Insight #25-10 - Bid Protests.jpg

Timeliness and Scope of Requests for Reconsideration in GAO Protests

Government Accountability Office (GAO) bid protest regulations provide government agencies and protestors 10 days to file their requests for reconsideration after the basis for reconsideration is known or should have been known. This typically means that in the absence of significant development or changes, the parties have 10 days from the issuance of the GAO’s protest decision to file their request for reconsideration. Requests to change or modify GAO’s recommended remedy are also considered requests for reconsideration and when filing such requests, the parties must adhere to the 10-day filing deadline. If the request for reconsideration is untimely, the GAO may not consider it, regardless of the party filing the request. This is because GAO regulations do not contain a provision granting the office discretion to consider untimely requests for reconsideration, even when a significant issue is involved or for good cause shown. Thus, unsuccessful protestors who wish to file requests for reconsideration with the GAO should ensure strict adherence to the 10-day filing deadline.

On December 12, 2024, the GAO sustained a post-award bid protest in B-422938; B-422938.2, finding that the government’s answer to a contractor question during the Q&A period amounted to a mandatory solicitation requirement that had to be met at the time of proposal submission, and which the awardee’s proposal had failed to satisfy. This protest was the subject of the year’s first TILLIT LAW Featured Insight article published on January 2, 2025. In that post-award protest decision, the GAO concluded that the Air Force had erred in awarding an approximately $180 M task order for portable satellite terminals to a small business holder of the National Aeronautics and Space Administration (NASA) Solution for Enterprise-Wide Procurement (SEWP) indefinite delivery, indefinite quantity (IDIQ) contract. The protestor’s solution, which was technically acceptable and met solicitation requirements at the time of proposal submission, had a total evaluated price of approximately $300 M. The GAO recommended that the Air Force either reevaluate the proposals and issue the award to an offeror that proposed a terminal assembly that met the solicitation requirements or amend the solicitation to reflect the government’s actual needs.

On January 15, 2025, the Air Force filed a request with the GAO to reconsider and modify its recommendations in B-422938; B-422938.2. The agency cited significant expenses and unacceptable delays in implementing the recommendations as reasons for its reconsideration request. The Air Force argued that implementing one of the two recommendations would necessarily require terminating the task order for the government’s convenience while subjecting the agency to termination costs. Notably, the protestor had filed its protest more than five days following the debriefing, which meant that performance was not automatically stayed during the pendency of the GAO protest. Additionally, the Air Force had not voluntarily stayed performance, which meant that it would owe the previous contractor a portion of the obligated amount for performance until the termination date, along with any termination costs. The agency also provided that if the proposals were reevaluated, as the only technically acceptable proposal received by the Air Force, the protestor would most likely be the awardee, despite having proposed a total evaluated price approximately $120 M higher than the awardee’s solution. Alternatively, resoliciting an amended solicitation would delay the acquisition by more than 18 months, which was unacceptable from a readiness standpoint.

The GAO began its analysis by first acknowledging the cost and readiness concerns raised by the agency as barriers to implementing its recommendations. However, despite recognizing these concerns, the GAO dismissed the Air Force’s request for reconsideration because it was untimely filed. The GAO explained that its regulations required requests for reconsideration to be filed within 10 days after the basis for reconsideration is known or should have been known. In the present case, over a month had passed between the issuance of the GAO’s decision and the Air Force’s request for reconsideration. Furthermore, the Air Force did not argue that there had been any significant changes or developments in that month that would have informed its request. On the contrary, the agency was aware of the cost and readiness concerns raised in its reconsideration request during the pendency of the protest. The GAO also noted the Air Force’s failure to raise its concerns during the protest as objections to the protestor’s ability to demonstrate competitive prejudice or to the impracticability of its requested remedies.

