Considerations Involving Key Personnel Qualifications Information

When evaluating key personnel qualifications, agencies generally assess the experience of the personnel proposed by the contractor against the requirements of the solicitation. Depending on the evaluation criteria, a proposal may be subject to downgraded ratings and even elimination if it fails to provide the necessary information demonstrating that the proposed key personnel possess the type and level of experience and qualifications required by the solicitation. Therefore, it is crucial that offerors include current, accurate, and responsive experience information in key personnel resumes and other relevant sections of their proposals. The evaluation of proposed key personnel qualifications is based on all information provided to the agency, sometimes including information not specifically stated in key personnel resumes. For instance, the government must consider any key personnel qualifications information received from the offeror during discussions. On the other hand, agencies are not required to consider information that an offeror fails to provide, even if evaluators have personal knowledge of the information through other sources. In this respect, the evaluation of key personnel qualifications differs from that of past performance information due to the inapplicability of the “too close at hand” principle, under which evaluators are required to consider certain past performance information personally known to them even if that information is not provided by the offeror in response to the solicitation.

In B-293102, a decision issued on February 2, 2004, the Government Accountability Office (GAO) sustained a protest, finding that the agency improperly assigned a weakness based on the omission of certification information from key personnel resumes when the protester had provided that information during discussions. The Department of Health and Human Services (HHS) issued the relevant request for proposals (RFP) for occupational health and ancillary staff services in the western United States. As relevant here, the RFP required the area nurse manager key positions to possess automatic external defibrillator (AED) and cardiopulmonary resuscitation (CPR) certifications. In evaluating the protester’s initial proposal, the agency found that resumes for the proposed key personnel did not mention AED or CPR certifications and later raised this issue with the protester during discussions. In response, the protester submitted a revised proposal, withdrew the resumes of the initially proposed individuals, and submitted resumes of five incumbent area nurse managers. Notably, although the protester’s new resumes also did not include the certification information, the protester informed the agency during discussions that the incumbent nurse managers held the required AED and CPR certifications. Nevertheless, the agency assigned the protester’s final proposal a significant weakness/deficiency in the key personnel evaluation factor, citing the resumes’ failure to demonstrate compliance with the AED/CPR certification requirements.

In the subsequent protest, the GAO observed that while the agency assigned a weakness to the protester’s proposal for omitting certification information from the area nurse manager key personnel resumes, it also assigned a strength for proposing all incumbent candidates for those key positions, noting that the proposed candidates met the RFP’s minimum education and experience requirements. Furthermore, during discussions, the protester informed the agency that the incumbent candidates it proposed for the area nurse manager key positions possessed the required AED and CPR certifications. Since the evaluation of proposed key personnel qualifications had to be based on all information provided to the agency, the certification information provided by the protester during discussions should have been considered, even if not expressly included in the resumes. Stated another way, the flaw in the protester’s key personnel resumes was an inconsequential matter of form that the agency should have waived. After finding that the agency’s unreasonable evaluation of the key personnel qualifications prejudiced the protester, the GAO sustained the protest.

Meanwhile, in B-416415; 416415.2, a decision issued on August 31, 2018, the GAO held that evaluators were not required to consider key personnel qualifications information that the protester failed to provide, even if that information was allegedly known to agency personnel, as the “too close at hand principle” did not apply to key personnel qualifications information. The Department of Commerce (DOC) issued the RFP for services supporting the nation’s environmental satellites. As relevant here, the agency assigned a weakness to the protester’s proposed key personnel resumes for failing to demonstrate leadership and communication skills. The protester argued that, although the submitted resumes did not reflect it, its proposed key personnel had demonstrated leadership and communication skills through presentations at conferences and workshops widely attended by agency personnel. The protester maintained that this information was too close at hand for the agency to ignore when evaluating the leadership and communication qualifications of its proposed key personnel. However, the GAO rejected this argument, reminding the protester that the agency based its evaluation of proposed key personnel qualifications only on the information the offeror furnished. In denying the protest, the GAO declined to extend the too close at hand principle applicable to certain past performance information to information relating to key personnel qualifications.

Key personnel qualifications can be a determining factor, especially in highly competitive procurements that require specialized skills and experience. The evaluation of the qualifications of an offeror’s proposed key personnel is based on the information provided to the agency. Therefore, contractors should strive to provide all necessary key personnel information in resumes and relevant sections of their proposals in accordance with the solicitation’s requirements. In addition to considering all key personnel information provided to them in the offerors’ proposals, procuring agencies must also consider any information received during discussions. However, agencies are not required to seek out missing key personnel qualifications information from external sources and can limit their evaluation to information received from the offeror. Even information already in possession of the agency need not necessarily be considered if not provided by the offeror in response to the solicitation. In this regard, the “too close at hand principle,” which has limited applicability to certain past performance information already known to the government, does not extend to information related to the solicitation’s technical requirements, including key personnel qualifications information.

This Federal Procurement Insight is provided as a general summary of the applicable law in the practice area and does not constitute legal advice. Contractors wishing to learn more are encouraged to consult the TILLIT LAW PLLC Client Portal or Contact Us to determine how the law would apply in a specific situation.

