Insight 7 - Substack.jpg

Claims Based on Impracticability of Performance

The impracticability of performance doctrine is applicable in situations where the contractor’s performance of a contract, although not impossible, is rendered impracticable due to a problem encountered that was unforeseen at the time of formation of the contract. This impracticability of performance may be caused by a variety of unforeseen situations faced by the contractor during performance, including substantial increases in costs, significant problems encountered, or technological changes. Contractors must satisfy at least three conditions for the doctrine of impracticability to be applicable. First, the contractor must demonstrate that an unexpected condition or contingency occurred during the performance of the contract. Secondly, the contractor must show that it did not assume the risk of that contingency either expressly or through trade usage or custom. Finally, the contractor must prove that the unexpected condition or contingency caused the impracticability of performance.

Existence of Unexpected Condition or Contingency

The claim adjudicating forum may consider several factors to determine whether an unexpected condition or contingency exists. For instance, it may consider whether any other similarly situated contractor could have performed the contract. That is, whether the requirements or conditions are subjectively impractical for the contractor bringing the claim or impractical for any contractor in its position. Another factor to consider is the extent of the contractor’s efforts to meet the performance requirements in face of the contingency. Generally, the contractor must demonstrate that it was diligent and exhaustive in its attempts to perform the contract. In cases where the contractor alleges commercial impracticality or unfeasibility, it must prove that the performance costs would be so high that performing the contract would not make commercial sense. Notably, non-substantial increases in contract price will not result in successful commercial impracticability claims.

Assumption of Risk

After establishing the existence of an unexpected condition or contingency, the contractor must show that it did not assume the risk of the occurrence of such a condition. Depending on the specific facts, contractors may find this challenging because the contractor assumes various performance risks when entering a federal contract. For instance, the contractor generally assumes the risk of competence. Consequently, the contractor is presumed to be, at a minimum, just as competent as other contractors in the industry. Similarly, in claims of commercial impracticability, contractors may assume the risk of scarcity of necessary materials or fluctuations in price. Meanwhile, in technical impracticability claims such as those arising due to defective specifications, the contractor generally assumes the risk of non-performance if it had proposed to perform the contract according to its own specifications. This is especially true if a contractor possesses expertise in the field relevant to the contract and it is determined that the government relied on that expertise. To overcome this assumption, contractors must typically demonstrate that they performed according to the specifications provided by the government.

Causation

Finally, to successfully establish a claim based on impracticability, contractors must show that the unforeseen condition or contingency caused the issues that made performance impracticable. This is generally demonstrated by showing the existence of a logical nexus between the unexpected condition or contingency and the contractor’s inability to perform successfully. Contractors can establish causation by proving that had it not been for the unforeseen condition or contingency, they would have performed on the contract as stipulated during contract formation or subsequent modifications. In establishing causation, contractors may also have to show that the contingency was beyond their control and that they did not contribute to the impracticability of performance.

To prove the impracticability of performance, contractors must demonstrate the existence of a contingency or conditions that were not reasonably foreseeable at the time of formation. Additionally, contractors must prove that they did not assume the risk of the contingency and show that the contingency led to the impracticability of performance. Depending on the facts underlying the impracticability claim, contractors may present several types of evidence to support the existence of a contingency. Such evidence may include expert testimony or documentary evidence such as cost estimates, invoices, communications, and performance reports. Once the presence of unforeseen circumstances has been established, contractors must show that they did not assume the risk of the occurrence of that contingency either expressly under the terms of the contract or implicitly, such as by trade usage or custom. Finally, to successfully establish an impracticability claim, contractors must prove that the contingency caused the impracticability of performance. By understanding the elements of an impracticability claim, contractors can be better positioned to obtain recovery when unforeseen circumstances or contingencies hinder their ability to perform.

This Federal Contract Claims Insight is provided as a general summary of the applicable law in the practice area and does not constitute legal advice. Contractors wishing to learn more are encouraged to consult the TILLIT LAW PLLC Client Portal or Contact Us to determine how the law would apply in a specific situation.

Related Insights

Insight 5 - Substack.jpg

The primary method for managing risks associated with latent physical conditions encountered in construction projects is the differing site conditions clause in Federal Acquisition Regulation (FAR) 52.236-2. Since fully redressable claims under specifically included contract clauses may not be brought under separate breach of contract claims, most claims for hidden site conditions are brought under the differing site conditions clause. However, certain federal contracts for smaller construction projects awarded through simplified procedures, and some custom-negotiated construction contracts may lack a well-defined differing site conditions clause. In such cases, contractors must pursue their claims arising out of unforeseen conditions, such as claims related to subsurface conditions under traditional breach of contract theories. Additionally, when faced with unforeseeable events like extreme and unpredictable weather or unanticipated changes in labor conditions that are not typically covered by the differing site conditions clause, construction contractors may opt to initiate breach of contract claims to recover their increased costs.

