Shutterstock_2686388569-2.jpg

Demonstrating Compliance with Specifications for Recovery Under the Spearin Doctrine

The government may provide design specifications to the contractor for the performance of a government contract, directing work and implying a warranty that the supplied specifications are free of defects. Under the Spearin doctrine, if the government’s design specifications are then found defective or result in unsatisfactory performance, the contractor is permitted to recover its increased costs of performance attributable to the defective specifications. To obtain such recovery, the contractor must prove a causal connection between the defective specifications and the additional costs incurred to resolve the issue. Significantly, however, to recover under the Spearin doctrine, a contractor must demonstrate that it substantially complied with the government-furnished plans and specifications and that, despite its compliance, the end result was unsatisfactory. On the other hand, if the contractor does not comply with the government’s specifications, it may not recover its increased costs of performance under the Spearin doctrine, even if the government's design specifications are ultimately found defective.

In Armed Services Board of Contract Appeals (ASBCA) No. 62627, a decision issued on February 13, 2024, the Board determined that the contractor could not recover under the Spearin doctrine because it had failed to demonstrate compliance with the government-supplied specifications. The Naval Facilities Engineering Systems Command (NAVFAC) Southwest (SW) awarded a task order for roughly $4.3 million under a previously issued indefinite delivery, indefinite quantity (IDIQ) contract for the renovation of Building 53423 at the Marine Corps Base Camp Pendleton in California. Among other things, the project required the contractor to remove and dispose of all existing hazardous materials, including asbestos, and to perform abatement and cleanup services as necessary. The project also required the removal and replacement of non-load-bearing partition walls to support potential space reconfiguration. The order noted that the removal of any additional walls during construction would be handled as a modification. As relevant to the interior walls, the government stated in RFI 20, a pre-award request for information (RFI), that there may be small amounts of asbestos tiles under the wall framing where interior walls were being demolished.

After the commencement of the construction work, the contractor brought to the government’s attention an issue concerning asbestos abatement with respect to the corridor walls. The contractor had discovered asbestos-containing floor tile and mastic under the concrete mop curbs in the corridors. To resolve this issue, the contractor submitted a cost proposal of $163,234 to demolish and replace the corridor walls. A few months later, the government requested that the contractor provide additional information relating to the demolition of the corridor walls. Upon receiving the requested information, the government informed the contractor that it would not proceed with the contractor’s recommendation to demolish and replace four non-load-bearing walls because these walls did not pose a safety risk to the building’s inhabitants. The contractor then submitted an RFI concerning the demolition of the corridor wall to effectuate asbestos abatement under the mop curbs, which ran the length of the corridor walls. The government again stated that it did not direct the contractor to demolish the corridor walls. The contractor resubmitted the RFI, and a few days later, informed the government that it would nevertheless proceed with the demolition of the corridor walls and later submit a request for equitable adjustment (REA).

After demolishing the corridor walls, the contractor submitted an REA, which was later converted into a claim under the Contract Disputes Act (CDA). The contracting officer (CO) denied the contractor’s claim by issuing a final decision, which concluded that the government had not directed the contractor’s performance. In the ASBCA appeal that followed, the contractor took the position that the government-supplied design specifications were defective because they failed to address the asbestos threat in the corridor walls. The contractor argued that when the CO directed the contractor to perform the contract without removing the corridor walls as suggested by the contract, it decided the means and method for the contractor’s performance. In other words, the contractor asserted that the Board consider the government’s direction to retain the corridor walls as a defective design specification and permit recovery for the increased costs associated with the corridor walls under the Spearin doctrine. However, the Board was unpersuaded by the contractor’s arguments. The ASBCA reminded the contractor that the implied warranty that the government’s specifications are free of defects runs only to contractors that comply with those specifications. Here, the contractor did not comply with the government’s clear direction to retain the corridor walls. Therefore, even assuming the CO’s directions were the type of design specifications to which the Spearin doctrine typically applies, the contractor could not recover its increased costs because it had failed to comply with the CO’s directions by proceeding to demolish the corridor walls.

The Spearin doctrine allows a contractor to recover its increased costs of performance when the government’s defective design specifications result in undesirable outcomes. However, only contractors that can demonstrate substantial compliance with the government-supplied design specifications may benefit from the implied warranty of specifications contemplated under the doctrine. Furthermore, it is the contractor’s burden to prove that it substantially complied with the government’s specifications. In cases where the contractor is unable to carry that burden, it may not recover its increased costs of performance even if the government’s specifications later prove defective. That being said, contractors should remember that they can still stop performing when it becomes evident from the performance results that the government-supplied design specifications are defective to such a degree that complying with them is commercially impracticable. Ultimately, in situations similar to the case described above, where the contractor does not show that compliance with the government-supplied specifications is commercially impracticable, and also fails to adhere to the specifications in the first place, it may not recover its increased costs of performance even if the design specifications eventually prove defective.

This Federal Contract Claims Insight is provided as a general summary of the applicable law in the practice area and does not constitute legal advice. Contractors wishing to learn more are encouraged to consult the TILLIT LAW PLLC Client Portal or Contact Us to determine how the law would apply in a specific situation.

