TLF-Contract-Claims-Insight-8.jpg

Use of Extrinsic Evidence in Interpreting Federal Contracts

The interpretation of federal contracts is generally governed by the plain language of the contract. This means that adjudicative forums assign meaning to federal contracts primarily by giving the contractual words their ordinary sense and without referring to extrinsic evidence. If the plain meaning of contractual words is unambiguous, that meaning generally controls for the purposes of contract interpretation. However, there may be situations where the contract terms are unclear or ambiguous permitting more than one reasonable interpretation. In such situations, adjudicative forums may rely on certain extrinsic evidence to resolve contract interpretation disputes.

  • Extrinsic Evidence in the Solicitation Phase

In resolving the meaning of ambiguous terms in case of interpretive disputes in federal contracts, adjudicative forums often look to the discussions between the government and prospective contractors in the solicitation phase of the procurement. Statements made by government officials during their interactions with prospective contractors at pre-proposal conferences, industry days, or pre-award testing may be used as evidence in contract interpretations as long as such statements do not directly contradict the contract language. As with other extrinsic evidence in the context of contract interpretation, written communications, such as handouts and meeting minutes, generally hold much more weight than oral statements made by government officials.

  • Extrinsic Evidence in the Performance Phase

In disputes involving the interpretation of ambiguous terms in federal contracts, adjudicative forums also look to the parties’ actions during the performance phase of the contract to determine their intent. On follow-on contracts, materials documenting the parties’ previous performance trends, such as internal memorandums and progress reports, are seen as strong evidence for determining a reasonable interpretation of ambiguous terms. Pre-dispute performance phase actions of the government and the contractor are generally seen as demonstrating their respective subjective interpretations of how performance should be delivered on the contract.

In resolving ambiguous contract clauses, any government interpretations of similar clauses on other contracts may be viewed by adjudicative forums as the government’s reasonable understanding of how performance should be carried out under the clause at issue. Similarly, government interpretations may be contained in official pronouncements, such as agency policy letters, internal memorandums, and relevant laws and statutes. Official pronouncements are considered actions of the government during the performance phase of the contract for the purposes of assigning reasonable meaning to ambiguous terms. Such extrinsic evidence relevant to the performance phase of the contract may be strong enough to bind the parties contractually.

  • Limitations on Extrinsic Evidence

The parole evidence rule serves as the primary limitation on using extrinsic evidence in interpreting federal contracts. This common law principle states that a final integrated contract may not be modified by earlier or contemporaneous evidence that may contradict or alter the written terms of the contract. The parole evidence rule thus prevents parties from introducing pre-award evidence of negotiations during the pre-solicitation or solicitation phases that contradicts, adds to, or introduces ambiguity into an integrated contract. As an additional limitation on the use of extrinsic evidence in resolving contract interpretation disputes, the government will generally not be bound by any statements made by government officials that exceed their respective authority, regardless of the phase of the procurement lifecycle during which such statements are made.

Contractors should carefully collect and maintain information, materials, and communications received from the government during all procurement phases, as they may prove helpful extrinsic evidence during contract disputes involving ambiguous terms, provisions, or clauses. Furthermore, contractors should immediately request clarifications from the government of any ambiguous terms they identify in their solicitations or contracts and diligently pursue these clarifications if they do not receive an immediate response from the government. By doing this, contractors can preserve and support potential claims through favorable interpretations of ambiguous terms in case of contract interpretation disputes with the government.

This Federal Contract Claims Insight is provided as a general summary of the applicable law in the practice area and does not constitute legal advice. Contractors wishing to learn more are encouraged to consult the TILLIT LAW PLLC Client Portal or Contact Us to determine how the law would apply in a specific situation.

Related Insights

TLF-Contract-Claims-Insight-5.jpg

In case of contract disputes, contractors must typically carry the burden of proof to establish the excusability of delays in performance of government contracts. This burden of proof must be carried by meeting the preponderance of the evidence standard. That is, contractors must generally show that it was more likely than not that the government was responsible for the performance delays. Depending on the terms of the contract and the circumstances surrounding the delay, contractors may need to rely on various types of evidence to achieve this. While the burden of proof may be relatively low, proving excusability of delays may nevertheless be challenging in the absence of properly documented evidence. For instance, the government may be in control of some of the evidence necessary to establish excusability, or there may be concurrent events contributing to delays in performance. Such scenarios may require contractors to produce different types of evidence, which may complicate their path to recovery. Therefore, contractors attempting to prove excusable delays must document, maintain, and produce detailed records demonstrating the government’s share of responsibility for the delay in performance.

more
TLF-Federal-Procurement-Insight-73.jpg

When reviewing an agency’s procurement actions, adjudicative forums such as the Government Accountability Office (GAO) typically consider various materials and information in the record. Such materials may include arguments the agency and contractor raised during litigation, explanations of decisions and events advanced during the procurement cycle, and any hearing testimony. When reviewing evidence to determine the reasonableness of the government’s procurement actions, the adjudicative forum will generally assign greater weight to contemporaneous materials than post hoc arguments or analyses. This is because the judgments made in the heat of an adversarial process do not always represent the fair and considered judgment of the agency. Therefore, while adjudicative forums will consider explanations provided by agency counsel that merely fill in previously unrecorded details, post hoc rationalizations are typically deemed less persuasive. For instance, in resolving bid protests, the GAO has explained that it accords greater weight to contemporaneous materials, which are far more indicative of whether the agency conducted a rational evaluation and source selection process.