The Government’s non-disclosure or misrepresentation of information material to site conditions are two breach of contract actions available to construction contractors in such situations. To be successful in a non-disclosure claim, the construction contractor must demonstrate that the Government possessed information pertinent to a material site condition, which it failed to disclose to the contractor. The contractor must also establish that the presence of the material site condition could not have been readily determined through a site inspection or other reasonable methods. Government misrepresentation is the other breach of contract claim commonly applicable in contracts without a differing site conditions clause. A misrepresentation claim is essentially based on the Government breaching its duty to disclose its superior knowledge of the site condition. To prove that the Government breached its duty to disclose, the Court of Federal Claims (COFC) has previously required that the contractor demonstrate Government culpability. One way of demonstrating Government culpability is by proving that the Government knew that the contractor was unaware of the differing site conditions. However, the Federal Circuit has recently rejected the Government culpability requirement, making contractor claims easier to prove in such situations. Therefore, depending upon the circumstances, the adjudicative forum’s analysis for a breach of contract claim for Government misrepresentation is similar if not identical to a differing site conditions claim.

more
TLF-Contract-Claims-Insight-51.jpg

Contractors may sometimes make mistakes due to erroneous assumptions during the formation of federal contracts. Such mistakes may include an inaccurate assessment of costs, level of effort, or scope of the contract. For certain such mistakes, contractors may be able to obtain relief if the government shares their mistaken belief during the formation of the contract. Federal Acquisition Regulation (FAR) § 14.407-4(a) permits the correction of such mistakes through contract modifications, provided the mistake is not discovered until after award and if other requirements of the section are met. To obtain recovery based on the theory of mutual mistake, the contractor must demonstrate that: (1) the government and the contractor were both mistaken in their belief regarding a fact, (2) that mistaken belief constituted a basic assumption underlying the contract, (3) the mistake had a material effect on the bargain struck by the parties, and (4) the contractor did not assume the risk of the mistake. If successful in proving these elements of mutual mistake, contractors may be able to obtain monetary relief or relief from their obligation of performance on the contract.

Mutuality of Belief

more
Insight 44 - Substack.jpg

Due to the highly regulated nature of federal government contracts, their formation and administration are governed by a well-defined set of rules. Despite this, government contracts rely on a foundation of mutual trust and cooperation between the government and its contractors. Parts of this invisible layer of obligation are embedded in the implied duties of cooperation, good faith, and fair dealing. Therefore, while related and somewhat interchangeable concepts, these implied duties are inherent to all government contracts and help ensure a successful, productive, and professional relationship between the contracting parties. However, from time to time, the Government may violate these implied duties, giving rise to contractor claims. Understanding these duties empowers contractors to navigate potential issues by identifying causes of action for Government breaches that result in disruption in performance or monetary damages. Therefore, a general discussion distinctly describing these obligations may be helpful to contractors alleging Government violations during contract performance.

o Duty of Cooperation

The Government’s duty to cooperate during the performance phase is as inherent to a government contract as the Government’s right to expect performance in accordance with specifications. Since both parties are required to work together as partners to achieve common contractual objectives, a lack of cooperation during performance by the Government may, and often does, become a source of disputes. When facing scenarios where contractors suspect a lack of adequate cooperation by the Government, they should evaluate the Government’s conduct in the context of the contract’s overall objectives. If the conduct at issue is inconsistent with the Government’s stated mission needs or hinders the contractor’s performance, the Government may be in breach of its duty of cooperation. The Government’s duty to cooperate during performance may be viewed independently by adjudicative forums in accordance with the facts at issue or in contrast with its treatment of other similarly situated contractors. Understanding the government's duty to cooperate empowers contractors to identify potential roadblocks and seek redress for hindered performance.

more
TLF-Contract-Claims-Insight-53.jpg

The government may terminate a federal contract if the contractor fails to meet its contractual obligations. The contracting officer (CO), in such cases, issues a final decision terminating the contract for default and outlines the reasons for the default. In the event of a termination for default, the government is only liable to the contractor for the portion of the contract that was already performed. While the CO may exercise discretion to terminate a contract for default, such a decision is appealable to the Board of Contract Appeals or the Court of Federal Claims (COFC) pursuant to the Contract Disputes Act (CDA). The CO’s decision to terminate may be set aside by the adjudicative forum if it is arbitrary, capricious, or constitutes an abuse of the CO’s discretion. For instance, a decision to terminate for default may be arbitrary and capricious if there is a lack of nexus between the CO’s decision to terminate the contract for default and the contractor’s performance on the contract. In such situations, while the concerned adjudicative forum may lack the ability to provide injunctive relief, it may nevertheless convert the CO’s default termination to one for the government’s convenience.

more

Claims Based on Impracticability

TILLIT LAW Federal Contract Claims Insights