While the GAO acknowledged that the agency provided letters from senior Air Force officials dated early January 2025, which described the potential impacts of implementing its recommendation, it nevertheless dismissed the request, noting that these potential impacts were known or should have been known to the agency at the time the decision was issued on December 12, 2024. The Air Force was also reminded that by allowing performance to continue during the period between the issuance of the decision and the late-filed request for reconsideration, the agency only exacerbated the costs of potential termination or reprocurement delays it had cited as concerns in implementing the GAO’s recommendations. Ultimately, in dismissing the Air Force’s request, the GAO noted the absence of a “significant issue” exception to its timeliness rules governing the filing of requests for reconsideration. Thus, the protest was dismissed because the governing bid protest regulations did not give the GAO discretion to reconsider untimely filed requests for reconsideration.

Parties in a GAO protest may file a request for reconsideration of their protests within 10 days after the issuance of the protest decision. Contractors should strictly adhere to this 10-day deadline to file their reconsideration requests as the GAO does not have the discretion to consider late-filed requests even in the presence of a significant issue or good cause. Contractors should be mindful that requests to change or modify the GAO’s recommended remedy are considered reconsideration requests and subject to the same 10-day deadline. It is also worth noting that the government may not typically raise threshold issues such as lack of prejudice to the protestor for the first time in its request for reconsideration, if such issues can be appropriately raised during the pendency of the protest. To properly raise such issues in a request for reconsideration, the agency must demonstrate that it did not and could not have known of the relevant issues while the protest was pending. In rare cases where the reason for the reconsideration request is known after the protest decision has been issued, the parties must submit their requests within 10 days of discovering the reason. In such cases, a showing of significant changes or developments after the issuance of the protest decision would likely be necessary to support the reconsideration request.

This Bid Protest Insight is provided as a general summary of the applicable law in the practice area and does not constitute legal advice. Contractors wishing to learn more are encouraged to consult the TILLIT LAW PLLC Client Portal or Contact Us to determine how the law would apply in a specific situation.

Related Insights

TLF-Bid-Protest-Insight-7.jpg

For its bid protest function, the Government Accountability Office (GAO) has strict timeliness rules for protest submissions. These timeliness rules are designed so that protestors may receive an effective and efficient resolution to their bid protests without unduly jeopardizing or delaying the procurement at issue. Protestors must file pre-award protests based on alleged improprieties in a solicitation before the time established for the receipt of proposals. Meanwhile, all other protests must generally be filed within ten calendar days of when the protestor knew or should have known about the basis of the protest. However, there is a debriefing exception to these general timeliness rules, which ensures contractors have an opportunity to understand the basis for their loss before deciding to protest. Under 4 C.F.R. § 21.2, this exception applies to procurements involving competitive proposals under which a debriefing is required and requested. The debriefing exception allows protestors to bring protests within 10 days of the required and requested debrief, therefore potentially extending the timeline under which a protest concerning competitive proposals may be brought at the GAO. The term “competitive proposals” is a term of art in government contracts parlance and is not expressly defined by statute or regulation. Competitive proposals involve negotiated procurement procedures that contemplate the creation of a competitive range of offerors before awarding the contract to the offeror that presents the most advantageous solution. Notably, the debriefing exception only applies to competitive proposals.

more
Expanded Protestor Standing for Potential Subcontractors under Percipient.jpg

Government agencies are required to acquire and use commercially available products and services to the maximum extent practicable. In the implementation of 10 U.S.C. § 3453, government agencies are required to ensure that prime and subcontractors at all levels incorporate commercially available products and services as components of items supplied to the government. Under the Tucker Act, 28 U.S.C. § 1491(b)(1), interested parties are permitted to file suit in the Court of Federal Claims (COFC) challenging (1) a solicitation issued by a federal agency, (2) an award or a proposed award of a contract, or (3) any alleged violation of statute or regulation in connection with a procurement or a proposed procurement. The Federal Acquisition Streamlining Act (FASA) of 1994 contains a “task order bar” that removes from Tucker Act coverage any protests in connection with the issuance or proposed issuance of task or delivery orders that are below the monetary threshold of $25M for defense procurements and $10M for non-defense procurements.

