Shutterstock_2014536923-2.jpg

Doctrine of Accord and Satisfaction in Federal Contracts

In government contracts, the doctrine of accord and satisfaction is an affirmative defense that discharges a claim because some performance different from that which was claimed to be due is rendered and the claimant accepts such performance as full satisfaction of his claim. Accord and satisfaction may be viewed as a type of settlement agreement that typically takes the form of a bilateral modification executed by the government and its contractor. Furthermore, the terms of the bilateral modification are considered to be the best evidence of the parties’ intent to enter into an accord and satisfaction. To invoke the doctrine of accord and satisfaction, the party asserting the affirmative defense must demonstrate that four elements are met. First, the subject matter must be proper. Second, both parties must be competent; that is, the individuals signing the bilateral modification on behalf of the parties must be duly authorized. Third, there must have been a meeting of the minds between the parties. A meeting of the minds exists when there are accompanying expressions sufficient to make a reasonable claimant understand that the performance offered is in full satisfaction of the claim. Fourth, and finally, there must exist some form of valid consideration, which is defined as a bargained-for exchange that consists of an act, forbearance, or a return promise. If these four elements are met, the doctrine of accord and satisfaction may be invoked to discharge the claimant’s claim.

In Armed Services Board of Contract Appeals (ASBCA) No. 64036, a decision issued on July 15, 2025, it was determined that all four elements of accord and satisfaction were met, and as a result, the contractor’s claim was deemed discharged. The Army awarded the underlying contract in September 2023 for the remote performance of medical coding services for the Keller Army Community Hospital in West Point. In December 2023, within a few months of the contract’s effective start date, and before the contractor had performed any remote medical coding services, the Army fully terminated the contract for the government’s convenience. Following the termination, the Army issued a modification establishing a complete no-cost termination for convenience, but the contractor refused to execute that modification. Instead, in April 2024, the contractor submitted a termination settlement proposal seeking a payment of $44,559.80. Later in August 2024, the contractor reduced the amount sought to $38,875.80. At this stage, the contracting officer (CO) determined that while the contractor had not demonstrated entitlement to the full amount sought in its termination settlement proposal, the Army was still willing to pay the contractor $9,418 for preparatory costs incurred and reasonable settlement expenses. In October 2024, the CO forwarded the contractor a purchase order for $9,418 and issued a second bilateral modification releasing the Army from any additional charges arising under the terminated contract. The modification also acknowledged that the contractor had no further obligation to perform under the terminated contract. This time, the contractor signed the modification and returned it to the CO, who also executed the modification on the same day.

After receiving a payment of $9,418, the contractor filed a notice of appeal with the ASBCA, seeking reconsideration of the settlement amount and requesting reimbursement of the full $38,875 included in the contractor’s revised termination settlement proposal. In addition to invoking the affirmative defense of release, the Army also argued that the second modification constituted an accord and satisfaction, which barred any further recovery for the contractor. In reviewing the evidence in the record, the Board concluded that all four elements of an accord and satisfaction were met when the parties executed the bilateral modification in October 2024. Firstly, the subject matter of the executed bilateral modification was the same as the underlying contract between the parties. For the second element, both the CO and the President of the contractor who signed the bilateral modification were duly authorized to do so. Next, the Board found that the intention of the executed bilateral modification was clearly stated. That is, the modification’s purpose was to pay the contractor $9,418 following the termination for convenience. At the same time, the contractor agreed to unconditionally waive any claims against the Army for further payments without any exceptions or reservations. Therefore, the Board found that the contractor was aware of the bilateral modification’s clearly stated intention and thus a meeting of the minds existed between the parties, satisfying the third element. Finally, the fourth element of consideration was also met because the Army agreed to pay the contractor $9,418, and the contractor agreed to unconditionally waive any claims for further payments. Therefore, the contractor’s claim was discharged due to an accord and satisfaction.

Meanwhile, in ASBCA No. 63239, a decision issued on January 4, 2024, the Board found that the government failed to establish accord and satisfaction because the element concerning the parties’ meeting of the minds was not met. The Air Force issued a contract for housing maintenance services for the Kaiserslautern Military Community in Germany. Following the end of the period of performance, the Air Force de-obligated unused funds on several CLINs via a bilateral modification. When the modification was initially sent to the contractor, it included language releasing the government from any and all liabilities concerning the de-obligated funds. However, the contractor refused to sign the modification. The contractor requested that the CO remove the statement of release from the modification and include language indicating that the contractor reserved the right to submit additional invoices and claims for the de-obligated funds. The CO obliged, and the release language was removed from the bilateral modification, which was executed by both parties. The contractor later filed a claim seeking the amount that was de-obligated from the contract. In the appeal that followed, the Board determined that there was no specific language in the bilateral modification that would indicate a meeting of the minds between the parties regarding the fact that the contractor’s claims for the de-obligated amount were fully satisfied. In fact, the Air Force was aware of the contractor’s contrary position on the matter and yet failed to resolve the issue before the modification was executed. Furthermore, there was no language in the modification to demonstrate that the contractor was accepting the Air Force’s position. Consequently, the Board ruled that the Air Force could not invoke the doctrine of accord and satisfaction to discharge the contractor’s claim.

