Shutterstock_1244565646.jpg

Principle of Whole-Text Interpretation in Federal Contracts

When interpreting the terms of a government contract, contractors should generally look for the “plain-meaning” of the contract, assigning words their ordinary meaning. However, an equally important rule of federal contract interpretation requires a “whole-text” interpretation of the contract within the context of its structure and the logical relation of its various parts. Pursuant to this rule and the interpretative principles derived from and related to it, when interpreting a federal contract, the whole contract should be taken together such that none of its parts are rendered superfluous or ineffective. Put another way, in determining the meaning the parties intended to assign to specific contract terms or clauses, contractors should read the contract as a whole and within the entire context of the procurement. Furthermore, the meaning assigned by a party to a particular clause or term must be in harmony with the other parts of the contract. Contractors should also be mindful of their duty to enquire about patent ambiguities.

Harmonious Reading and Conflict Avoidance

In reading a federal contract as a whole, contractors should interpret the contract provisions in harmony with each other. That is, provisions should be interpreted in a manner that renders them compatible with each other rather than in contradiction. For instance, in a 2013 case before the Court of Federal Claims (COFC), the contractor attempted to argue that the government was required to exercise all option years in an indefinite delivery/indefinite quantity (IDIQ) contract for supplying leased aircrafts with one base and seven option years. The contractor primarily based its argument on the fact that the contract referred to itself as a “long-term” contract on at least three separate occasions. However, in applying the “whole-text” cannon, the Court disagreed with the contractor’s interpretation. The Court explained that the contractor’s interpretation of “long-term” would convert the word “option” into its opposite and make it an obligation. Instead, the Court harmoniously interpreted “long-term” as merely describing the contract with an assumption that the government would exercise the option years.

Avoiding Interpretations that Render Terms Superfluous

In reading a federal contract as a whole, contractors should typically avoid interpretations that make certain terms, clauses, or portions of the contract superfluous or ineffective. Such an interpretation ensures that the entirety of the contract is afforded its intended meaning and purpose. A Federal Circuit case from 1985 involving a construction contract with patently ambiguous rebar requirements provides an example of the application of this interpretive principle. In that case, the contractor suffered increased costs due to the incorrect rebar installation. In seeking an equitable adjustment, the contractor argued that the government had accepted the contractor’s rebar installation method because it had a quality assurance representative on-site responsible for ensuring that the contractor complied with the government’s plans and specifications. However, clause 10 of the contract’s general provisions specifically stated that no inspection or test by the government would be construed as implying acceptance of the work. In applying the “whole-text” interpretive cannon, the Court ruled that the contractor’s interpretation could not be accepted as it would render clause 10 of the contract’s general provisions redundant. In rejecting the contractor’s interpretation, the Court adopted an interpretation that gave meaning to clause 10 of the contract rather than rendering it superfluous.

Giving Preference to Specific over General Contractual Terms

Despite reading the contract as a whole and attempting to avoid conflict between its various terms, contractors may still find inconsistencies between certain terms or provisions. In such situations, when the different meanings of the terms cannot be reconciled with each other, contractors should accept specifically drafted contractual terms and provisions over general ones. In the COFC case involving the supply of leased aircrafts described above, in addition to pointing out its obligation to read the contract as a whole, the Court also rejected the contractor’s interpretation by explaining that the general description of the contract as “long-term” could not be favored over the specific option provisions. In that case, requiring a mandatory exercise of option years in the absence of other limiting language would require giving the contract’s general description of itself as a “long-term” contract preference over the government’s specifically defined right to exercise its options. In quoting a previous decision by the Federal Circuit, the COFC elaborated that when general and specific terms are in apparent conflict, the terms and provisions of the contract that relate specifically to a particular matter are preferred over the general language.

A federal government contract contains many interdependent parts that provide it context and meaning. In case of ambiguities, various interpretative cannons and principles may be employed to determine the parties’ intent and give meaning to the contract. However, contractors should remember that they have a duty to request clarification from the government regarding patent ambiguities. While the “plain-meaning” interpretation of the contract language is arguably the primary method of contract interpretation, an equally important interpretative principle requires that the text of a federal contract be read as a whole. Several other principles of contract interpretation are directly derived from the “whole-text” interpretation principle and may be employed in conjunction with it. Some derived and related principles include harmonious reading and conflict avoidance, avoiding interpretations that render terms superfluous, and giving preference to specific over general terms. While contractors should always seek early clarification from the government regarding perceived ambiguities, by understanding the “whole-text” contract interpretation and its related framework of interpretive principles, contractors can be better positioned to review solicitation and contract documents and materials at various stages of the federal acquisition lifecycle.

This Federal Procurement Insight is provided as a general summary of the applicable law in the practice area and does not constitute legal advice. Contractors wishing to learn more are encouraged to consult the TILLIT LAW PLLC Client Portal or Contact Us to determine how the law would apply in a specific situation.

