Shutterstock_1201428055-2.jpg

Recovering Under a Type II Differing Site Conditions Claim

The Differing Site Conditions clause at Federal Acquisition Regulation (FAR) 52.236-2 is typically included in construction contracts to discourage contractors from inflating their proposed prices on account of unexpected physical conditions that may not arise. There are two types of differing site conditions claims contemplated under the clause. In a type I claim, the conditions encountered by the contractor differ materially from those indicated in the contract. On the other hand, in a type II claim, the conditions are different from those ordinarily encountered. To qualify as a type II differing site condition, the conditions must be such that they cannot be predicted by the contractor’s review of the contract documents, site inspections, and its general experience, if any, as a contractor in the region. Proving a type II differing site condition is typically more difficult than proving a type I condition, as it involves a heavier burden of proof because there is no clear point of reference in the contract documents as to the known and usual conditions on site. To prove a type II condition, the contractor must first establish the known and usual conditions at the site. Next, the contractor must show that the actual physical conditions it encountered were different from the known and usual conditions. Finally, the contractor must demonstrate that the different conditions increased the cost of performance.

In Skanska USA Bldg., Inc. v. United States, 07-143 C, 2013 WL 1179528 (Fed. Cl. 2013), the U.S. Court of Federal Claims (COFC) held that the contractor successfully satisfied the elements of a type II differing site conditions claim. The U.S. Army Corps of Engineers (USACE) awarded the relevant contract for the construction of nine buildings at North Fort Lewis in Washington. The earthwork under the contract required the contractor to excavate, transport, and place soil and other materials. The contractor did not include any costs for disposing surplus soil in its proposal because it believed the contract permitted it to retain any savings from selling the clean soil material. The contractor and its team ultimately accumulated a stockpile of roughly 15,000 cubic yards of soil material over the course of the project. While the contract documents or site visit reports did not indicate it, a soil sampling of the stockpile conducted by USACE revealed lead contamination, as the soil contained chips and materials from World War II-era buildings demolished in the 1990s that had been painted with lead-based paint. Since the contractor could no longer sell the stockpiled soil due to the contamination, it moved the surplus soil to a government-designated landfill and submitted a certified claim for $148,498, which was partially denied by the contracting officer (CO).

In the suit that followed, the contractor argued that the discovery of lead in the stockpiled soil constituted a type II differing site condition under the clause at FAR 52.236-2, included in the contract. The COFC agreed, noting with respect to the known and usual conditions at the site, that the contract documents and the site inspection did not disclose the lead contamination. Additionally, the contractor presented evidence that its estimator, with 17 years of experience in the Fort Lewis region, who worked for a construction firm doing business in the region for more than 41 years, found lead contamination to be an unusual condition. Thus, the lead contamination was not a known or usual condition at the site. Next, there was no dispute that the contractor had encountered contaminated soil following excavation, as the USACE soil sampling revealed lead contamination. The CO testified that the contractor was neither responsible for the contamination nor could it have known about it. Accordingly, the actual physical conditions encountered by the contractor were different from the known and usual conditions. Finally, the contractor presented evidence that, under its proposal to retain savings from selling clean soil, disposal costs for uncontaminated material would have been $0. Meanwhile, disposal costs for the contaminated material exceeded $120,000, and the surplus material could not be sold as the contractor had originally anticipated. Consequently, the third and final element for establishing a type II condition was also met as the contractor had demonstrated that its cost of performance had increased due to the differing conditions.

Government construction contracts typically include a differing site conditions clause that addresses two types of conditions. For both types of differing site conditions, the contractor must prove its claim by a preponderance of the evidence. In a type I claim, the known and usual conditions are indicated in the contract, and the conditions encountered by the contractor differ materially from those indicated. Meanwhile, in a type II claim, the conditions encountered by the contractor differ from the known and usual conditions at the site. Proving a type II differing site condition is typically more difficult than proving a type I condition because the contractor has the additional burden to establish the known and usual conditions at the site. Next, the contractor must demonstrate that the physical conditions it encountered were different from the known and usual conditions. In this regard, the unknown physical condition must be such that it cannot be reasonably anticipated from the nature and location of the work or the review of contract documents. The contractor can present any relevant climatological, hydrological, and geological data, among other relevant evidence, to demonstrate that the conditions encountered materially differed from what should have been reasonably expected. Finally, the contractor must prove that the differing site conditions increased its performance costs. Once the three elements are established, the contractor can recover under a type II differing site conditions claim.

This Federal Contract Claims Insight is provided as a general summary of the applicable law in the practice area and does not constitute legal advice. Contractors wishing to learn more are encouraged to consult the TILLIT LAW PLLC Client Portal or Contact Us to determine how the law would apply in a specific situation.