Accord and satisfaction in government contracts usually takes the form of a bilateral modification. It occurs when some performance different from that which was claimed as due is rendered, and the claimant accepts such substituted performance as full satisfaction of its claim. Contractors should be mindful that an accord and satisfaction is distinct from the affirmative defense of waiver or release and requires the party claiming it to meet four specific elements. Specifically, to invoke the doctrine of accord and satisfaction, the party must prove: (1) the propriety of the subject matter; (2) the competence of both parties; (3) a meeting of the minds between the parties; and (4) consideration. The affirmative defense of accord and satisfaction may not be invoked if any one of these four elements is not satisfied. In the event a bilateral modification is executed, the adjudicative forum will carefully review the terms of the modification to determine whether each element has been satisfied, and, as a result, an accord and satisfaction has occurred. Since an accord and satisfaction often follows a full or partial termination for convenience, contractors should carefully review the terms of any post-termination modifications to ensure that they accurately reflect their position, especially with respect to any language that releases the government from all future liability. If contractors wish to preserve their right to submit future invoices or file future claims, they can also insist on including language in the bilateral modification that reserves their rights regarding these matters. In doing so, and by understanding the elements required for invoking the doctrine of accord and satisfaction, contractors can be better positioned to negotiate and execute bilateral modifications or supplemental agreements in their government contracts.

This Federal Procurement Insight is provided as a general summary of the applicable law in the practice area and does not constitute legal advice. Contractors wishing to learn more are encouraged to consult the TILLIT LAW PLLC Client Portal or Contact Us to determine how the law would apply in a specific situation.

Related Insights

TLF-Contract-Claims-Insight-7.jpg

Contractors often face situations requiring them to enter bilateral contract modifications towards the end of a contract to close it out. To avoid incurring excessive costs and liability in such situations, contractors should carefully consider whether the modifications increase the scope of the contract beyond what was initially agreed upon. Federal contractors should review the impact of any applicable Federal Acquisition Regulation (FAR) provisions in their contract on the modification at issue, as recovery under future requests for equitable adjustments and claims may depend on it.

The Armed Services Board of Contract Appeals (ASBCA), in one of its first decisions of 2024, reminded contractors to carefully assess the scope and governing authority before agreeing to bilateral contract modifications. In ASBCA No. 61819, the contractor brought unsuccessful claims of contract changes based on economic waste theory and differing site conditions against NASA. The contract involved construction work on an aircraft parking apron and taxiway at a NASA flight facility in Virginia. It included the Default (Fixed-Price Construction) clause from FAR § 52.249-10(a) and an Inspection of Construction clause from FAR § 52.246-12. The contract also contained Technical Direction and Special Instruction provisions that prohibited the Contracting Officer’s Representative (COR), Government inspectors, or any other Government employees from issuing technical directions that waived or changed any contract provisions without written authorization from the Contracting Officer (CO).

more
TLF-Contract-Claims-Insight-8-2.jpg

One of the unique privileges enjoyed by the U.S. Government as a contracting party under a federal contract is its authority to terminate the contract at any time, regardless of the contractor’s fault. Known as termination for convenience, the contracting action allows the Government an exclusive and almost unlimited right to terminate a government contract unilaterally. When terminating a contract for convenience, the Government may terminate the contract entirely or choose to make partial terminations with practically no limitations on the extent, type, or profitability of the portion of the contract being terminated.

While contract termination is seldom a cause for celebration for the contractor, a convenience termination is still greatly preferred over termination for default. This is because of the simple reason that a convenience termination indicates that the Government terminated the contract in its own best interests rather than due to the contractor’s fault. This allows contractors to receive the costs they incurred in performing the contract up to the point of termination, along with any profits on the completed work, if applicable. Under convenience termination, contractors can also recover any costs expended in delivering the termination proposal.

more
Shutterstock_648122044.jpg

Some projects require the contractor to begin performance immediately, with the urgency of the government requirement providing no time to establish terms, specifications, or prices. The government may enter into undefinitized contract actions (UCAs) or letter contracts for such projects. The contract clause at Federal Acquisition Regulation (FAR) 52.216.25 provides the process for the definitization of UCAs. Since UCAs permit performance without firmly established terms such as pricing, procuring agencies are expected to agree on the undefinitized contract terms in a timely manner after the commencement of performance. When the agency and the contractor cannot agree on a firm price, the FAR definitization clause allows the contracting officer (CO) to conclude negotiations and unilaterally determine a reasonable price. Notably, because the definitization clause expressly permits it, the CO’s unilateral establishment of pricing is considered an act of contract administration and not a government claim. Consequently, if the contractor does not agree with the CO’s unilaterally established price, it must file a claim with the CO before appealing that decision at a relevant Board of Contract Appeals (BCA) or the Court of Federal Claims (COFC).

more
Shutterstock_2569164843.jpg

The federal government has the right to unilaterally terminate contracts when it is in the government’s interest to do so. In the event of a termination for convenience, the contractor may typically submit its termination settlement proposal within a year of the termination. Since the contractor submits the settlement proposal primarily for negotiation purposes, it is not considered a claim under the Contract Disputes Act (CDA) when it is first submitted to the contracting officer (CO). Stated another way, the termination settlement proposal is considered an instrument of negotiation rather than a non-routine request for payment or a request for the CO’s final decision. For this reason, the costs of preparing a termination settlement proposal are also generally considered allowable. However, if the termination settlement proposal otherwise meets the requirements of a claim, it can be converted into a CDA claim if the parties’ negotiations reach an “impasse” and the contractor demands that the CO issue a final decision. In this context, an impasse means a deadlock or a point where a resolution through continued negotiations is unlikely when viewed from the perspective of an objective, third-party observer. Notably, whether the parties’ negotiations have reached an impasse is a question of fact, to be determined on a case-by-case basis.

more

Doctrine of Accord and Satisfaction in Federal Contracts

TILLIT LAW Federal Procurement Insights