Shutterstock_2611622515-3.jpg

Timeliness of Motions for Dismissal Based Upon the Nonjurisdictional Sum Certain Requirement

While the Contract Disputes Act (CDA) does not define a claim, the Federal Acquisition Regulation (FAR) § 2.101 defines a monetary claim as a written demand or assertion by a contracting party seeking, as a matter of right, the payment of money in a “sum certain.” Since the sum certain requirement is not included in the CDA, the Federal Circuit has held that the requirement is non-jurisdictional. Stated another way, a CDA claim does not need to include a sum certain for the Court of Federal Claims (COFC) or a relevant Board of Contract Appeals to exercise jurisdiction over it. Instead, the sum certain requirement is considered an element of a claim for relief that the contractor must satisfy in order to recover. The distinction is important because parties may raise a motion challenging the Court’s or the Board’s jurisdiction at any time. Meanwhile, if a party presents a defense based on the sum certain requirement after litigation has far progressed, it may be deemed to have forfeited the defense entirely. Therefore, the sum certain requirement is a mandatory but non-jurisdictional claim processing rule that is subject to forfeiture. It is somewhat unclear exactly when the claims litigation progresses to a point where a party loses the right to challenge a deficient sum certain. However, the Federal Circuit has indicated that forfeiture may apply as soon as the merits of the case are evaluated, including after the summary judgment stage.

In Armed Services Board of Contract Appeals (ASBCA) No. 63842, a decision issued on June 24, 2025, the Board granted the government’s motion to dismiss for failure to state a claim based on the sum certain requirement after concluding that the government had not forfeited its motion because it had filed the motion during discovery. The U.S. Army Corps of Engineers (USACE) awarded the underlying fixed-price contract in 2021 for approximately $19.5 million to install turbines and a generator rewind at the Philpotts Powerhouse in Virginia. One year into the contract, the contractor notified the government of its intent to pursue a price adjustment under the contract’s Economic Price Adjustment (EPA) clause. In December 2023, the contractor submitted a “merit-only” claim requesting that the CO determine the enforceability of the contract’s EPA clause and confirm the contractor’s right to an adjustment under the clause. The contractor did not seek a sum certain in its claim, representing that no quantum was involved. The CO denied the claim, and the contractor filed its appeal with the Board. During the subsequent appeals litigation, a little more than two weeks before the close of discovery, the government filed its motion to dismiss for failure to state a claim. In its motion, the government asserted that the contractor’s claim was essentially a monetary claim that should be dismissed for lacking a sum certain.

The Board agreed in holding that USACE had not forfeited its right to bring the motion and ruled that the contractor’s claim was required to include a sum certain. The decision compared the procedural facts of the present case with ECC International, LLC v. Secretary of the Army, 79 F.4th 1364 (2023), where the government was deemed to have forfeited a lack of sum certain defense by not raising it until after a hearing on the merits. The Board also cited its past precedent in ASBCA 63252, where it held that the government had not forfeited a lack of sum certain defense by raising it during discovery. In relying on these cases, the Board held that the appeals litigation in the present case had not far progressed when the government filed its motion to dismiss for failure to state a claim. Furthermore, the Board also found the government’s motion meritorious, noting that because the only significant consequence of a declaration that the contractor has the right to seek an adjustment under the contract’s EPA clause would be a price adjustment, the essence of the dispute was purely monetary in nature. Therefore, the contractor was not permitted to circumvent the sum certain requirement by reframing its monetary claim as a nonmonetary claim for declaratory judgment. Ultimately, the Board dismissed the contractor’s claim without prejudice because the contractor’s monetary claim failed to meet the nonjurisdictional but mandatory sum certain requirement.

