TLF-Contract-Claims-Insight-6.jpg

Achieving Privity of Contract for Subcontractor Claims

Subcontractors under U.S. federal contracts cannot generally sue the government directly as they lack privity of contract with the government. Privity refers to a legal concept describing a relationship or nexus between contracting parties. The government often utilizes a two-tiered contracting system for procurements where it enters into a contract with the prime contractor that, in turn, contracts with subcontractor(s) to fulfill contractual requirements. Thus, in a federal contract, the government only has a privity of contract with the prime contractor, creating a legal buffer between the government and the subcontractor. Since subcontractors are not in privity with the government, the government does not waive its sovereign immunity, and subcontractors may not bring direct claims against the government.

However, as with most rules in U.S. federal contracting, the no subcontractor privity rule has its exceptions. These exceptions require that subcontractors looking to bring direct claims against the government must first establish a privity of contract with the government. That is, the contractor must successfully demonstrate that it explicitly or implicitly entered into a contract with the government.

o Asserting a Third-Party Beneficiary Claim

Subcontractors may assert claims as third-party beneficiaries of the prime contractor’s agreement with the government, provided they can demonstrate special contract provisions or payment arrangements that require the government to make joint payments to the prime and subcontractor or otherwise make direct payments to the subcontractor. Notably, to qualify as a third-party beneficiary, the subcontractor must be an intended direct beneficiary and not just an incidental or indirect beneficiary to the government contract. For instance, when a contract’s remittance clause is modified to allow the subcontractor control over government payments, the subcontractor qualifies as an intended third-party beneficiary with a right to sue the government directly for recovery. Finally, subcontractors looking to bring third-party beneficiary claims against the government may only do so at the COFC, as the Boards of Contract Appeals do not have jurisdiction over such claims.

o Proving the Existence of a Joint Venture

Contracting firms may also bring claims against the government if they can demonstrate that the relationship between the contractors was, in fact, a joint venture instead of a prime-sub relationship. FAR 9.601 recognizes joint ventures as a valid contractor teaming arrangement where two or more companies join together to create a legal entity that acts as a prime contractor. Since the joint venture contracts with the federal government as the prime contractor, the joint venture may bring its claim against the government as a legal entity. However, individual joint venture members may not generally assert a claim against the government.

o Demonstrating that the Prime Contractor was Acting as an Agent of the Government

Subcontractors can bring direct claims against the government if they can demonstrate that the prime contractor was merely acting as an agent of the government. Subcontractors may also establish privity with the government through the purchasing agent exception of the no subcontractor privity rule by showing the existence of a contracting provision or a formal intention to make the prime contractor the government’s purchasing agent. It should be noted, however, that subcontractors will generally find it challenging to establish privity of contract by showing that direct day-to-day contact with the government was so prevalent and persistent that it made the prime contractor a mere agent of the government.

o Otherwise Establishing Privity of Contract

Subcontractors may establish a direct privity of contract by showing that a contractual relationship exists between the subcontractor and the government. Direct privity may be established by showing an implicit or explicit contractual agreement depending on the specific facts. For instance, the teaming agreement may incorporate the prime contract with a modified disputes clause allowing the subcontractor to bring direct claims against the government, or the Court may otherwise find that the government and the subcontractor entered into an implied contract. It should be noted, however, that FAR 44.203 explicitly directs contracting officers not to consent to subcontracts that obligate them to deal directly with subcontractors.

This Federal Contract Claims Insight is provided as a general summary of the applicable law in the practice area and does not constitute legal advice. Contractors wishing to learn more are encouraged to consult the TILLIT LAW PLLC Client Portal or Contact Us to determine how the law would apply in a specific situation.

Related Insights

TLF-Contract-Claims-Insight-12.jpg

The U.S. Federal Government often utilizes federal supply schedule (FSS) contracts to purchase commercially available off-the-shelf software (COTS) software from reputable pre-vetted software vendors. These FSS contracts are administered by the General Services Administration (GSA), and they eliminate the need for lengthy open-market solicitations for common COTS software products. FSS contracts permit agencies to purchase COTS software products quickly and efficiently from pre-vetted software vendors using pricing that reflects volume discounts due to GSA’s government-wide purchasing leverage. Generally, the COTS software product manufacturer’s end-user licensing agreement (EULA) is incorporated into the procurement contract and dictates the Government’s use of the COTS software. The term “contractor” has been expressly defined in 41 U.S.C. § 7107(7) as a “party to a Federal Government contract other than the Federal Government.” Therefore, in COTS software product purchases, since the pre-vetted software vendor has the FSS contract with the Government, the COTS software product manufacturer is generally not considered a contractor in the traditional sense because it is not a party to the Government contract. Accordingly, since the CDA does not permit appeals by anyone who is not a party to a Government contract, COTS software product manufacturers are generally unable to bring contract claims against the Government under the CDA. However, subcontractors and certain third parties may achieve privity of contract with the Government under particular circumstances, which allows them to bring claims against the Federal Government under the CDA.

more
TLF-Contract-Claims-Insight-47.jpg

While there are ways in which subcontractors may achieve privity of contract, they may not generally bring direct claims against the Government due to a lack of privity. Therefore, subcontractor claims against the Government are typically asserted by prime contractors as pass-through claims. However, prime contractors may only bring such pass-through claims if they meet the requirements of the Severin Doctrine. First articulated by the Court of Claims in 1943, the Severin Doctrine bars pass-through subcontractor claims unless the prime contractor itself remains liable to claims by the subcontractor. While the Severin Doctrine has evolved through its application to various pass-through claims scenarios, at its outset, it barred the assertion of pass-through claims unless the prime contractor either reimbursed the subcontractor due to the Government’s fault or was at least liable to make such a reimbursement in the future.