Related Insights

Shutterstock_2160344179.jpg

While the Contract Disputes Act provides no definition of a claim, the Federal Acquisition Regulation (FAR) § 2.101 defines a claim as a written demand or assertion by one of the contracting parties seeking, as a matter of right, the payment of a sum certain arising under or relating to the contract. The FAR further provides that a routine request for payment that is not in dispute when submitted is not a claim. However, such submissions may be converted to a claim by written notice to the contracting officer as provided in FAR § 33.206(a) if it is disputed as to the liability or amount or is not acted upon in a reasonable time. Finally, the FAR requires claims over $100,000 to be certified. To assess whether a submission is a CDA claim rather than a request for equitable adjustment (REA), contractors may typically look to three objective criteria:

  1. The submission meets the definition of a “claim”
  2. The submission includes a CDA certification
  3. The contractor must request a final decision from the contracting officer

Despite these objective criteria, it may not always be clear when an REA is converted into a “claim,” the denial or deemed denial of which can be appealed to a Board of Contract Appeals or the Court of Federal Claims (COFC). On August 29, 2024, the Armed Services Board of Contract Appeals (ASBCA) in ASBCA No. 63197 issued a decision on a government’s motion to dismiss for the contractor’s failure to convert an REA into a CDA claim. The underlying contract for medical coding services was issued by the Army in January 2018 using the government-provided browser-based Application Virtualization Hosting Environment (AVHE) for the United States Medical Command. Almost two years later, on November 18, 2019, the contractor submitted a “Request for Price Modification” seeking various cost adjustments. The pertinent portion of the request sought costs for lost production due to the government-imposed downtime for the AVHE system. In February 2021, the contractor provided supporting material to validate downtime costs in response to a government request for additional information. In July 2021, the contractor submitted a revised request for price modification labeled “Request for Equitable Adjustment,” seeking payment for downtime costs in the amount of $615,199 categorized as an unexpected loss.

more
Shutterstock_2474143053.jpg

Firm-fixed-price contracts place maximum risk and full responsibility upon the contractor for all costs and resulting profit or loss incurred in performing a government contract. Fixed price contracts provide for a price that is not subject to any adjustment based on the contractor’s cost experience. Meanwhile, fixed-price contracts with economic price adjustments provide for upward or downward revisions of the stated contract price upon the occurrence of specified contingencies. There are three general types of price adjustments. First, price adjustments based on established prices provide for increases or decreases from an agreed-upon level in published prices of specific items. Second, adjustments based on actual costs of labor or materials contemplate increases or decreases in the specified costs of labor or materials actually experienced by the contractor during contract performance. Finally, adjustments based on labor or material cost indexes provide for increases or decreases in labor or material cost standards or indexes identified explicitly in the contract. In fixed-price contracts that do not provide for economic price adjustments, the contractor assumes the risk of unexpected costs not attributable to the government.

more
Shutterstock_2221857605.jpg

Contractors may sometimes encounter unforeseen conditions that make a government contract commercially impracticable because performance would cause extreme and unreasonable difficulty, expense, injury, or loss. Unless the contractor has assumed the risk of the unforeseen condition, a finding of commercial impracticability excuses the contractor from performing. In other situations, commercial impracticability may be treated as a constructive change, warranting an equitable adjustment due to the substantial, unforeseen costs imposed upon the contractor. Whether the performance of a contract would be commercially impracticable is a question of fact to be resolved on a case-by-case basis. Therefore, adjudicative forums have consistently declined to adopt a bright-line rule providing that a certain percentage of cost overrun automatically constitutes commercial impracticability. However, due to the potential for abuse, the standard for establishing commercial impracticability is challenging to meet, and contractors are not entitled to relief merely because they are unable to sustain their profit margins.

In Armed Services Board of Contract Appeals (ASBCA) No. 63615, a decision issued on May 19, 2025, the Board granted the agency summary judgment on the issue of commercial impracticability when the contractor suffered a 37% cost overrun on a construction contract. The U.S. Army Corps of Engineers (USACE) issued the underlying contract for construction work at Placement Area No. 10 in the Corpus Christi Ship Channel. The total adjusted contract price following all modifications was $11,046,369.04. During performance, the contractor encountered excessive erosion on the south side of the placement area. Subsequently, the work to address the erosion was added to the contract via two bilateral contract modifications addressing the inland and shoreline sides of the placement area, totaling $909,332.04. However, even after the modifications, the contractor continued to incur costs and expend additional resources. A year after the contract was deemed substantially complete, the contractor submitted certified claims asserting entitlement to roughly $3,560,723.65 in cost overruns for work associated with the first modification and $447,522.64 in cost overruns for the second modification. These claims were denied by the contracting officer (CO) in their entirety.

more
Shutterstock_664567501-3.jpg

Under the Spearin doctrine, when the government furnishes design specifications directing the contractor on how to undertake performance on a contract, it provides an implied warranty that the contractor will be able to perform the contract satisfactorily if it adheres to the government’s specifications. The doctrine allows contractors to transfer to the government the risk of increased costs resulting from defective specifications. Notably, however, the Spearin doctrine only applies when the defective specifications are design specifications as opposed to performance specifications. Design specifications expressly describe how contract performance must be undertaken and do not permit the contractor to make any deviations. Meanwhile, performance specifications state the overall objectives that must be achieved but leave the decisions on how to achieve those objectives at the discretion of the contractor. Since design specifications do not allow deviations or grant the contractor discretion in achieving contractual objectives, the government implicitly warrants that design specifications are free from defects. Consequently, when the government’s design specifications are defective or result in unsatisfactory performance the government is deemed to have breached its implied warranty of specifications under the Spearin doctrine. In such cases, the contractor may recover all proximate costs stemming from the government’s breach.

more

Demonstrating Compliance with Specifications for Recovery Under the Spearin Doctrine

TILLIT LAW Federal Contract Claims Insights