Related Insights

Insight 13 - Substack.jpg

Often used loosely in government contracts services parlance, the impermissible bait and switch of key personnel is prohibited for adversely impacting contract performance and integrity of the procurement system. Therefore, prospective contractors can file post-award bid protests, challenging the awardee’s impermissible bait and switch of key personnel provided they can meet specifically defined elements. In such protests, the protestor essentially alleges that the awardee made misrepresentations to the government during the acquisition process by proposing personnel that it had no reasonable basis to expect to perform on the contract. The protest is sustained if the government is found to have relied on the awardee's misrepresentations by favorably evaluating the awardee's proposal, materially impacting the overall evaluation in the process. However, not all situations involving a switch of personnel upon contract award are considered an impermissible bait and switch, partly because whether the personnel identified in an offeror’s proposal will perform on the subsequently awarded contract is generally a matter concerning contract performance. Notably, the Government Accountability Office (GAO), which is a legislative agency that performs a quasi-judicial bid protest function, does not review matters concerning contract performance. Therefore, the GAO will only review bid protests involving an impermissible bait and switch of key personnel when the protestor alleges that the awardee received an evaluation advantage by proposing personnel that it had no reasonable basis to expect to perform on the contract.

more
Shutterstock_2295886611-3.jpg

Past performance evaluations play an important role in determining the strength and viability of competing offerors’ proposals. It is generally within the procuring agency’s discretion to determine the scope of the past performance history to be considered during evaluation, provided all proposals are evaluated on the same basis and the evaluation is consistent with the terms of the solicitation. While procuring agencies are typically permitted to limit their evaluations to only consider past performance information submitted in response to the solicitation, under certain limited circumstances, outside information not submitted with the offerors’ proposals must also be considered. Under such circumstances, the procuring agency is required to consider outside information as part of its past performance evaluation when the information is determined to be “too close at hand” to require competing offerors to bear the inequities that would arise from the agency’s failure to obtain and consider the information. Notably, the “too close at hand” principle is narrowly interpreted and is only applied to information related to the offerors’ past performance.

In B-275554, the Government Accountability Office (GAO) sustained a bid protest challenging the procuring agency’s past performance evaluation by applying the “too close at hand” principle. In that procurement, the Department of Veterans Affairs (VA) intended to acquire a replacement telephone system for the VA Medical Center in Wilkes-Barre, Pennsylvania. In evaluating the protester’s past performance, the contracting officer (CO), as the source selection authority, identified two directly relevant past performance references but only considered one reference, as an agency official did not complete a required form with respect to the protester’s other past performance reference. Notably, the contract whose reference was not considered involved the same agency, the same CO, and virtually the same services as the solicitation at hand. Furthermore, the CO conducting the procurement not only had the first-hand knowledge of the prior contract but also described the protester’s performance as “exemplary” in a letter provided to the Small Business Administration (SBA) on an unrelated matter. In applying the “too close at hand” principle, the GAO sustained the protest and concluded that it was unreasonable for the CO not to consider the protester’s past performance information on the earlier contract under these circumstances.

more
Shutterstock_1746124490.jpg

In solicitations that require the submission of key personnel resumes, the resumes are considered a material solicitation requirement. Thus, offerors have a duty to notify the procuring agency if one or more of their proposed key personnel become unavailable to perform. The procuring agency may proceed in one of two ways once it receives notification of the unavailability of a key employee from an offeror. It can either evaluate the offeror’s proposal as submitted and reject the proposal as technically unacceptable for failing to meet a material requirement, or the agency may open discussions with all remaining offerors to permit proposal revisions. An offeror must notify the agency of a key employee’s unavailability even when the employee signs a letter of commitment before proposal submission but subsequently resigns or retires during the evaluation period. Alternatively, in addition to the letter of commitment, the offeror must be prepared to present evidence of the employee’s reaffirmation of availability or willingness to return to the offeror’s employment. In this regard, the primary consideration is whether the offeror has actual knowledge of the key employee’s unavailability because the duty to notify the agency is not triggered otherwise. Notably, despite the employee’s resignation or retirement, the Government Accountability Office (GAO) will not find an offeror to have actual knowledge of a key employee’s unavailability if the offeror can advance a credible basis to deny such actual knowledge.

more
shutterstock_2704634783.jpg

When submitting key personnel resumes and information with their proposals, offerors must have a reasonable basis to expect that the proposed personnel will perform on the subsequently awarded contract. In this connection, offerors often obtain signed letters of commitment from the individuals proposed as key personnel either independently or under express instructions of the solicitation. For highly specialized positions, sought-after individuals may sometimes provide letters of commitment to multiple offerors. When one or more letters of commitment by the same individual also contain exclusivity language, disappointed offerors may challenge the award by alleging that the awardee misrepresented the key individual’s availability to perform on its contract. The Government Accountability Office (GAO) will typically deny such protests as long as the awardee had a reasonable basis to represent the availability of the personnel before proposal submission and there is no countervailing evidence suggesting that the individual revoked or rescinded his commitment to the awardee. As for the exclusivity language appearing in the protester’s letters of commitment signed by the same key individual as in the awardee’s proposal, the GAO treats this issue akin to a potential violation of a non-compete agreement. Accordingly, arguments raising this issue are rejected as concerning a private dispute between the protester and the awardee, not involving any government action. At the same time, offerors are not permitted to include information of key personnel in their proposals if they have knowledge that those individuals do not intend to join them.