Related Insights

Insight 5 - Substack.jpg

The primary method for managing risks associated with latent physical conditions encountered in construction projects is the differing site conditions clause in Federal Acquisition Regulation (FAR) 52.236-2. Since fully redressable claims under specifically included contract clauses may not be brought under separate breach of contract claims, most claims for hidden site conditions are brought under the differing site conditions clause. However, certain federal contracts for smaller construction projects awarded through simplified procedures, and some custom-negotiated construction contracts may lack a well-defined differing site conditions clause. In such cases, contractors must pursue their claims arising out of unforeseen conditions, such as claims related to subsurface conditions under traditional breach of contract theories. Additionally, when faced with unforeseeable events like extreme and unpredictable weather or unanticipated changes in labor conditions that are not typically covered by the differing site conditions clause, construction contractors may opt to initiate breach of contract claims to recover their increased costs.

The Government’s non-disclosure or misrepresentation of information material to site conditions are two breach of contract actions available to construction contractors in such situations. To be successful in a non-disclosure claim, the construction contractor must demonstrate that the Government possessed information pertinent to a material site condition, which it failed to disclose to the contractor. The contractor must also establish that the presence of the material site condition could not have been readily determined through a site inspection or other reasonable methods. Government misrepresentation is the other breach of contract claim commonly applicable in contracts without a differing site conditions clause. A misrepresentation claim is essentially based on the Government breaching its duty to disclose its superior knowledge of the site condition. To prove that the Government breached its duty to disclose, the Court of Federal Claims (COFC) has previously required that the contractor demonstrate Government culpability. One way of demonstrating Government culpability is by proving that the Government knew that the contractor was unaware of the differing site conditions. However, the Federal Circuit has recently rejected the Government culpability requirement, making contractor claims easier to prove in such situations. Therefore, depending upon the circumstances, the adjudicative forum’s analysis for a breach of contract claim for Government misrepresentation is similar if not identical to a differing site conditions claim.

more
Shutterstock_664567501-3.jpg

Under the Spearin doctrine, when the government furnishes design specifications directing the contractor on how to undertake performance on a contract, it provides an implied warranty that the contractor will be able to perform the contract satisfactorily if it adheres to the government’s specifications. The doctrine allows contractors to transfer to the government the risk of increased costs resulting from defective specifications. Notably, however, the Spearin doctrine only applies when the defective specifications are design specifications as opposed to performance specifications. Design specifications expressly describe how contract performance must be undertaken and do not permit the contractor to make any deviations. Meanwhile, performance specifications state the overall objectives that must be achieved but leave the decisions on how to achieve those objectives at the discretion of the contractor. Since design specifications do not allow deviations or grant the contractor discretion in achieving contractual objectives, the government implicitly warrants that design specifications are free from defects. Consequently, when the government’s design specifications are defective or result in unsatisfactory performance the government is deemed to have breached its implied warranty of specifications under the Spearin doctrine. In such cases, the contractor may recover all proximate costs stemming from the government’s breach.

more
Shutterstock_2211056755.jpg

The government provides contractors with a variety of information during the solicitation process before a contract is awarded. Such information may be furnished through pre-award conferences, questions and answers, solicitation attachments, specifications, diagrams, drawings, contract provisions, etc. When the government misstates material facts during the contract formation process, it may later be liable under express provisions of the contract or for breaching an implied warranty that it furnishes correct information. In this regard, when the government provides incorrect representations and directs or expects prospective offerors to base their contract pricing on those misrepresentations, the government is responsible for any losses the contractor suffers as a result of its reliance on that information. In other words, when the government instructs offerors to base their pricing on data it furnishes, it assumes responsibility for ensuring that the data accurately reflects the conditions the contractor will encounter during performance. In such cases, as long as the contractor can demonstrate that the government's information was incorrect, it need not prove the government's intent to deceive or bad faith. Furthermore, the contractor may also not need to prove that the incorrect information was inadequately or negligently prepared.

more
Shutterstock_2330768049-4.jpg

Government contracts for construction projects typically include a Differing Site Conditions clause to account for the risk that the contractor may encounter unanticipated subsurface or otherwise latent physical conditions. The purpose of this clause is to discourage contractors from inflating their pricing on account of unexpected physical conditions that may or may not arise. The clause contemplates two types of differing site conditions. In a type I condition, the contractor encounters physical conditions materially different from those specified in the contract. Meanwhile, a type II condition is unknown, unusual, and materially different from that ordinarily encountered. To successfully recover under a type I differing site conditions claim, the contractor must establish five elements by a preponderance of the evidence. The contractor must establish that: (1) a reasonable contractor reading the contract as a whole would interpret it as making a representation as to the site conditions; (2) the actual site conditions were not reasonably foreseeable to the contractor with the information available to it outside the contract documents; (3) the contractor in fact relied on the contract representation; (4) the conditions differed materially from those represented; and (5) the contractor suffered damages as a result.

more

Recovering Under a Type II Differing Site Conditions Claim

TILLIT LAW Federal Contract Claims Insights