Based on the principles of sovereign acts immunity and privity of contract as applied to government contracts, the Severin Doctrine requires the prime contractor to have at least some demonstrable exposure to subcontractor liability. To prevent pass-through claims through this affirmative defense, the Government typically points to any provisions in the subcontract that tend to exculpate the prime contractor from liability to the subcontractor. When entering teaming arrangements, contractors should be aware that if the subcontract agreement contains a clause completely or specifically exonerating a prime contractor from liability to the subcontractor for pertinent damages, then the prime contractor may not assert a related pass-through claim against the Government. Prime contractors are similarly barred from asserting pass-through claims if the subcontract specifically extinguishes prime contractor liability upon the meeting of certain requirements, such as the subcontractor being granted additional time or the acceptance of final payment.

more
TLF-Federal-Procurement-Insight-55.jpg

As a sovereign and a contracting party, the government holds the prerogative to terminate a government contract, either partially or completely, whenever it is in its best interest. While a contractor may pose certain challenges to the CO’s decision to terminate a contract, it is generally accepted that the government’s rights in this regard are practically limitless. The Federal Acquisition Regulation (FAR) outlines the methods through which the government may settle contracts it terminates for its convenience. Specifically, under FAR § 49.103, the government may settle contracts terminated for convenience through negotiated agreement, CO’s determination, costing-out under vouchers for cost-reimbursable contracts, or through a combination of these methods. Typically, when the government exercises its right to terminate a contract for convenience, it enters into a settlement agreement with the prime contractor. In turn, prime contractors are required to settle any subcontractor termination settlement proposals.

Once the government issues a notice terminating a contract for convenience, the prime contractor must terminate all subcontracts related to the terminated portion of the prime contract. Under FAR § 49.104, prime contractors are required to settle all outstanding liabilities that arise out of the termination of subcontracts and promptly notify the CO of any legal proceedings that may be instituted by a subcontractor. Additionally, FAR § 49.108 generally outlines the parties’ rights, obligations, and procedures pertaining to subcontractor settlement proposals. Notably, FAR § 49.108-2(b) makes it abundantly clear that the government’s rights to terminate the contract for convenience are unaffected by a prime contractor’s failure to include an appropriate termination clause in a subcontract. Therefore, contractors should review the termination clause of their subcontract agreements to ensure their rights are adequately protected in case of a termination for the government’s convenience.

more
Expanded Protestor Standing for Potential Subcontractors under Percipient.jpg

Government agencies are required to acquire and use commercially available products and services to the maximum extent practicable. In the implementation of 10 U.S.C. § 3453, government agencies are required to ensure that prime and subcontractors at all levels incorporate commercially available products and services as components of items supplied to the government. Under the Tucker Act, 28 U.S.C. § 1491(b)(1), interested parties are permitted to file suit in the Court of Federal Claims (COFC) challenging (1) a solicitation issued by a federal agency, (2) an award or a proposed award of a contract, or (3) any alleged violation of statute or regulation in connection with a procurement or a proposed procurement. The Federal Acquisition Streamlining Act (FASA) of 1994 contains a “task order bar” that removes from Tucker Act coverage any protests in connection with the issuance or proposed issuance of task or delivery orders that are below the monetary threshold of $25M for defense procurements and $10M for non-defense procurements.

On June 7, 2024, in Percipient.AI v. U.S. (23-1970), the Court of Appeals for the Federal Circuit (CAFC) addressed the interplay of these statutes to carve out a new rule conferring standing upon manufacturers of commercially available products and services to bring a protest alleging harm to their direct economic interests due to the government’s violation of 10 U.S.C. § 3453 – when their product or service has a substantial chance of meeting the government’s needs, either partially or completely, and when they take care not to directly or indirectly challenge the solicitation, contract award, or proposed contract award. The decision may be of particular interest to commercial software manufacturers that produce software in emerging sectors that satisfy at least some of the government’s solicited requirements in large-value procurements. In Percipient.AI, the National Geospatial-Intelligence Agency (NGA) issued the “SAFFIRE” solicitation contemplating a single award Indefinite Delivery, Indefinite Quantity (IDIQ) contract to sustain and improve its processes for obtaining and storing visual intelligence data and integrating those capabilities with a form of user-facing artificial intelligence (AI) called computer vision (CV). The NGA simultaneously solicited Task Order 1 of the IDIQ, which, in pertinent part, directed the contractor to develop and deliver the CV suite of systems. While the protestor produced commercial software that could meet the government’s CV system requirements, it could not meet the storage component of the contract. Therefore, in reliance on the government’s and the eventual awardee’s anticipated compliance with 10 U.S.C. § 3453, the protestor chose not to bid for or protest the SAFFIRE solicitation or the eventual contract award to a large systems integrator.

more

Achieving Privity of Contract for Subcontractor Claims

TILLIT LAW Federal Contract Claims Insights