The sum certain requirement is not included in the CDA and is consequently a mandatory claim processing rule, not a jurisdictional requirement. Thus, the party requesting a dismissal based on the sum certain requirement must file a motion to dismiss for failure to state a claim rather than a motion to dismiss for lack of (subject matter) jurisdiction. Since the requirement is not jurisdictional, a sum certain defense may not be raised at any point and is subject to forfeiture if the party asserting it waits until appeals litigation has far progressed. In the appeal described here, the Board decided that the government’s motion to dismiss was timely because it was filed during the discovery stage. It is worth noting that, although not evident from the decision, the determining factor underlying the Board’s decision on the timeliness of the government’s motion may have been that the Board had not yet considered the merits of the contractor’s appeal. Indeed, in ECC International, the Federal Circuit indicated that forfeiture may be applicable as soon as the adjudicative forum considers the merits of the case, including after the summary judgment stage. While it is true that in most cases, parties file a motion for summary judgment after the close of discovery, a summary judgment motion may also be filed before or during discovery. If a motion to dismiss for failure to state a claim based on the sum certain requirement is filed after the summary judgment decision, the adjudicative forum may well find the motion untimely in ruling that the litigation has far progressed under the ECC International standard, even if the motion to dismiss is filed before the close of discovery.

This Federal Contract Claims Insight is provided as a general summary of the applicable law in the practice area and does not constitute legal advice. Contractors wishing to learn more are encouraged to consult the TILLIT LAW PLLC Client Portal or Contact Us to determine how the law would apply in a specific situation.

Related Insights

TLF-Contract-Claims-Insight-75.jpg

A Contract Disputes Act (CDA) claim meets the mandatory “sum certain” requirement when the contractor has submitted to the contracting officer (CO) a clear and unequivocal statement that gives the CO adequate notice of the basis and amount of the claim. While the CDA provides no definition of a claim, the Federal Acquisition Regulation (FAR) § 2.101 defines a government contract “claim” as a written demand or assertion by a contracting party seeking, as a matter of right, the payment of money in a “sum certain.” This “sum certain” requirement contained within the FAR definition of a claim was considered jurisdictional until the Federal Circuit’s relatively recent decision in ECC International, LLC v. Secretary of the Army, 79 F.4th 1364 (2023). In the much publicized ECC decision, the Federal Circuit held that the “sum certain” requirement was not a jurisdictional prerequisite for a CDA claim but a mandatory claim-processing rule that claimants must follow. Since parties may raise jurisdictional issues at any time during appeals litigation, the ECC decision has practically limited the government’s “sum certain” challenges to motions for dismissal for failure to state a claim upon which relief may be granted, brought at the outset of the appeals litigation.

more
Shutterstock_1059713198.jpg

A claim under the Contract Disputes Act (CDA) must first be presented to and denied by the contracting officer (CO) before it can be appealed to a Board of Contract Appeals (BCA) or the Court of Federal Claims (COFC). Adjudicative forums have consistently held the CDA’s presentment requirement to be jurisdictional. That is, for a BCA or the COFC to exercise jurisdiction over a CDA appeal, the underlying claim must first have been presented to the CO for a final decision. Contractors may satisfy the presentment requirement by submitting the claim to the CO in accordance with the requirements of the CDA. While the CDA does not require the claim to be submitted in a particular form, it must typically provide a clear and unequivocal statement that gives the CO adequate notice of the basis and amount of the claim. The CO must then issue a final decision on the claim. The contractor may appeal the CO’s final decision at a BCA or the COFC within 90 days or 12 months, respectively.

