Shutterstock_648122044.jpg

Disputing Unilateral Definitization Actions

Some projects require the contractor to begin performance immediately, with the urgency of the government requirement providing no time to establish terms, specifications, or prices. The government may enter into undefinitized contract actions (UCAs) or letter contracts for such projects. The contract clause at Federal Acquisition Regulation (FAR) 52.216.25 provides the process for the definitization of UCAs. Since UCAs permit performance without firmly established terms such as pricing, procuring agencies are expected to agree on the undefinitized contract terms in a timely manner after the commencement of performance. When the agency and the contractor cannot agree on a firm price, the FAR definitization clause allows the contracting officer (CO) to conclude negotiations and unilaterally determine a reasonable price. Notably, because the definitization clause expressly permits it, the CO’s unilateral establishment of pricing is considered an act of contract administration and not a government claim. Consequently, if the contractor does not agree with the CO’s unilaterally established price, it must file a claim with the CO before appealing that decision at a relevant Board of Contract Appeals (BCA) or the Court of Federal Claims (COFC).

In an April 2023 decision, the Court of Appeals for the Federal Circuit resolved this issue on appeal by affirming an Armed Services Board of Contract Appeals (ASBCA) decision. That appeal involved two UCAs the United States Air Force entered into to upgrade the F-16 Fighting Falcon aircraft. When the Air Force and its contractor could not agree upon a price despite years of negotiations, the CO unilaterally definitized the UCAs at approximately $1 billion. Considering the CO’s definitization actions to be government claims, the contractor filed an appeal directly with the ASBCA, alleging that the CO failed to establish a reasonable price per the requirements of the UCAs. The contractor sought a declaratory judgment that the CO’s unilateral definitizations were inconsistent with the FAR, which required the CO to definitize the UCAs at a reasonable price. The Air Force moved to dismiss the contractor’s appeal for failing to submit a certified claim and requesting the CO’s final decision per CDA requirements. The ASBCA agreed with the agency’s position and dismissed the appeal for lack of jurisdiction. Subsequently, the contractor filed its appeal with the Federal Circuit, with the sole issue on appeal being whether the CO’s definitizations were government claims directly appealable to the ASBCA.

The Federal Circuit pointed to its previous decisions in which it held that the FAR definition of a “claim” requires the government or the contractor to expressly assert entitlement to relief sought. Stated another way, the claim must be a demand for something due or something believed to be due. The Court explained that when the Air Force COs unilaterally definitized the pricing terms of the UCAs, they were simply following the agreed-upon procedures provided in the definitization clause for finalizing the contract terms. Thus, the COs did not make a demand or an assertion seeking entitlement to something due. Similarly, the government did not seek relief against the contractor after completing the definitization process. The Court compared the unilateral price definitizations to previous cases involving a government claim, such as cases where the government sought a non-monetary remedy under the contract’s inspection clause and where the government terminated the contract for default. The Court noted that the CO’s actions in those cases were necessarily different from the definitization actions in the present case because the CO’s actions there amounted to a demand or an assertion by the government against the contractor. Meanwhile, the definitization actions in the present case were simply administration actions expressly permitted under the contract’s definitization clause.

Letter contracts or UCAs are acquisition flexibilities that permit contractors to immediately begin performance on urgent government requirements before all the contract terms, like pricing, are definitized. The definitization clause in the FAR requires procuring agencies to negotiate with the contractor and define the terms in a timely manner after the commencement of performance. If the parties cannot agree on the undefinitized terms, the CO may conclude negotiations and unilaterally establish the terms, including firm pricing. In such a scenario, the CO’s actions in establishing the pricing terms do not amount to a government claim as they do not constitute a demand or an assertion seeking entitlement to something due or something believed to be due. Such actions are considered administrative actions because they are expressly authorized under the contract’s definitization clause and are, therefore, subject to traditional contractor claims under the CDA. Thus, contractors seeking to assert that the CO failed to set a reasonable price when unilaterally establishing pricing under the definitization clause may not directly appeal the definitization action at a relevant BCA or the COFC. In such situations, contractors should first file a claim with the CO and request his final decision before appealing that decision if necessary.

This Federal Contract Claims Insight is provided as a general summary of the applicable law in the practice area and does not constitute legal advice. Contractors wishing to learn more are encouraged to consult the TILLIT LAW PLLC Client Portal or Contact Us to determine how the law would apply in a specific situation.