On June 7, 2024, in Percipient.AI v. U.S. (23-1970), the Court of Appeals for the Federal Circuit (CAFC) addressed the interplay of these statutes to carve out a new rule conferring standing upon manufacturers of commercially available products and services to bring a protest alleging harm to their direct economic interests due to the government’s violation of 10 U.S.C. § 3453 – when their product or service has a substantial chance of meeting the government’s needs, either partially or completely, and when they take care not to directly or indirectly challenge the solicitation, contract award, or proposed contract award. The decision may be of particular interest to commercial software manufacturers that produce software in emerging sectors that satisfy at least some of the government’s solicited requirements in large-value procurements. In Percipient.AI, the National Geospatial-Intelligence Agency (NGA) issued the “SAFFIRE” solicitation contemplating a single award Indefinite Delivery, Indefinite Quantity (IDIQ) contract to sustain and improve its processes for obtaining and storing visual intelligence data and integrating those capabilities with a form of user-facing artificial intelligence (AI) called computer vision (CV). The NGA simultaneously solicited Task Order 1 of the IDIQ, which, in pertinent part, directed the contractor to develop and deliver the CV suite of systems. While the protestor produced commercial software that could meet the government’s CV system requirements, it could not meet the storage component of the contract. Therefore, in reliance on the government’s and the eventual awardee’s anticipated compliance with 10 U.S.C. § 3453, the protestor chose not to bid for or protest the SAFFIRE solicitation or the eventual contract award to a large systems integrator.

more
Shutterstock_1788508130.jpg

The Government Accountability Office (GAO) has strict timeliness rules for submission of bid protests. Under these timeliness rules, post-award protests must typically be filed no later than 10 days after the basis of the protest is known or should have been known, except when the debriefing exception applies. The debriefing exception, which does not apply to federal supply schedule (FSS) procurements, requires unsuccessful offerors to file their protests within 10 days of a required and requested debriefing. In General Services Administration (GSA) FSS procurements conducted under Federal Acquisition Regulation (FAR) subpart 8.4, unsuccessful offerors are only entitled to a “brief explanation.” Due to the terms being somewhat similar, contractors may confuse the “brief explanation” contemplated under FAR subpart 8.4 with the required and requested “debriefing” of competitive proposals. Such confusion may prove problematic as it can cause an unsuccessful offeror to miss the 10-day deadline to file their post-award protest at the GAO.

In B-422881, a decision issued on September 12, 2024, the GAO dismissed such a protest as untimely, reminding the protestor of the distinction between a required and requested “debrief” and a “brief explanation” under FAR subpart 8.4. The Navy’s Military Sealift Command issued the relevant FSS Request for Quotation (RFQ) for lodging negotiation and management services, requiring vendors to provide multiple extended-stay studio rooms in Mobile, Alabama. The RFQ contemplated a lowest-priced technically acceptable (LPTA) award and required offerors to submit their quotations on or before August 8, 2024. The protestor was notified that its quotation was unsuccessful on August 13 via the GSA eBuy system. On August 16, the government provided the protestor with a “brief explanation,” as required under FAR subpart 8.4. In the brief explanation, the Navy advised the protestor that its quotation was evaluated as technically unacceptable and was therefore ineligible for award. The brief explanation also specifically noted that it was not a debrief.

more
Shutterstock_2307202485.jpg

During the solicitation phase of a procurement, the government may disseminate information regarding the solicitation to prospective offerors. If the information is in writing, signed by the contracting officer, and provided to all prospective offerors, it contains the essential elements of a solicitation amendment and may operate as such. Bid protest adjudicative forums have previously held that questions and answers (Q&As) published with amendments to a solicitation are considered part of the amended solicitation’s requirements. Thus, if the government’s answers clarify or even modify existing solicitation requirements, prospective offerors must submit proposals that conform to those updated requirements. Furthermore, whether an answer the government provides imposes a particular requirement is ultimately a matter of solicitation interpretation. To resolve matters of interpretation in bid protests, adjudicative forums such as the Government Accountability Office (GAO) look to determine the plain meaning of the solicitation language. Similarly, the principle of whole-text interpretation is also employed, and the interpretation that gives meaning to all the solicitation’s requirements without creating conflicts or rendering parts of the solicitation superfluous prevails as reasonable.

more

Timeliness and Scope of Requests for Reconsideration in GAO Protests

Bid Protest Insights | TILLIT LAW PLLC