Shutterstock_1176097972-2.jpg

Plain Meaning Interpretation in Federal Contracts

The primary method of interpreting a government contract is to determine the “plain meaning” of the disputed language. The plain meaning method is applied when the contractual language is clear and unambiguous. Under this method, contract terms are interpreted according to the plain and ordinary meaning of the disputed words, and extrinsic evidence may not be relied on for interpretation. In determining the plain meaning of the disputed language, adjudicative forums may look to the dictionary definitions of the relevant words. In doing so, the words are assigned the meaning they had at the time of contract formation. In situations where the disputed words have more than one dictionary definition, the definition that is most appropriate within the context of the whole contract prevails. However, even when the plain meaning interpretation is applied, the contract must be construed as a whole and interpreted to harmonize and give reasonable meaning to all its parts without rendering terms superfluous or meaningless.

In Armed Services Board of Contract Appeals (ASBCA) No. 62461, issued on August 17, 2021, the Army Contracting Command, Rock Island Arsenal, awarded a task order under the awardee’s General Services Administration (GSA) IT Schedule 70 for Network and Communications, Engineering and Installation Support for the Army in Afghanistan and Kuwait. The task order contained the clause at Federal Acquisition Regulation (FAR) 52.217-8, Option to Extend Services (Nov 1999), which stated in pertinent part that “[t]he Contracting Officer may exercise the option by written notice to the Contractor within 90 days before the expiration of the contract.” Following the award, the contractor encountered difficulties retaining staff at the proposed labor rates under the primarily firm-fixed-price task order, leading the contractor to discuss with the government the possibility of terminating the contract. Despite the contractor’s staffing difficulties, the Army notified the contractor four days before the base period ended that it would exercise its option to extend the task order.

Following the notification, the Army exercised its right to extend services for a three-month period under FAR 52.217-8 on the last day of the base period. Later, the contractor filed a claim for approximately $3.7 million for its excess incurred costs. In the appeal that followed the deemed denial of the claim, among other arguments, the contractor asserted that the Army had failed to timely exercise the option in accordance with the clause at FAR 52.217-8. Specifically, the contractor contended that since FAR 52.217-8 allowed the contracting officer to exercise the option “within 90 days before the expiration of the contract,” the Army was required to exercise the option at least 90 days before the expiration of the base period of performance. Stated another way, the contractor argued that the Army’s exercise of the option was untimely because the word “within” in the clause should be read as “at least.”

The Board disagreed with the contractor and interpreted the disputed language of FAR 52.217-8 based on the plain meaning of the word “within” and its ordinary use. The Board quoted the definition of the word “within” from the 3rd edition of the New Oxford American Dictionary. Per this definition, “within” meant “inside the range of” or “occurring inside (a particular period of time)”. In accordance with this definition, the Board found that the government had timely exercised the option because it did so inside the 90-day period preceding the contract’s end. The Board rejected the contractor’s interpretation of “within 90 days,” which would have required the Army to exercise the option no later than 90 days before the base period expired. The decision noted that the contractor’s interpretation was not supported by precedent or the plain meaning of the disputed words. Consequently, the Board held that the Army had properly exercised the option to extend services.

Plain meaning interpretation is the primary method employed to interpret government contracts. Under this method, words are assigned their ordinary, everyday meanings. When the meaning of the disputed terms is plain and unambiguous on the face of the contract, parties may not introduce extrinsic evidence to support their respective interpretations. Extrinsic evidence may only be relied upon when the language is ambiguous and open to more than one reasonable interpretation. As was the case in the decision described above, adjudicative forums may rely on contemporaneous dictionary definitions of the relevant words to determine their plain meaning in order to resolve government contracts interpretation disputes. In situations where a word has multiple dictionary definitions, the definition that is most appropriate given the context of the entire contract prevails. This is because even when the plain meaning method of interpretation is used, the contract is still construed as a whole, with reasonable meaning assigned to all its parts.

This Federal Procurement Insight is provided as a general summary of the applicable law in the practice area and does not constitute legal advice. Contractors wishing to learn more are encouraged to consult the TILLIT LAW PLLC Client Portal or Contact Us to determine how the law would apply in a specific situation.

Related Insights

Shutterstock_1244565646.jpg

When interpreting the terms of a government contract, contractors should generally look for the “plain-meaning” of the contract, assigning words their ordinary meaning. However, an equally important rule of federal contract interpretation requires a “whole-text” interpretation of the contract within the context of its structure and the logical relation of its various parts. Pursuant to this rule and the interpretative principles derived from and related to it, when interpreting a federal contract, the whole contract should be taken together such that none of its parts are rendered superfluous or ineffective. Put another way, in determining the meaning the parties intended to assign to specific contract terms or clauses, contractors should read the contract as a whole and within the entire context of the procurement. Furthermore, the meaning assigned by a party to a particular clause or term must be in harmony with the other parts of the contract. Contractors should also be mindful of their duty to enquire about patent ambiguities.