In B-422162; B-422162.2; B-422162.3, a bid protest decision issued on February 1, 2024, the GAO applied this principle in sustaining the protestor’s challenge to the government’s cost realism evaluation. The United States Army Corps of Engineers (USACE) awarded the contract at issue for environmental remediation services at the Durham Manufacturing Company superfund site in Connecticut. The cost-plus-fixed-fee contract was awarded on a best-value tradeoff basis where the non-price factors, when combined, were approximately equal to cost. Notably, the solicitation provided that the government would evaluate proposed costs for realism and, if needed, adjust an offeror’s unrealistically low proposed costs to a most probable cost (MPC) calculated solely for evaluation purposes. Among other contentions, the protestor alleged that USACE made unreasonable upward adjustments to the proposed rates for two labor positions. Specifically, USACE evaluators found the protestors’ rates for the quality control (QC) manager and site safety and health officer (SSHO) position to be unrealistically low when compared to the independent government estimate (IGE). However, instead of upwardly adjusting the protestor’s QC manager and SSHO rates to the IGE rates for these positions, the evaluators adjusted these rates to the protestor’s proposed rate for the superintendent position. The evaluators also failed to contemporaneously record their rationale for this adjustment.

more
Shutterstock_2438192851.jpg

The Contract Disputes Act, codified at 41 U.S.C. §§ 7101-7109, requires that a contract claim filed under the Act relate to a contract with the government. Adjudicative forums that resolve appeals challenging the contracting officer’s (CO) final decision in such claims, including Boards of Contract Appeals and Federal Courts, have consistently ruled that the phrase “relating to a contract” should be read broadly. Therefore, for a claim to be related to a contract for the purposes of CDA jurisdiction, the claim must have some relationship to the terms or performance of an underlying government contract. Despite this broad categorization, it may not always be apparent whether a claim sufficiently relates to a particular government contract to fall under CDA jurisdiction. In such situations, contractors should be aware that if they can demonstrate that their claim bears some relation to the contract, they stand a good chance of properly bringing their claim under the CDA.

On January 11, 2024, the Armed Services Board of Contract Appeals (ASBCA) issued an opinion in ASBCA No. 63634, denying the Air Force’s motion to dismiss, and exercising jurisdiction over an appeal arising from a claim pursuant to § 3610 of the Coronavirus Aid, Relief, and Economic Security (CARES) Act. The contractor was performing on a government contract to operate, maintain, support, and upgrade the training systems for the Air Force’s B-52 bomber aircraft. Among the relief sought in the claim, the contractor requested compensation in the form of equitable adjustment for increased costs to keep its workforce in a ready state during the COVID-19 pandemic. However, the CO denied that portion of the contractor’s claim. During the subsequent ASBCA appeal, the government again moved to dismiss the contractor’s § 3610 claims, asserting that the ASBCA did not have subject matter jurisdiction to resolve claims under the CARES Act. The government analogized § 3610 of the CARES Act to Public Law 85-804, which provides government agencies broad discretionary authority to modify government contracts but does not give the Board authority to entertain appeals from the government’s adverse decisions.

more
Shutterstock_2241902509.jpg

When interpreting terms of a federal contract, dispute adjudicative forums may turn to extrinsic evidence of trade practice and custom to resolve ambiguities. Trade usage refers to the use of terms or language with such regularity in a particular vocation, location, or industry that a contracting party is justified in its expectation that their technical meaning will be observed with respect to the contract. The use of trade practice and custom evidence as an interpretive device is not typically available when contractual language is plain and unambiguous on its face. However, under certain conditions, such as when a term has an accepted industry meaning different from its ordinary meaning, it may be appropriate for the dispute adjudicative forum to turn to evidence of trade practice and custom even when the contractual language is seemingly unambiguous. In such situations, the party introducing the evidence must demonstrate that it reasonably relied upon the accepted industry meaning as opposed to the ordinary meaning at the time of contract formation. In other words, the party presenting the evidence must show that the trade practice or custom genuinely reflected its intent when entering the contract, rather than serving as a post hoc rationalization for its actions.

more

Use of Extrinsic Evidence in Interpreting Federal Contracts

TILLIT LAW Federal Contract Claims Insights