Related Insights

TLF-Federal-Procurement-Insight-6.jpg

Federal government contracting operates under a well-defined and highly regulated framework of rules and procedures. However, unforeseen circumstances like natural disasters or national emergencies often disrupt the typical procurement process. Recognizing this, the Federal Acquisition Regulation (FAR) contemplates the need for emergency acquisition flexibilities for contracting officers under special circumstances such as disasters, contingencies, or presidential declarations so that critical work continues. Notably, FAR 18.001 defines emergency acquisition flexibilities as flexibilities provided with respect to any acquisition that is used to facilitate:

  • A contingency operation.
  • The defense against or recovery from cyber, nuclear, biological, chemical, or radiological attacks.
  • The provision of international disaster assistance.
  • A presidential emergency declaration or a major disaster declaration.

FAR 18.1 lists several flexibilities available to contracting officers in emergency acquisitions, provided certain conditions are met. Emergency acquisition flexibilities that are most relevant to the administration of federal government contracts include:

more
Shutterstock_1059713198.jpg

A claim under the Contract Disputes Act (CDA) must first be presented to and denied by the contracting officer (CO) before it can be appealed to a Board of Contract Appeals (BCA) or the Court of Federal Claims (COFC). Adjudicative forums have consistently held the CDA’s presentment requirement to be jurisdictional. That is, for a BCA or the COFC to exercise jurisdiction over a CDA appeal, the underlying claim must first have been presented to the CO for a final decision. Contractors may satisfy the presentment requirement by submitting the claim to the CO in accordance with the requirements of the CDA. While the CDA does not require the claim to be submitted in a particular form, it must typically provide a clear and unequivocal statement that gives the CO adequate notice of the basis and amount of the claim. The CO must then issue a final decision on the claim. The contractor may appeal the CO’s final decision at a BCA or the COFC within 90 days or 12 months, respectively.

In Avant Assessment v. U.S., No. 20-1185C, a decision issued on May 7, 2024, the COFC dismissed an appeal from a CDA claim for a lack of subject matter jurisdiction because the contractor failed to first present its claim to the CO. The appeal was part of a long-running litigation relating to contracts first issued by the U.S. Army in 2011 for foreign language testing materials to assess the proficiency of military linguists. The Army terminated the contracts for default in 2013, but following a successful appeal at the Armed Services Board of Contract Appeals (ASBCA), the default termination was converted into a termination for the government’s convenience. Following the successful convenience conversions, the contractor submitted termination settlement proposals to the CO, which were denied. After the CO’s denial, the contractor again appealed the CO’s final decision to the ASBCA. Notably, during the discovery phase in the second round of ASBCA litigation, the contractor learned that the government had not only retained the rejected testing materials but also “used” them by transferring them to a third party. Therefore, the contractor demanded payment for the rejected test materials. The contractor alleged that the Army had constructively accepted the rejected testing materials by retaining and using them after rejection. Alternatively, the contractor argued that the Army improperly rejected the testing materials. The ASBCA dismissed a large portion of the contractor’s claim for lack of jurisdiction since the contractor’s constructive acceptance claims had not first been first presented to the CO.

more
Insight #25-5.jpg

The Contract Disputes Act (CDA) requires that a contractor present its claim to the contracting officer (CO) before an appeal or suit may be properly filed on that claim. This presentment requirement can be characterized as the linchpin of the contract appeals process under the CDA and is also the last clear chance for the government and the contractor to avoid appeals litigation. Once the contractor submits its claim to the CO, the CDA requires the CO to issue his final decision within 60 days of receiving the claim if the claimed amount is less than $100,000. For certified claims over $100,000, the CO must either issue his final decision within 60 days or notify the contractor within 60 days of the time within which a final decision will be issued. The CDA also requires that the CO issue the final decision within a reasonable time, accounting for factors such as the size and complexity of the claim and the adequacy of information provided by the contractor in support of its claim. In the event of an undue delay by the CO in issuing a final decision, the contractor may request the appeals adjudicative forum to exercise its discretion and direct the CO to issue a decision within a specified period. If the CO fails to issue a decision within that period, the contractor’s claim may be “deemed denied” and considered appealable under the CDA.

more
Shutterstock_73059598.jpg

The Contract Disputes Act (CDA) provides contractors with alternate forums to resolve claims relating to their federal contracts. After submitting their claim to the contracting officer (CO) and either receiving a denial or a deemed denial on their claim, contractors may appeal the CO’s final decision to either an appropriate Board of Contract Appeals (BCA) or the Court of Federal Claims (COFC). However, once the contractor elects one of the two dispute adjudicative forums and appeals the CO’s adverse decision after receiving notice of the available options, it may not then change forums. Also known as the election doctrine, this rule ensures that once the contractor chooses the forum in which to lodge its appeal under the CDA, it is bound by the election decision and may no longer pursue its appeal in the alternate forum. For the doctrine to apply, the contractor must make an informed, knowing, and voluntary decision to pursue the appeal in one of the two forums with jurisdiction. Once the action is filed in one forum, the other forum must dismiss any subsequently filed appeals concerning the same claim for lack of jurisdiction.

more