Government typically has no obligation to assist the contractor in completing work before the contract completion date. Despite this lack of obligation, it is still not permissible for the government to hinder or otherwise prevent a contractor’s early completion of performance. In this regard, when the contractor’s early completion of work is delayed due to government actions, the government may be liable for the delay it causes even when the contractor completes performance within the agreed-upon contract completion deadline. Contractors must satisfy three elements to establish entitlement to benefits of a planned early completion which is adversely impacted by government-caused delays. First, from the outset of the contract, the contractor must establish its intent to complete performance on an accelerated schedule and ahead of the contractually mandated completion date. Notably, while it is necessary for the contractor to convey its intent to complete early performance, it need not inform the government of a specific early completion date. Second, the contractor must have the capability to perform early, and its intent must be supported by consistent actions and performance activities during the performance period. Third, the contractor must establish that had it not been for the government-caused delays, its actions in pursuing acceleration would have led to an early completion. Once the three elements are established, the government is liable for damages arising from its dilatory actions that prevent the contractor’s early performance.
In Armed Services Board of Contract Appeals (ASBCA) No. 48087, a decision issued on April 27, 1999, the government was found liable for the contractor’s increased costs attributable to the government's delay, even though the contractor completed performance ahead of schedule. The U.S. Air Force awarded the underlying contract to repair and replace underground gas mains and service lines to buildings at Davis-Monthan Base in Tucson, Arizona. The Air Force failed to properly coordinate the installation of the main gas connection with the contractor and was found responsible for unreasonable delays. However, the government argued that the contractor could not recover because it completed the contract ahead of schedule. During the Board hearing, the contractor’s project manager responsible for scheduling testified that he intended to complete the work early when he first prepared the progress schedule. Consistent with his testimony, the original progress schedule showed a plan to complete 15 days early. Next, the contractor’s activities supported its intent to accelerate the schedule. Monthly schedule updates demonstrated steady progress, and the work was six weeks ahead of schedule before the government-caused delays began. The contractor also had the capability to perform early, as there was no dispute about the availability of personnel, materials, and equipment. Finally, when performance resumed after the government delays, the contractor completed performance per its schedule. Consequently, the ASBCA concluded that the contractor was entitled to recover its increased costs due to government delays under the contract’s suspension of work clause, even though overall performance was completed ahead of schedule.
Meanwhile, in ASBCA No. 63457, a decision issued on May 18, 2023, the contractor was unable to recover delay damages when it completed performance before the contract completion date because it could not establish its intent from the outset of the contract to complete performance early. The Navy awarded the underlying delivery order to renovate ten buildings at the San Diego Naval Base. The contractor submitted a baseline construction schedule within 15 days after award, which anticipated meeting the June 13, 2022, contract completion date. Following a delay due to limitations on access to work areas, on February 22, 2022, the contractor submitted an updated progress schedule in which it stated an early project turnover and closeout date of May 9, 2022. The contractor eventually completed the project even earlier on April 28, 2022, and requested compensation for additional costs incurred due to government-caused delays. Since the contractor had completed the work before the contract completion date, its ability to complete the work early and the fact that it would have completed the work earlier than the completion date but for the alleged government delays was not challenged. Instead, the government’s argument and the Board’s analysis focused only on the first element – whether it was the contractor’s intent from the outset of the contract to complete the work on an accelerated schedule. The Board found that the contractor could not satisfy this element because its baseline schedule only anticipated meeting the original completion date. While a later revised schedule contemplated an early completion, it did not reflect the contractor’s intent at the outset of the contract, barring its recovery.
Contractors may be able to recover for government-caused delays even when they complete the overall performance ahead of schedule. To do so, contractors must plan for early completion from the outset of the contract and establish their intent to do so. While contractors need not provide the government with a firm early completion date, any accelerated schedule must be feasible and attainable. Furthermore, the contractor’s intent to complete the work early must be supported by its performance activities and actions over the course of the contract. Finally, contractors must show that, but for the government-caused unreasonable delays, their efforts would have led to the planned early completion. If these three elements are satisfied, contractors may obtain compensation for government-caused delays even when overall contract performance is complete ahead of schedule. As in the appeal described above, when a contractor completes early performance, the second and third elements are typically easy to satisfy. That is, the contractor can usually show it had the ability to complete the work early and that it would have done so but for the alleged government delays. However, proving the first element may prove challenging if the contractor did not plan on early performance from the outset of the contract or adequately inform the government of its intent. Therefore, if early performance is anticipated, contractors should inform the government of their intent at the outset of the contract and maintain records of their activities during performance that are consistent with that intent. After all, doing so may be critical to realizing the benefits of planned early completion of work in the face of unexpected government-caused delays.
This Federal Procurement Insight is provided as a general summary of the applicable law in the practice area and does not constitute legal advice. Contractors wishing to learn more are encouraged to consult the TILLIT LAW PLLC Client Portal or Contact Us to determine how the law would apply in a specific situation.




