Claims Involving Warranty of Utilities

Performance of contracts on government sites often require contractor’s access to utilities such electricity, water, gas etc. In such contracts, the government may provide a warranty regarding the availability of utilities. The inclusion in the contract of the “Availability and Use of Utility Services” standard clause at FAR 52.236-14 as prescribed in FAR 36.514 is interpreted as a government warranty of utilities. Fixed-price construction contracts typically contain this standard clause when performance is contemplated on government sites, the available utilities are adequate for the needs of both the government and the contractor, and it is in the government’s interest to furnish the utilities. Unless the contract states otherwise, the standard clause makes it the contractor’s responsibility to pay utility charges at the prevailing rates charged to the government. When the utilities are produced by the government, the contractor is responsible for utility payments based on reasonable rates determined by the contracting officer (CO). In contracts without the standard clause, claims adjudicative forums review the relevant contractual language to determine whether the government has warranted the availability of utilities. Both the standard clause and relevant contract language are strictly interpreted in accordance with their plain meaning to determine if a warranty of utilities exists and whether the contractor is responsible for the payment of any utility charges.

In Armed Services Board of Contract Appeals (ASBCA) No. 42916, 42927, a decision issued on October 31, 1991, the Board reviewed the contract documents in the absence of the standard clause and held that the government had warranted the availability of gas service. The contractor was awarded two contracts for the construction of various buildings at the Naval Station Ingleside in Corpus Christi Bay, Texas. Both contracts required the contractor to furnish, install, and test hot water heating boilers. While the contracts did not include the clause at FAR 52.236-14, they contained a general paragraph titled “Utilities for Construction and Testing,” which was silent about gas service. The contracts also included a utility site plan drawing that showed the location of an existing gas line. Due to delays in a separate gas service contract, the contractor was prevented from completing performance in a timely manner. In the appeal before the ASBCA, the Board reviewed the contract and found that although it placed responsibility for furnishing certain utilities required for construction and testing on the contractor, it did not expressly mention gas service. Meanwhile, the contract drawings showed an existing gas line. The Board interpreted the contract documents and drawings together as a government warranty of gas service. Consequently, it was held that the government was responsible for furnishing gas service but had failed to do so in a timely manner.

In Labor Board of Contract Appeals (LBCA) No. 1997-BCA-4, the Board determined that the contractor was responsible for electricity charges during performance under the “Availability and Use of Utility Services” standard clause incorporated by reference into the contract. The Department of Labor (DOL) awarded the underlying fixed-price contract for the demolition, renovation, and construction of buildings at the Job Corps Center in San Jose, California. During the preconstruction conference, the government provided written materials stating that reasonable amounts of water and electricity would be provided. The contractor argued that this language created an exception to the general rule under FAR 52.236-14(a) that the contractor was responsible for the cost of using electricity. The Board noted that although not customary, the standard FAR clause regarding utilities and applicable case law established that, under certain circumstances, the contractor may not be required to pay utility charges. However, in this case, the text in the preconstruction conference materials alone was insufficient to create such an exception. Additionally, there was no factual support for the contractor’s allegations that the government made repeated statements at the preconstruction conference assigning liability for the electricity costs to the government. The contractor seemed to have conflated the distinction between the provision of electricity and the payment of electricity charges in interpreting the preconstruction conference materials. Ultimately, the Board held that the government had warranted the provision of electricity, but the contractor was required to pay for the electricity charges.

The government provides a warranty of utilities by the incorporation of the “Availability and Use of Utility Services” standard clause at FAR 52.236-14. Even in the absence of the standard clause, other relevant contract terms and conditions may amount to a warranty. Applicable case law has established that in most construction contracts it is customary for the government to provide certain utilities, such as electricity. Under the standard clause, while the government is responsible for the provision of reasonably required amounts of utilities, the contractor pays for the utilities it consumes. Contractors should remember that although the standard clause places responsibility for paying utility charges on the contractor, other contract terms may still be negotiated to shift this burden to the government. In other words, the standard clause does not preclude the contractor from negotiating the recovery of utility costs from the government. In a dispute over whether the government or the contractor is responsible for the utility charges, adjudicative forums will strictly interpret the language of the standard clause, if included in the contract, and any other applicable terms and conditions. Ultimately, while it may be relatively straightforward for contractors to establish the existence of a government warranty of utilities, especially in contracts containing the standard clause at FAR 52.236-14, proving government liability for utility charges may be more challenging unless the contract establishes an exception to the normal requirement that the contractor pays the cost of using available utilities.

This Federal Contract Claims Insight is provided as a general summary of the applicable law in the practice area and does not constitute legal advice. Contractors wishing to learn more are encouraged to consult the TILLIT LAW PLLC Client Portal or Contact Us to determine how the law would apply in a specific situation.

