion. The government retained intellectual property rights in both accepted and rejected items as the contracts provided the government sole ownership and exclusive rights to the deliverables. After the contracts were awarded to the same contractor, the Army issued nearly identical modifications, stating that any foreign language test items still required under the contracts but not accepted by the government would be “automatically descoped” from the contract. The Army eventually terminated the contracts for default, citing the contractor’s failure to provide the agreed-upon number of acceptable items.

more
Shutterstock_2240795647-2.jpg

Government contracts often include first article testing (FAT) requirements to ensure the contractor can supply a product that meets the contract requirements for acceptance. Such contracts incorporate the clause at FAR 52.209-3 (Contractor Testing) or FAR 52.209-4 (Government Testing) to impose FAT requirements on the contractor. Both clauses allow the government to waive the FAT requirements where the contractor has previously furnished supplies of identical or similar items that the government has accepted. An improper waiver of the FAT requirements that is inconsistent with the relevant FAR clause may be grounds for protest. In such protests, it is the procuring agency’s burden to establish that its decision to waive the FAT requirements was reasonable and in accordance with applicable procurement law and regulation. In addition to prior successful performance, if the agency can demonstrate that the contractor in question previously received FAT approval for the same items being procured, the Government Accountability Office (GAO) will typically not sustain the protest challenging the FAT waiver, unless the protester can present countervailing evidence that the item being supplied will not meet material solicitation requirements.

more
shutterstock_2378303535.jpg

Contractors may encounter delays when performing government contracts that increase the time or cost of performance. Contractors typically bear the risk of such increases for delays that are avoidable or otherwise within their control. When both the government and the contractor are responsible for a delay, neither party can recover damages unless the delay can be clearly apportioned and the increased expenses can be attributed to each party. To establish entitlement to an extension based on an excusable delay or to monetary damages for a compensable delay, contractors must demonstrate that the delay was caused by unforeseen events beyond their control and without their fault or negligence. In addition, contractors must show that the unforeseeable events delayed the overall contract completion timeline by impacting the critical path of performance. Notably, in cases involving a delivery schedule extended by the parties’ agreement, delays caused by either party before the agreement are excluded from consideration, so neither party may recover for delays before the date of the agreement. The government may terminate a contract for default due to the contractor’s failure to complete contract performance in a timely manner. Once terminated for this cause, the contractor may prove the excusability of the delay to convert the default termination into a termination for the government’s convenience. However, an impact on the overall schedule and the critical path must be demonstrated to establish the compensability of the delay.

more

Government Waiver of Completion Deadlines in Construction Contracts

TILLIT LAW Contract Claims Insights