Harmonious Reading and Conflict Avoidance

In reading a federal contract as a whole, contractors should interpret the contract provisions in harmony with each other. That is, provisions should be interpreted in a manner that renders them compatible with each other rather than in contradiction. For instance, in a 2013 case before the Court of Federal Claims (COFC), the contractor attempted to argue that the government was required to exercise all option years in an indefinite delivery/indefinite quantity (IDIQ) contract for supplying leased aircrafts with one base and seven option years. The contractor primarily based its argument on the fact that the contract referred to itself as a “long-term” contract on at least three separate occasions. However, in applying the “whole-text” cannon, the Court disagreed with the contractor’s interpretation. The Court explained that the contractor’s interpretation of “long-term” would convert the word “option” into its opposite and make it an obligation. Instead, the Court harmoniously interpreted “long-term” as merely describing the contract with an assumption that the government would exercise the option years.

more
Shutterstock_1817376860.jpg

A federal contract interpretation claim may involve requests for the meaning of contractual words, determination of the manner in which the contractor must undertake performance or supply of missing terms. Since the Contract Disputes Act (CDA) does not define a claim, adjudicative forums look to the definition of a claim provided in the Federal Acquisition Regulation (FAR). The FAR § 2.101 defines a claim as a written demand or assertion by one of the contracting parties seeking, as a matter of right, the payment of money in a sum certain, the adjustment or interpretation of contract terms, or other relief arising under or relating to the contract. Thus, the FAR definition of a claim includes non-monetary claims such as for the adjustment and interpretation of contract terms and claims for other relief. However, even claims for contract interpretation may have significant monetary consequences. Since the CDA requires certification of contractor claims over $100,000, contractors may consider certifying such contract interpretation claims to avoid potential dismissals for lack of certification in subsequent appeals. Including certifications can be particularly beneficial when a contractor has already incurred costs related to the claim at the time of submission, as such claims are often monetary claims disguised as interpretation claims.

more
Shutterstock_1721477512-2.jpg

The interpretation of government contracts begins with the plain language of the contract, with meaning assigned to all clauses within the context of the contract as a whole. When contract language is susceptible to more than one interpretation falling within the zone of reasonableness, an ambiguity exists that may be resolved by considering extrinsic evidence. If the ambiguity is still not resolved, the doctrine of contra proferentum is applied for interpretation. Under the doctrine, the ambiguity is resolved in favor of the non-drafting party, which is typically the contractor. However, for contra proferentum to apply, the ambiguity must be latent rather than a patent ambiguity. That is, the ambiguity must not be so glaring or obvious as to place upon the non-drafting party the duty to inquire before contract formation. Under this exception to the contra proferentum doctrine, if the non-drafting party fails to timely inquire about a patent ambiguity, the ambiguity is resolved against it. Furthermore, contractors seeking application of contra proferentum must show that they relied on their reasonable interpretation of the ambiguity in developing their offer.

more
Shutterstock_317810786.jpg

In government contract interpretation disputes, adjudicative forums may rely on extrinsic evidence of the parties’ prior course of dealing to interpret ambiguous terms. In this context, prior course of dealing refers to a sequence of previous conduct between the government and the contractor which can be fairly regarded as establishing a common basis of understanding for the purposes of interpretation. When the parties have interpreted the disputed terms in a certain manner in a previous contract, those terms are typically presumed to hold the same meaning in a later disputed contract, absent clear evidence of changed intent or the parties’ disagreement at the time of contract formation. Furthermore, for the parties to be bound by their prior course of dealing, they must have actual knowledge of the conduct and be aware that it can reasonably be construed as indicative of their common understanding or intentions. In such cases, after determining the existence of an ambiguity, the claims adjudicative forum may rely on prior course of dealing evidence to assign meaning to the disputed terms.

In Armed Services Board of Contract Appeals (ASBCA) No. 60448, issued on June 24, 2020, the Board determined that the contractor was entitled to an equitable adjustment as the parties’ prior course of dealing had established a common basis of understanding regarding the ambiguous terms. The U.S. Air Force issued the three underlying contracts for the production and delivery of Advanced Medium Range Air-to-Air Missiles (AMRAAM). The contracts were part of a series of annual contracts issued for over more than two decades under which the contractor delivered a specified number of missiles each year. As relevant to the interpretation dispute, the statements of content (SOCs), which are similar to statements of work, for the three contracts each contained two paragraphs that the Board determined were ambiguous. The first paragraph, SOC 2.a, required the contractor to produce a specified number of missiles (or lot) over a three-year period of performance. Meanwhile, the second paragraph, SOC 2.b, required the contractor to provide Systems Engineering/Program Management (SEPM) support for a one-year performance period.

more

Plain Meaning Interpretation in Federal Contracts

TILLIT LAW Federal Procurement Insights