Related Insights

TLF-Contract-Claims-Insight-8.jpg

The interpretation of federal contracts is generally governed by the plain language of the contract. This means that adjudicative forums assign meaning to federal contracts primarily by giving the contractual words their ordinary sense and without referring to extrinsic evidence. If the plain meaning of contractual words is unambiguous, that meaning generally controls for the purposes of contract interpretation. However, there may be situations where the contract terms are unclear or ambiguous permitting more than one reasonable interpretation. In such situations, adjudicative forums may rely on certain extrinsic evidence to resolve contract interpretation disputes.

  • Extrinsic Evidence in the Solicitation Phase

In resolving the meaning of ambiguous terms in case of interpretive disputes in federal contracts, adjudicative forums often look to the discussions between the government and prospective contractors in the solicitation phase of the procurement. Statements made by government officials during their interactions with prospective contractors at pre-proposal conferences, industry days, or pre-award testing may be used as evidence in contract interpretations as long as such statements do not directly contradict the contract language. As with other extrinsic evidence in the context of contract interpretation, written communications, such as handouts and meeting minutes, generally hold much more weight than oral statements made by government officials.

more
TLF-Contract-Claims-Insight-38.jpg

A War Risks clause may be added to government contracts if performance is required in regions with a risk of war or war-like events. Such a clause helps allocate responsibility between the government and the contractor for any losses or damages caused by such events. While the Federal Acquisition Regulation (FAR) does not specifically contain a standard war risks clause, the defense supplement to the FAR (DFARS) includes clauses such as DFARS 252.228-7000, “Reimbursement for War-Hazard Losses.” Such a clause addresses the allowability of costs of war-hazard benefits for contractor employees. A War Risks clause can typically be negotiated between the government and the prospective contractor at the time of formation of the contract. As contracts in different regions have varying circumstances, risk allocation for specific events described in the War Risks clause should also be tailored and negotiated for each applicable contract. When disputes between the government and the contractor arise that implicate the War Risks clause, adjudicative forums such as the Boards of Contract Appeals or Federal Courts interpret the language of the War Risks clause to allocate increased costs liability between the parties.

more
TLF-Contract-Claims-Insight-69.jpg

The government retains the right to terminate a contract for default when the contractor fails to meet its performance obligations. The default termination, commonly considered one of the most undesirable outcomes for contractors, may nevertheless be converted into a termination for the government’s convenience if, on appeal, the government fails to prove that its default termination decision was justifiable. Notably, when the contractor appeals the government’s decision to terminate its contract for default, it is the government’s burden to prove default termination in the first instance. In other words, the government must demonstrate the correctness of its actions in terminating a contract for default. When contract modifications change the terms of the original contract such that the government’s default termination decision is no longer justified under the modified contract, adjudicative forums will typically convert the default termination to one for the convenience of the government, citing the change in circumstances from contract award to termination.

The Armed Services Board of Contract Appeals (ASBCA) in ASBCA 58866 and ASBCA 58867 converted the Army’s terminations for default for two similar contracts into terminations for convenience due to changes in the terms of the contracts due to later modifications. The Army awarded the underlying contracts for the acquisition of thousands of foreign language test items to assess the proficiency of military linguists. The contracts included the Federal Acquisition Regulation (FAR) 52.212-4 clause: “Contract Terms and Conditions—Commercial Products and Commercial Services.” During the performance, the government was only responsible for paying for the items it accepted, with no apparent definition of what constituted an acceptable item, presumably leaving the acceptability determination at the government’s discretion. The government retained intellectual property rights in both accepted and rejected items as the contracts provided the government sole ownership and exclusive rights to the deliverables. After the contracts were awarded to the same contractor, the Army issued nearly identical modifications, stating that any foreign language test items still required under the contracts but not accepted by the government would be “automatically descoped” from the contract. The Army eventually terminated the contracts for default, citing the contractor’s failure to provide the agreed-upon number of acceptable items.

more
TLF-Federal-Procurement-Insight-79.jpg

Under certain circumstances throughout the procurement lifecycle, contractors may need to establish understandings, agreements, planned actions, or otherwise define the scope and procedures for relationships between themselves and a federal agency to accomplish mutual goals and objectives. When meeting such objectives does not require fiscal obligations or contract awards governed by the Federal Acquisition Regulation (FAR), contractors may negotiate and enter memorandums of understanding (MOUs) or memorandums of agreement (MOAs) with the government. These memorandums provide an overarching framework to govern the relationship between the parties under such circumstances by clearly defining their roles, responsibilities, and expectations. Such memorandums may have binding authority depending on the authority used to execute the memorandum and the facts surrounding other impacted contracts or agreements. In such situations, if the government is in breach of its obligations under the memorandum, contractors may have the right to obtain monetary damages as a party to the memorandum of agreement.

  • Memorandums of Understanding

When an effort requires the federal government to provide federal funds, resources, or items for support, and the memorandum is only being used for the limited purposes of establishing a general framework of the parties’ rights and obligations, contractors may elect to enter into an MOU with the government. An MOU is typically used if the circumstances do not require a high level of detail to establish the parties’ specific roles, responsibilities, and actions. MOUs are generally not issued under specific authority and are not usually legally binding.

more

Principle of Whole-Text Interpretation in Federal Contracts

TILLIT LAW Federal Procurement Insights