The government may provide design specifications to the contractor for the performance of a government contract, directing work and implying a warranty that the supplied specifications are free of defects. Under the Spearin doctrine, if the government’s design specifications are then found defective or result in unsatisfactory performance, the contractor is permitted to recover its increased costs of performance attributable to the defective specifications. To obtain such recovery, the contractor must prove a causal connection between the defective specifications and the additional costs incurred to resolve the issue. Significantly, however, to recover under the Spearin doctrine, a contractor must demonstrate that it substantially complied with the government-furnished plans and specifications and that, despite its compliance, the end result was unsatisfactory. On the other hand, if the contractor does not comply with the government’s specifications, it may not recover its increased costs of performance under the Spearin doctrine, even if the government's design specifications are ultimately found defective.
In Armed Services Board of Contract Appeals (ASBCA) No. 62627, a decision issued on February 13, 2024, the Board determined that the contractor could not recover under the Spearin doctrine because it had failed to demonstrate compliance with the government-supplied specifications. The Naval Facilities Engineering Systems Command (NAVFAC) Southwest (SW) awarded a task order for roughly $4.3 million under a previously issued indefinite delivery, indefinite quantity (IDIQ) contract for the renovation of Building 53423 at the Marine Corps Base Camp Pendleton in California. Among other things, the project required the contractor to remove and dispose of all existing hazardous materials, including asbestos, and to perform abatement and cleanup services as necessary. The project also required the removal and replacement of non-load-bearing partition walls to support potential space reconfiguration. The order noted that the removal of any additional walls during construction would be handled as a modification. As relevant to the interior walls, the government stated in RFI 20, a pre-award request for information (RFI), that there may be small amounts of asbestos tiles under the wall framing where interior walls were being demolished.
After the commencement of the construction work, the contractor brought to the government’s attention an issue concerning asbestos abatement with respect to the corridor walls. The contractor had discovered asbestos-containing floor tile and mastic under the concrete mop curbs in the corridors. To resolve this issue, the contractor submitted a cost proposal of $163,234 to demolish and replace the corridor walls. A few months later, the government requested that the contractor provide additional information relating to the demolition of the corridor walls. Upon receiving the requested information, the government informed the contractor that it would not proceed with the contractor’s recommendation to demolish and replace four non-load-bearing walls because these walls did not pose a safety risk to the building’s inhabitants. The contractor then submitted an RFI concerning the demolition of the corridor wall to effectuate asbestos abatement under the mop curbs, which ran the length of the corridor walls. The government again stated that it did not direct the contractor to demolish the corridor walls. The contractor resubmitted the RFI, and a few days later, informed the government that it would nevertheless proceed with the demolition of the corridor walls and later submit a request for equitable adjustment (REA).
After demolishing the corridor walls, the contractor submitted an REA, which was later converted into a claim under the Contract Disputes Act (CDA). The contracting officer (CO) denied the contractor’s claim by issuing a final decision, which concluded that the government had not directed the contractor’s performance. In the ASBCA appeal that followed, the contractor took the position that the government-supplied design specifications were defective because they failed to address the asbestos threat in the corridor walls. The contractor argued that when the CO directed the contractor to perform the contract without removing the corridor walls as suggested by the contract, it decided the means and method for the contractor’s performance. In other words, the contractor asserted that the Board consider the government’s direction to retain the corridor walls as a defective design specification and permit recovery for the increased costs associated with the corridor walls under the Spearin doctrine. However, the Board was unpersuaded by the contractor’s arguments. The ASBCA reminded the contractor that the implied warranty that the government’s specifications are free of defects runs only to contractors that comply with those specifications. Here, the contractor did not comply with the government’s clear direction to retain the corridor walls. Therefore, even assuming the CO’s directions were the type of design specifications to which the Spearin doctrine typically applies, the contractor could not recover its increased costs because it had failed to comply with the CO’s directions by proceeding to demolish the corridor walls.
The Spearin doctrine allows a contractor to recover its increased costs of performance when the government’s defective design specifications result in undesirable outcomes. However, only contractors that can demonstrate substantial compliance with the government-supplied design specifications may benefit from the implied warranty of specifications contemplated under the doctrine. Furthermore, it is the contractor’s burden to prove that it substantially complied with the government’s specifications. In cases where the contractor is unable to carry that burden, it may not recover its increased costs of performance even if the government’s specifications later prove defective. That being said, contractors should remember that they can still stop performing when it becomes evident from the performance results that the government-supplied design specifications are defective to such a degree that complying with them is commercially impracticable. Ultimately, in situations similar to the case described above, where the contractor does not show that compliance with the government-supplied specifications is commercially impracticable, and also fails to adhere to the specifications in the first place, it may not recover its increased costs of performance even if the design specifications eventually prove defective.
This Federal Contract Claims Insight is provided as a general summary of the applicable law in the practice area and does not constitute legal advice. Contractors wishing to learn more are encouraged to consult the TILLIT LAW PLLC Client Portal or Contact Us to determine how the law would apply in a specific situation.




