The government may provide performance workload estimates during the solicitation phase to assist offerors in preparing their bids or proposals. If due care is not exercised in preparing these estimates and the contractor relies on them, the government may be liable for breach of contract. Due care requires the government to base its estimates on all relevant information reasonably available at the time. If the government fails to base its estimate on the latest available data or is otherwise negligent in preparing it, the contractor may recover any resulting damages. To prevail in such a claim, the contractor must show that it is more likely true than not true that the government’s estimate, on which it relied to prepare its offer, was inadequately or negligently prepared. In a typical case, the contractor must prove that the government’s negligent estimate misled it into submitting an unfairly low bid. The contractor may also need to demonstrate that the government had exclusive control over the information used in developing the estimate, which was unavailable to the contractor from other sources.
In Agility Defense & Government Services, Inc. v. United States, 847 F.3d 1345 (2017), the United States Court of Appeals for the Federal Circuit held that the government was in breach of contract because it negligently estimated its requirements and the contractor relied on the government’s estimates. The Defense Logistics Agency (DLA) awarded the underlying contract for the disposal of surplus military property at Defense Reutilization and Marketing Offices (DRMOs) upon the military’s departure from an area of operations. While the DLA usually handled the requirement internally, it became aware of planned troop movements, which were expected to cause a surge in workload that it was not equipped to handle without contracting out the requirement. During the solicitation phase, DLA issued several amendments relating to anticipated workload and costs. Under one such amendment, DLA provided offerors with a website that showed historical workload, including the number of military property items received for processing and the amount of scrap processed for each DRMO. In a later amendment, the DLA provided offerors with a workload chart that projected a stable workload for the first two years of the contract, followed by a progressive decline of 75%, 50%, and 30% in the option years three to five, respectively. The government also provided the contractor a workload baseline for each DRMO which utilized the same historical data.
Relying on the government’s estimates, the contractor submitted a successful proposal to operate six DRMOs at a fixed price of roughly $45 million per year for the five-year contract, which was much lower than the other two offers of approximately $68 million and $71 million, respectively. Upon commencing work on the six DRMO sites, the contractor realized that it had inherited a significant backlog of line items on five of the six sites, totaling 30 weeks of additional work for one of the sites, as compared to the government-furnished baseline data. In other words, the actual workload was significantly higher than the government’s estimates. A little over two years after the commencement of performance, the contract was terminated for the government’s convenience. Following the termination, the contractor submitted two claims for increased costs totaling roughly $ 4.6 million. In response, the contracting officer (CO) partially approved one of the claims for $ 236,363.93 but denied the remaining amount. The contractor filed suit at the Court of Federal Claims (COFC), which found that the contractor had experienced workloads much higher than the baseline data during the base year of performance at five of the six DRMO sites. Specifically, the COFC found that the contractor’s workload on the five sites ranged from 156.5% to 358.4% higher than the government-furnished baseline data. These findings notwithstanding, the COFC found that DLA was not liable for providing negligent or misleading estimates because it had furnished reasonably available historical data from which the contractor could extrapolate the government’s future needs. The contractor appealed to the Federal Circuit.
The Federal Circuit began its analysis by determining that the workload chart provided by the DLA during the solicitation phase was itself an estimate of projected requirements because it was intended to assist offerors in preparing their proposals. Next, the Federal Circuit determined that the COFC had clearly erred in holding that the DLA had furnished a realistic estimate just because it had provided the contractor with historical workload data. The Federal Circuit explained that providing historical data does not automatically guarantee that the government’s estimates are realistic. While it is true that estimates may be obtained from previous requirements, if the government is in possession of more current information different from historical requirements, it has the obligation to develop more accurate estimates based on the most current information available to it. In this case, the most current information differed from the government’s historical requirements because the DLA was aware of planned troop movements that would cause a surge in workload. In fact, this anticipated surge was one of the primary reasons the DLA had decided to award the underlying contract. Under these circumstances, it was insufficient for the DLA to merely furnish historical workload data as an estimate because it was not the most current information available to it. Finally, it was clear from the contractor’s proposal that it had relied on the government’s outdated workload estimates in preparing its pricing. Consequently, the Federal Circuit reversed the COFC’s denial of the negligent estimate claim and remanded the case for the calculation of an equitable adjustment.
When providing estimates regarding its requirements, the government is obligated to act in good faith and exercise due care. If the government supplies inaccurate or unrealistic workload estimates to offerors, it may subsequently be held liable for any resulting damages. That said, the government is under no obligation to fully guarantee its estimates or perfectly forecast its workload requirements. Any government estimate must withstand logical scrutiny and be based upon all relevant information that is reasonably available to the government at the time the estimate is prepared. The government may use historical requirements to develop its workload estimates, but solely relying on such an approach is not inherently reasonable in every scenario. If more current information, different from the historical requirements, is available, the government must use that information to develop its estimates. If the government fails to do so, it may be held liable, as demonstrated in the case above. To obtain recovery in such cases, the contractor must prove the inadequacy of the estimates by a preponderance of the evidence. Additionally, the contractor should have relied on the government’s negligent estimates in preparing its offer and should be able to demonstrate that the pertinent information underlying those estimates was exclusively available to the government.
This Federal Contract Claims Insight is provided as a general summary of the applicable law in the practice area and does not constitute legal advice. Contractors wishing to learn more are encouraged to consult the TILLIT LAW PLLC Client Portal or Contact Us to determine how the law would apply in a specific situation.