In Avant Assessment v. U.S., No. 20-1185C, a decision issued on May 7, 2024, the COFC dismissed an appeal from a CDA claim for a lack of subject matter jurisdiction because the contractor failed to first present its claim to the CO. The appeal was part of a long-running litigation relating to contracts first issued by the U.S. Army in 2011 for foreign language testing materials to assess the proficiency of military linguists. The Army terminated the contracts for default in 2013, but following a successful appeal at the Armed Services Board of Contract Appeals (ASBCA), the default termination was converted into a termination for the government’s convenience. Following the successful convenience conversions, the contractor submitted termination settlement proposals to the CO, which were denied. After the CO’s denial, the contractor again appealed the CO’s final decision to the ASBCA. Notably, during the discovery phase in the second round of ASBCA litigation, the contractor learned that the government had not only retained the rejected testing materials but also “used” them by transferring them to a third party. Therefore, the contractor demanded payment for the rejected test materials. The contractor alleged that the Army had constructively accepted the rejected testing materials by retaining and using them after rejection. Alternatively, the contractor argued that the Army improperly rejected the testing materials. The ASBCA dismissed a large portion of the contractor’s claim for lack of jurisdiction since the contractor’s constructive acceptance claims had not first been first presented to the CO.

more
Shutterstock_2160344179.jpg

While the Contract Disputes Act provides no definition of a claim, the Federal Acquisition Regulation (FAR) § 2.101 defines a claim as a written demand or assertion by one of the contracting parties seeking, as a matter of right, the payment of a sum certain arising under or relating to the contract. The FAR further provides that a routine request for payment that is not in dispute when submitted is not a claim. However, such submissions may be converted to a claim by written notice to the contracting officer as provided in FAR § 33.206(a) if it is disputed as to the liability or amount or is not acted upon in a reasonable time. Finally, the FAR requires claims over $100,000 to be certified. To assess whether a submission is a CDA claim rather than a request for equitable adjustment (REA), contractors may typically look to three objective criteria:

  1. The submission meets the definition of a “claim”
  2. The submission includes a CDA certification
  3. The contractor must request a final decision from the contracting officer

Despite these objective criteria, it may not always be clear when an REA is converted into a “claim,” the denial or deemed denial of which can be appealed to a Board of Contract Appeals or the Court of Federal Claims (COFC). On August 29, 2024, the Armed Services Board of Contract Appeals (ASBCA) in ASBCA No. 63197 issued a decision on a government’s motion to dismiss for the contractor’s failure to convert an REA into a CDA claim. The underlying contract for medical coding services was issued by the Army in January 2018 using the government-provided browser-based Application Virtualization Hosting Environment (AVHE) for the United States Medical Command. Almost two years later, on November 18, 2019, the contractor submitted a “Request for Price Modification” seeking various cost adjustments. The pertinent portion of the request sought costs for lost production due to the government-imposed downtime for the AVHE system. In February 2021, the contractor provided supporting material to validate downtime costs in response to a government request for additional information. In July 2021, the contractor submitted a revised request for price modification labeled “Request for Equitable Adjustment,” seeking payment for downtime costs in the amount of $615,199 categorized as an unexpected loss.

more
Shutterstock_619806914-2.jpg

The Contract Disputes Act (CDA) requires contracting officers (COs) to issue their final decision on contractor claims in writing and mail or otherwise furnish the decision to the contractor. To be legally valid, the CO’s final decision must adhere to specific content requirements. For instance, 41 U.S.C. § 7103(e) requires the CO’s final decision to state the reasons for the decision and inform the contractor of its appeal rights. The appeals rights notice should include language substantially similar to the notice provided in Federal Acquisition Regulation (FAR) § 33.211(a)(4)(v). The CO is not required to include specific findings of fact in the final decision, and if included, such facts are not binding in a subsequent appeal. Notably, the FAR further expands upon the content requirements for the final decision. FAR § 33.211(a)(4) requires the final decision to include a description of the claim along with references to the relevant contract terms. The CO must also explain the factual areas of agreement and disagreement, and provide a statement of the decision along with a supporting rationale. However, despite the requirements to provide a supporting rationale, the CO’s final decision need not necessarily be voluminous. On appeal, dispute adjudicative forums rarely find that the final decision is legally defective due to a lack of sufficient rationale.

more

Timeliness of Motions for Dismissal Based Upon the Nonjurisdictional Sum Certain Requirement

Contract Claims Insights | TILLIT LAW PLLC