While the Contract Disputes Act (CDA) does not define a claim, the Federal Acquisition Regulation (FAR) § 2.101 defines a monetary claim as a written demand or assertion by a contracting party seeking, as a matter of right, the payment of money in a “sum certain.” Since the sum certain requirement is not included in the CDA, the Federal Circuit has held that the requirement is non-jurisdictional. Stated another way, a CDA claim does not need to include a sum certain for the Court of Federal Claims (COFC) or a relevant Board of Contract Appeals to exercise jurisdiction over it. Instead, the sum certain requirement is considered an element of a claim for relief that the contractor must satisfy in order to recover. The distinction is important because parties may raise a motion challenging the Court’s or the Board’s jurisdiction at any time. Meanwhile, if a party presents a defense based on the sum certain requirement after litigation has far progressed, it may be deemed to have forfeited the defense entirely. Therefore, the sum certain requirement is a mandatory but non-jurisdictional claim processing rule that is subject to forfeiture. It is somewhat unclear exactly when the claims litigation progresses to a point where a party loses the right to challenge a deficient sum certain. However, the Federal Circuit has indicated that forfeiture may apply as soon as the merits of the case are evaluated, including after the summary judgment stage.
In Armed Services Board of Contract Appeals (ASBCA) No. 63842, a decision issued on June 24, 2025, the Board granted the government’s motion to dismiss for failure to state a claim based on the sum certain requirement after concluding that the government had not forfeited its motion because it had filed the motion during discovery. The U.S. Army Corps of Engineers (USACE) awarded the underlying fixed-price contract in 2021 for approximately $19.5 million to install turbines and a generator rewind at the Philpotts Powerhouse in Virginia. One year into the contract, the contractor notified the government of its intent to pursue a price adjustment under the contract’s Economic Price Adjustment (EPA) clause. In December 2023, the contractor submitted a “merit-only” claim requesting that the CO determine the enforceability of the contract’s EPA clause and confirm the contractor’s right to an adjustment under the clause. The contractor did not seek a sum certain in its claim, representing that no quantum was involved. The CO denied the claim, and the contractor filed its appeal with the Board. During the subsequent appeals litigation, a little more than two weeks before the close of discovery, the government filed its motion to dismiss for failure to state a claim. In its motion, the government asserted that the contractor’s claim was essentially a monetary claim that should be dismissed for lacking a sum certain.
The Board agreed in holding that USACE had not forfeited its right to bring the motion and ruled that the contractor’s claim was required to include a sum certain. The decision compared the procedural facts of the present case with ECC International, LLC v. Secretary of the Army, 79 F.4th 1364 (2023), where the government was deemed to have forfeited a lack of sum certain defense by not raising it until after a hearing on the merits. The Board also cited its past precedent in ASBCA 63252, where it held that the government had not forfeited a lack of sum certain defense by raising it during discovery. In relying on these cases, the Board held that the appeals litigation in the present case had not far progressed when the government filed its motion to dismiss for failure to state a claim. Furthermore, the Board also found the government’s motion meritorious, noting that because the only significant consequence of a declaration that the contractor has the right to seek an adjustment under the contract’s EPA clause would be a price adjustment, the essence of the dispute was purely monetary in nature. Therefore, the contractor was not permitted to circumvent the sum certain requirement by reframing its monetary claim as a nonmonetary claim for declaratory judgment. Ultimately, the Board dismissed the contractor’s claim without prejudice because the contractor’s monetary claim failed to meet the nonjurisdictional but mandatory sum certain requirement.
The sum certain requirement is not included in the CDA and is consequently a mandatory claim processing rule, not a jurisdictional requirement. Thus, the party requesting a dismissal based on the sum certain requirement must file a motion to dismiss for failure to state a claim rather than a motion to dismiss for lack of (subject matter) jurisdiction. Since the requirement is not jurisdictional, a sum certain defense may not be raised at any point and is subject to forfeiture if the party asserting it waits until appeals litigation has far progressed. In the appeal described here, the Board decided that the government’s motion to dismiss was timely because it was filed during the discovery stage. It is worth noting that, although not evident from the decision, the determining factor underlying the Board’s decision on the timeliness of the government’s motion may have been that the Board had not yet considered the merits of the contractor’s appeal. Indeed, in ECC International, the Federal Circuit indicated that forfeiture may be applicable as soon as the adjudicative forum considers the merits of the case, including after the summary judgment stage. While it is true that in most cases, parties file a motion for summary judgment after the close of discovery, a summary judgment motion may also be filed before or during discovery. If a motion to dismiss for failure to state a claim based on the sum certain requirement is filed after the summary judgment decision, the adjudicative forum may well find the motion untimely in ruling that the litigation has far progressed under the ECC International standard, even if the motion to dismiss is filed before the close of discovery.
This Federal Contract Claims Insight is provided as a general summary of the applicable law in the practice area and does not constitute legal advice. Contractors wishing to learn more are encouraged to consult the TILLIT LAW PLLC Client Portal or Contact Us to determine how the law would apply in a specific situation.