Related Insights

Shutterstock_2211056755.jpg

The government provides contractors with a variety of information during the solicitation process before a contract is awarded. Such information may be furnished through pre-award conferences, questions and answers, solicitation attachments, specifications, diagrams, drawings, contract provisions, etc. When the government misstates material facts during the contract formation process, it may later be liable under express provisions of the contract or for breaching an implied warranty that it furnishes correct information. In this regard, when the government provides incorrect representations and directs or expects prospective offerors to base their contract pricing on those misrepresentations, the government is responsible for any losses the contractor suffers as a result of its reliance on that information. In other words, when the government instructs offerors to base their pricing on data it furnishes, it assumes responsibility for ensuring that the data accurately reflects the conditions the contractor will encounter during performance. In such cases, as long as the contractor can demonstrate that the government's information was incorrect, it need not prove the government's intent to deceive or bad faith. Furthermore, the contractor may also not need to prove that the incorrect information was inadequately or negligently prepared.

more
Shutterstock_1721477512-2.jpg

The interpretation of government contracts begins with the plain language of the contract, with meaning assigned to all clauses within the context of the contract as a whole. When contract language is susceptible to more than one interpretation falling within the zone of reasonableness, an ambiguity exists that may be resolved by considering extrinsic evidence. If the ambiguity is still not resolved, the doctrine of contra proferentum is applied for interpretation. Under the doctrine, the ambiguity is resolved in favor of the non-drafting party, which is typically the contractor. However, for contra proferentum to apply, the ambiguity must be latent rather than a patent ambiguity. That is, the ambiguity must not be so glaring or obvious as to place upon the non-drafting party the duty to inquire before contract formation. Under this exception to the contra proferentum doctrine, if the non-drafting party fails to timely inquire about a patent ambiguity, the ambiguity is resolved against it. Furthermore, contractors seeking application of contra proferentum must show that they relied on their reasonable interpretation of the ambiguity in developing their offer.

more
Shutterstock_1176097972-2.jpg

The primary method of interpreting a government contract is to determine the “plain meaning” of the disputed language. The plain meaning method is applied when the contractual language is clear and unambiguous. Under this method, contract terms are interpreted according to the plain and ordinary meaning of the disputed words, and extrinsic evidence may not be relied on for interpretation. In determining the plain meaning of the disputed language, adjudicative forums may look to the dictionary definitions of the relevant words. In doing so, the words are assigned the meaning they had at the time of contract formation. In situations where the disputed words have more than one dictionary definition, the definition that is most appropriate within the context of the whole contract prevails. However, even when the plain meaning interpretation is applied, the contract must be construed as a whole and interpreted to harmonize and give reasonable meaning to all its parts without rendering terms superfluous or meaningless.

In Armed Services Board of Contract Appeals (ASBCA) No. 62461, issued on August 17, 2021, the Army Contracting Command, Rock Island Arsenal, awarded a task order under the awardee’s General Services Administration (GSA) IT Schedule 70 for Network and Communications, Engineering and Installation Support for the Army in Afghanistan and Kuwait. The task order contained the clause at Federal Acquisition Regulation (FAR) 52.217-8, Option to Extend Services (Nov 1999), which stated in pertinent part that “[t]he Contracting Officer may exercise the option by written notice to the Contractor within 90 days before the expiration of the contract.” Following the award, the contractor encountered difficulties retaining staff at the proposed labor rates under the primarily firm-fixed-price task order, leading the contractor to discuss with the government the possibility of terminating the contract. Despite the contractor’s staffing difficulties, the Army notified the contractor four days before the base period ended that it would exercise its option to extend the task order.

more
shutterstock_2831254353.jpg

When the contractor’s performance requires the government to furnish a work site, failure to make the site available may result in liability for the government. Even when furnished by the government, the availability of a work site may depend on many variables. Therefore, unless the contract can be interpreted to imply an unqualified guarantee, contractors may find it challenging to prove the existence of a warranty of site availability. The extent of definitiveness of the contract language pertaining to availability of the work site is key in determining whether a warranty exists. General government representations specifying a date for making a work site available are typically insufficient to amount to a warranty absent express and unqualified contractual language. If the availability of the site is dependent on factors outside the government’s control, such as completion of performance on another contract, a finding that a warranty of site availability exists becomes highly unlikely. On the other hand, if the government alone has complete control over site availability, it makes it more likely that a claims adjudicative forum will find that a warranty exists. Additionally, certain facts may indicate the presence of a warranty of site availability, including the critical importance of the site and the limited period within which the work must be performed. Similarly, contract clauses can be important indicators, with a warranty of site availability more likely to be found in contracts that include a suspension of work clause.

more

Claims Involving Warranty of Utilities